Compliance Verification Activity Report: CV1920-221 - Trans-Northern Pipelines Inc.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1920-221
Start date: 2019-04-30
End date: 2019-05-03

Team:

Regulated company: Trans-Northern Pipelines Inc.

Operating company: Trans-Northern Pipelines Inc.

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

This field inspection was carried out to inspect TNPI's Mainline in its Operational state, including environmental focused inspection of a number of pump stations, meter stations, integrity digs, and Rights of Way (across a variety of land use types). On-going Integrity digs as well as recently reclaimed ones (2016-2018) were inspected to assess reclamation activity as well.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - Aboveground Facilities IR #1, #2 and #3

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Meter Stations, pump/booster stations and valve sites were inspected at a number of locations listed below between Tuesday 29 April and Friday 3 May. These facilities spanned the TNPI Main Line, the Toronto Airport Lateral and the Nanticoke Lateral pipelines:

Farrans Point Meter Station
Gananoque River crossing Valve
Aragon Road Valve
Perth Road Valve
Kingston Pump (Booster) Station
Kingston Meter Station
Belleville Meter Station
Toronto Airport Meter Station (and Elmbank Maintenance Station)
Nanticoke Pump (Lifting) Station

Discussion and inspection of the following were carried out at some or all locations as noted below:

  • Weed Management: Management of vegetation growing on the sites and herbicide application at all fenced stations were discussed. Specifically, the IO inquired as to whether the potential hazard of herbicide application in sloped areas (offsite runoff) has been appropriately assessed, documented and controlled by TNPI at their stations at which vegetation control is required. TNPI provided documentation upon request (after the inspection) indicating the permitted contractor hired to apply herbicide, as well as product information and permits provided by the Ministry of the Environment, Conservation and Parks accepting the specific herbicide product. NEB staff also reviewed the procedure for herbicide application provided by the contractor. No issues noted with the documentation provided, but more information is requested in IR #1.
  • Groundwater Monitoring Programs: At each station visited, NEB staff inquired as to whether or not a network of groundwater monitoring wells was present. Farrans Point Station had two separate groundwater monitoring programs associated with two distinct contaminated sites, while no other stations inspected along the Mainline had any wells installed. A discussion ensued about the concept of potentially contaminated groundwater below stations which have a relatively high likelihood to have had releases in the past, and when it is appropriate and to identify and assess that risk to determine if any mitigation is necessary. See IR #2.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Company action required:

IR #1 Herbicide Hazard Assessment
As outlined in the Aboveground Facilities Observation, an assessment of the potential hazard posed by off-site herbicide run-off is requested. Please provide documentation that this potential hazard has been assessed, documented and controlled by 19 July 2019.


IR #2 Groundwater Hazard Assessment
A common thread of discussion across the station visits was that there is little site specific information available on the potential hazard that contaminated groundwater may pose if it migrates off-site. NEB Staff are of the view that potentially contaminated groundwater under the Toronto Airport station (which has been in operation for decades without a groundwater monitoring program) has not been properly identified, assessed and mitigated. Please provide documentation that TNPI has identified the potential risk, assessed the risk and put into place any mitigation measures needed to manage the risk of contaminated groundwater, sourced from the Toronto Airport Station and its historical and current day activities, moving offsite to surrounding receptors. Depending on the framework of TNPIs response, this may include a plan and timeline of activity/work to be conducted to put into place assessment and/or mitigation measures. Please provide a response by 19 July 2019.


IR #3 Nanticoke Station Base of Valve
At the Nanticoke Station, the IO observed a crumbling base support under the thermal relief valve. Section 1.2 of TNPIs Safety Manual states that "Proper design and maintenance of facilities, equipment and tools are fundamental to achieving safe work place".
Provide documentation illustrating TNPIs plan to assess and mitigate the potential hazard this crumbling foundation poses. Please include a work plan and timeline if applicable, with a response by 19 July 2019. Section 1.2

 

Due date: 2019-07-19

Date closed: 2019-07-23
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Referred to enforcement

Compliance achieved: No

Observation 2 - CNC #1 Soiled gravel at Farrans Point

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Stained/soiled gravel was observed at three locations at the Farrans Point Station. The IO observed stained gravel with hydrocarbon odour in two locations and an oily patch of gravel in the third location. The group discussed TNPIs procedure when spills or drips are encountered, and NEB staff reviewed the procedure document. Photographic evidence was provided during the inspection that the soiled gravel areas had been cleaned up. This is considered a corrected non compliance and no other issues are outstanding.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TNPI will clean up the areas of soiled gravel and send photographic evidence that this has been completed.

