Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Trans Mountain Pipeline ULC
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
TMX Spread 5A - Assess field implementation of the environmental protection plan and association resource specific plans for ongoing construction activities; verify mitigation measures at watercourse crossings, adequate erosion and sediment control measures, sites of indigenous significance, and hydrostatic testing sites.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - Field Information/Documentation Requests
Date & time of visit: 2022-11-21 10:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
Over the course of the inspection documentation was requested: Opening Meeting requests 21 Nov 2022
Compliance tool used: No compliance tool used
Observation 2 - General Observations
Date & time of visit: 2023-11-16 16:00
Discipline: Socio-Economic
Heritage Resource DlRf-24 TMEP representatives stated:
Observation 3 - Watercourse Crossings
KP 976+600 Coldwater #3 BC-570 TMEP representatives stated:
Observation 4 - Coldwater West Alternative Route
Observation 5 - NNC #1 Preparedness for Commencing Instream Work
Date & time of visit: 2022-11-22 15:00
On 22 November 2022, TMEP personnel informed the inspection team that the watercourse crossing at Clapperton Creek (BC-482 KP 912.58) would not be completed because one of the sections of concrete coating failed the final cure test. The watercourse crossing crew had already prepared the banks, installed the isolation, and conducted multiple passes of fish salvage over two days for most of the crossing area. Instream excavation had not yet occurred. A meeting was held with the TMEP Construction Manager the next morning and he indicated they would not be completing the crossing until the pipe, or a new concrete coated pipe was confirmed to meet all concrete coating test requirements (design standards) which might take up to a month. He stated the isolation would be pulled and the banks of the watercourse would be restored. On the TMEP Isolated Watercourse Crossing -Phased Checklist, Section 8 states “Pipe section has been welded and coated, with appropriate testing and anti-buoyancy as required to ensure no delays with the installation of the crossing”. This section was checked off as complete on November 19 2022, however, as noted above, the pipe (concrete coating) did not meet the design standards.
Compliance tool used: Notice of Non-compliance (NNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Provide the following:
Due date: 2023-02-08
Date closed: 2023-03-22 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 6 - NNC #2 Water Quality Monitoring Data
Date & time of visit: 2023-01-12 13:00
CER IO reviewed the Resource Specialist Daily Environmental Inspection Reports for 21 and 22 November 2022 at Clapperton Creek BC-482 and the water quality monitoring data collected during the attempted crossing in November 2022 as well as the actual crossing completed in December 2022. The CER IO determined manual turbidity readings were not completed as per the TMEP Water Quality Monitoring and Fish Salvage Plan for the attempted crossing or the actual crossing. On 12 January 2023, CER IO met with TMEP representatives to discuss these findings and corrective actions for future watercourse crossings on the project.
Provide the corrective actions that will be completed for future water quality monitoring during watercourse crossings as per the Water Quality Monitoring and Fish Salvage Plan and provide confirmation Resource Specialists understand these requirements.
Observation 7 - Indigenous Monitor Observation
Date & time of visit: 2023-01-16 15:19
Discipline: Indigenous Monitoring
Inspection 22/11/2022 Incursion Site Note: IR request will be made for timeline of site plans. KP 956.050 where mechanical work was being done (Welding) Note: Question raised for refuelling less than 100ft from water course KP 955.300 where back filling was happening Note: Question raised for Steep Slope plan and other information regarding Steep Slope KP 976.000 Water Course Crossing 3 Note: Question raised on the process. Site had concerns prior to visit. Inspection 23/11/2022 KP 912.620 Water Course Crossing Note: Question raised involving the workers and contractors in regards to what the time frame is for them to be there. Questions on what other water course work permits are required. KP 806.600 Hydro Release Site Note: Happened previously, questions raised on the reclamation process. Indigenous Monitor Concerns and Observations IM was impressed with the dam and pump systems set up to keep water quantity flowing. Additionally a plan was made on how TMEP was going to build the banks back and what mitigation’s will be made. Inspection 24/11/2022 AK 2 Steep Slope Note: Question was raised on Steep Slope plan and work order of surrounding Archaeological sites AK 3 Steep Slope, WTP, Amphibian Crossing, Ant Colony Salvage Note: Questions raised on the boundary near the WTP, Maintenance of the Amphibian Crossing and the reclamation of the Ant Colonies. Note: Time frame lost, multiple other sites were inspected along the alternate route where work was occurring. Majority of the sites visited this day all had Steep Slopes. Indigenous Monitor Concerns and Observations IM was impressed with identification and marking of WTPs, TMEP had mentioned they were doing a 1:1 ratio of Tree Modification for Williamson Sapsucker Wildlife Tree. IM was also impressed with the plan in relation to Ant Colony Reclamation process.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program