Due date: 2019-05-03

Date closed: 2019-06-14
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 3 - NNC #1 Surface Water Management and Drainage

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

The swale system of surface water management at the Belleville Pump Station was observed to be cracked (see photos). At the time of the inspection, it was raining which allowed for visual confirmation that water was pooling and draining from the swale system through cracks and lowlying areas of the site rather than being directed towards the oil/water separator

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

1. TNPI will develop and implement a plan to address the broken swale system at Belleville Pump station.
The plan will include:
a) An interim fix to mitigate environmental risks until work is completed, to be implemented as soon as practicable upon receipt of this NNC.
b) A schematic diagram and discussion of what the system will look like once fixed, whether repaired or redesigned.
c) A work order outlining the maintenance activity and proposed dates during which the work has been scheduled to be conducted and completed.
d) Discussion of how the new or repaired system will be tested to confirm its efficacy including confirmation that slopes and grades effectively direct water towards the oil water separator. TNPI will provide a response with test results including photos once works are completed.

 

Due date: 2019-07-19

Date closed: 2019-09-11
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Referred to enforcement

Compliance achieved: No

Observation 4 - NNC #2 Hazardous Materials Storage

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Hazardous Materials and Waste Storage/Management:  Improper storage of hazardous materials and waste was observed at the Belleville pump station, the Toronto Airport station, Elmbank, and the Nanticoke lifting station. Specific issues observed were a lack of secondary containment, hazardous chemicals improperly stored in flammable material cabinets, as well as improperly labelled bottles . 

The IO observed a building which TNPI indicated had historically been used for sampling the jet fuel at the Toronto Airport station, referred to as the ‘sample shack’. NEB staff note that the space was orderly and hazardous materials containers were properly labelled and stored. However, the ‘sample shack’ smelled strongly of jet fuel. In addition, jetfuel staining was observed outside of the building on its concrete foundation. The staining led to the seam between the building walls and the foundation which IOs note does not provide any means of containment for leaks and spills during hazardous product handling within the building. IOs noted evidence of hydrocarbon contamination saturated within the wood cabinetry and flooring of the building.

 
 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

1. Provide photographic evidence that appropriate secondary containment has been achieved at each location where the issue was identified during the inspection, including:
a) Hazardous chemicals in the shed at the Belleville pump station
b) Hazardous materials including 20L lube oil pails and red drip pails in the shed at the Toronto Airport station
c) Paint cans and spray paint left outside in the 'boneyard' at the Toronto Airport station
d) Hazardous chemicals in the shed at the Elmbank facility
e) Hazardous chemicals in the shed at the Nanticoke pump station

2. Provide photographic evidence that improperly labeled containers in the flammable cabilet at the Elmbank facility have been appropriately labeled as per WHMIS guidance.

  3. Generate or amend existing TNPI Procedures to appropriately assess and control hazards related to waste management and hazardous storage:
a) Develop, implement and provide a plan to IOs which describes control measures to be installed and timeline for installation.
b) Provide TNPI's procedure and/or work instructions which addresses the expectations to staff and contractors for secondary containment,  storage of hazardous products, and hazard assessment for potentially dangerous product.

4. Re-assess the 'sample shack' at the Toronto Airport in the context of the risk it may pose, by considering the hazards and potential mitigations that might be appropriate with current-day best practices to protect the environmental and the people coming into contact with the shack:
a) Provide the NEB with a record of this exercise including
            i) identification of the hazards;
            ii) mitigations planned for each hazard; and
            iii) a timeline and workplan associated with each mitigation strategy.
 

Due date: 2019-08-30

Date closed: 2019-09-06
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - NNC #3 Housekeeping/Waste Management

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Across the stations visited, waste management and general housekeeping issues were observed as a theme, with the exception of the Kingston Pump Station which was notably clean and tidy. Non-compliances observed included:

-Discarded nitrile gloves around the Farrans Point Contaminated Site monitoring wells (along the right of way outside of the station fence);
-Paint cans and spray paint bottles sitting out in the weather, cans rusting and causing potential for leaks at Elmbank station. These need to be disposed of, placed in secondary containment and/or brought under cover and away from the elements;
-Empty barrels with no anticipated use should be disposed of around the Toronto Airport Station (near the sample shack) and at Elmbank;
-Used sections of pipe and discarded pigs laying outside exposed to the elements (rusting and corrosion) and potentially leaking residual contamination.

 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TNPI will provide a response including photographic evidence that all instances of non-compliance have been cleaned-up. The response will address the following:
     a) Discarded nitrile gloves around the Farrans Point Contaminated Site monitoring wells (along the right of way outside of the station fence);
     b) Paint cans and spray paint bottles sitting out in the weather, rusting and causing potential for leaks at Elmbank. These need to be disposed of, placed in secondary containment and/or brought under cover and away from the elements;
     c) Empty barrels with no anticipated use should be disposed of around the Toronto Airport Station (near the sample shack) and at Elmbank;
      d) Used sections of pipe and discarded pigs laying outside exposed to the elements (rusting and corrosion) and potentially leaking residual hydrocarbons to the surrounding environment at Toronto Airport station, Elmbank and Nanticoke;
      f) Confirm the grey pump trailer sitting outside near the sheds at Elmbank (beside which a sheen was observed on the wet ground) is not leaking. If maintenance is required, maintenance actions taken will be described.

Due date: 2019-07-19

Date closed: 2019-07-17
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 6 - CNC #2 Housekeeping and Waste at Elmbank

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

The disposal area at Elmbank consisting of a heaped container of recycleable metal, pails, garbage, open pails with soiled absorbent rags, etc. 

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Clean up the area, properly dispose of metal recyling.

Due date: 2019-07-19

Date closed: 2019-05-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 7 - Integrity Digs

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Eight integrity digs were inspected; four active digs and four previously-reclaimed digs:

 

Compliance tool used: No compliance tool used

Observation 8 - IR #4 Environmental Inspectors

Date & time of visit: 2019-05-03 11:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Across all four active integrity dig locations, NEB Inspectors determined in conversation that the Inspector on each site was tasked with oversight of health, safety, integrity, and the environment. In addition, some Inspectors were tasked with more than one integrity dig site at a time, depending on locations and critical tasks.  NEB Inspectors note that environmental deficiencies were observed, examples include:

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

1. As a means of identifying the expertise, training and knowledge that TNPIs Environmental Inspectors (EIs) have which deems them qualified to carry out the tasks related to environmental inspection, TNPI will provide:
        a) A list of the Environmental Inspectors employed by TNPI and all relevant environmental training each has received that deems them qualified
        b) TNPIs decision making framework and job requirements for choosing Environmental Inspectors - any relevant policies and documentation TNPI has in place
        c) Identify any gaps in the training and qualifications the staff listed in a) have to carry out the tasks of an Environmental Inspector.

2. Provide all Environmental-related reports generated by Environmental Inspectors at the Woodeden MP358.23 integrity dig and the NK24.87 Chippewa Rd integrity dig.





 

Due date: 2019-07-19

Date closed: 2019-07-24
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Referred to enforcement

Compliance achieved: No

Observation 9 - NNC #4 Bird Survey

Date & time of visit: 2019-05-02 14:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

During inspection of the integrity dig at MP358.23 at Woodeden, Mississauga, the IO inquired as to whether a bird survey had been conducted before construction commenced. At the time, TNPI staff were unable to provide a bird survey document and committed to looking into it to follow up at a later time. After the inspection (15 May and again 29 May) TNPI followed up over email (see saved documents for record of email) that site activities began on 8 April which was outside of the Primary Nesting Period (PNP) window. The PNP was estimated to range between approximately 10 April to 9 August, depending on the location and seasonal variations. The Environmental Protection Plan for the site, which was not provided to the IO to review while on site because there was confusion amongst staff about whether or not one existed, states that

“If construction is scheduled to occur during the breeding bird season (April 1 to August 31), a pre-construction survey will be completed by a qualified biologist for areas where vegetation clearing may be required to confirm the presence or absence of active nests.”

TNPI are of the position that "the EPP reference to the birding season was a generic statement and was not indicative of that site" (MP358.23). The start date of construction at the site was 8 April, and the PNP window began 10 April.  TNPI stipulates that the construction began 8 April, and the PNP window began 10 April, and thus they met the requirement of the PNP.

NEB Staff note that there is no mention of the PNP window in the site specific EPP prepared by Stantec (2018) as quoted above in italics. Staff also note that the inspection occurred on 2 May, within the PNP window, and the construction was still ongoing. Since the EPP states that construction occurring during the breeding bird season, 1 April to 31 August, necessitates a a pre-construction survey and TNPI did not conduct a survey for the construction which began on 8 April, the IO considers this as a non compliance to the site specific EPP. 

 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TNPI will:
a) Develop and or update its procedures and training to better account for requirements within their EPPs for construction, specifically related to requirements for bird surveys within the clearly identified breeding bird season window. TNPI will provide a response including its new and/or amended procedures.
b) Provide a response that includes discussion of what led to this non-compliance, as well as specific steps which will be taken to prevent future occurence including for construction activities scheduled to occur within the 2019 breeding bird season, including communication of this non-compliance and TNPI's corrective actions to its contractors conducting clearing or brushing activities on its O&M dig sites.
 

 

Due date: 2019-09-30

Date closed: 2019-10-07
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 10 - Right of Way

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

The Right of Way of the Mainline was inspected at a number of locations, as listed below, in order to assess compliance across various land uses and ecosystems:

Compliance tool used: No compliance tool used

Observation 11 - NNC #5 Signage

Date & time of visit: 2019-05-03 08:00

Discipline: Damage Prevention

Categories:

Facility:

Observations:

At the Grand River crossing where the Mainline crosses along the HONI easement, there was no signage observed along either shoreline of the river crossing. Although the IO is satisfied that there is no need for navigable water signage as discussed in the Right of Way Observation, general pipeline signage is required.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Company action required:

Provide photographic evidence that signage has been erected where the Mainline travels under the Grand River.

Due date: 2019-07-19

Date closed: 2019-07-17
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 12 - IR #5 Surface Water Management - Belleville Swale NNC

Date & time of visit: 2019-07-25 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

TNPI did not provide the information requested in the Company Action section to correct the Notice of Non-Compliance (NNC #1). TNPI's response indicated that they have carried out a preliminary assessment to implement the interim fix (1a), by the end of 2019 and acknowledged that the swale will need to be redesigned and replaced. Planning is anticipated to begin in 2019 and to be executed in 2020.

The NNC remains open, since TNPI's response did not address the questions asked.
 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide the following:

The interim fix for the swale system to properly direct surface water and potential spills to the oil water separator must be in place by 23 August. Provide photographic evidence and a schematic plan of the interim system by 23 August 2019.

Due date: 2019-08-23

Date closed: 2019-09-11
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Referred to enforcement

Compliance achieved: No

Observation 13 - NNC #6 Nanticoke Station Base of Valve

Date & time of visit: 2019-05-03 08:00

Discipline: Integrity Management

Categories:

Facility:

Observations:

The information requested in IR#3 regarding the crumbling base of a valve at the Nanticoke was not provided by the due date of 19 July 2019. Thus, the requested information and plan for assessing the hazard and mitigation plan is reiterated here as a notice of non compliance.

At the Nanticoke Station, the IO observed a crumbling base support under the thermal relief valve. Section 1.2 of TNPIs Safety Manual states that "Proper design and maintenance of facilities, equipment and tools are fundamental to achieving safe work place".
Provide documentation illustrating TNPIs plan to assess and mitigate the potential hazard this crumbling foundation poses. Please include a work plan and timeline if applicable.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Below is the initial information requested, reiterated here as an NNC rather than an IR:

Provide documentation illustrating TNPIs plan to assess and mitigate the potential hazard this crumbling foundation poses. Please include a work plan and timeline if applicable.

Provide a response by 20 September 2019.

Due date: 2019-09-20

Date closed: 2019-09-27
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 14 - NNC #7 Environmental Inspectors

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

 In IR #4, TNPI was unable to produce documentation of assessment of their environmental inspectors' training and competencyto fulfill their duties safely, securely and in a manner to protect the environment (OPR 6.5 (1) (k), thus this item has been elevated to a notice of non compliance.



 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Identify and address any gaps in the training and qualifications the environmental inspectors' have to carry out their duties safely, securely, and to protect the environment.

Submit a revised job requirement list of the Site Supervisor which accounts for the deficiencies identified in the above exercise.  
 

Due date: 2019-09-30

Date closed: 2019-10-07
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 15 - IR #2b-Follow up to Groundwater Hazard Assessment

Date & time of visit: 2019-04-30 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Associated with IR #2 regarding assessing potentially contaminated groundwater at the Toronto Airport as a hazard, TNPI did not submit documentation of the hazard assessment requested though it is understood that the Phase I will be complete by the end of August 2019. 

 

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Submit the Phase I report generated to assess groundwater contamination hazards at the Toronto Airport by 30 August 2019. Ensure that the Phase I report outlines the next steps TNPI will take to assess, manage and mitigate potentially impacted groundwater with time lines.

 

Due date: 2019-08-30

Date closed: 2019-09-11
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 16 - Inspection Officer Order, Belleville Swale Surface Water Management

Date & time of visit: 2019-08-28 08:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

On 30 April 2019 the IO conducted an inspection of the TNPI Belleville pump station and made the following observations as noted in the inspection report for activity CV1920-221:
The swale system of surface water management at the Belleville Pump Station was observed to be cracked. At the time of the inspection, it was raining which allowed for visual confirmation that water was pooling and draining from the swale system through cracks and low lying areas of the site rather than being directed towards the oil/water separator
The IO issued a Notice of Non-Compliance (NNC) which required TNPI to take the following actions by 19 July 2019:

  1. TNPI will develop and implement a plan to address the broken swale system at Belleville Pump station.
    The plan will include:
    a) An interim fix to mitigate environmental risks until work is completed, to be implemented as soon as practicable upon receipt of this NNC.
    b) A schematic diagram and discussion of what the system will look like once fixed, whether repaired or redesigned.
    c) A work order outlining the maintenance activity and proposed dates during which the work has been scheduled to be conducted and completed.
    d) Discussion of how the new or repaired system will be tested to confirm its efficacy including confirmation that slopes and grades effectively direct water towards the oil water separator. TNPI will provide a response with test results including photos once works are completed.
 
The IO analyzed the response provided and determined that TNPI did not provide the information requested to satisfy the Notice of Non-Compliance. TNPI's response indicated that it had carried out a preliminary assessment to implement the interim fix (1a) by the end of 2019. The IO determined that additional justification is needed to elucidate why the interim fix cannot be completed for up to 6 months from the date of the NNC.

Further, the IO noted that a response to NNC sections 1b, 1c, and 1d was not provided, other than acknowledgement that the swale will need to be redesigned and replaced. TNPI indicated that it anticipated to 'begin project work' in 2019 and that work had a target to be executed in 2020. No schematic diagram or description of the new swale system (1b), no work order with outlined scope (1c), nor a discussion of quality control for the new system (1d) were provided in the response. Thus, this NNC remains open and compliance has not yet been achieved.

On 25 July 2019 the IO issued an Information Request (IR#5) in follow up on this outstanding NNC. The IR required the following information be provided:

The interim fix for the swale system to properly direct surface water and potential spills to the oil water separator must be in place by 23 August. Provide photographic evidence and a schematic plan of the interim system by 23 August 2019.

On 23 August 2019 TNPI provided a response indicating that the interim fix required to mitigate environmental risks was still not in place. TNPI provided the following rationale for not initiating this work:

TNPI is providing the following rationale regarding the reason for not initiating the “interim repair” to the Belleville Swale by August 23, 2017. TNPI provided the NEB with the description of the interim repair and a timeline for the swale repair on July 19th. The interim mitigation is “to fill the cracks and jack up the swale to have proper slopes” by end of 2019. TNPI set the dates for the work based on the preliminary engineering analysis and timeline required to complete the work allowing for contingencies i.e. contractor availability and weather delays. TNPI provided a tentative schedule of work for the interim repair, including various target dates, and indicated that it will be able to provide the NEB with photographic evidence on or before November 8th.
 

Compliance tool used: Inspection Officer Order (IOO)

Regulatory requirement:

Relevant section(s):

Company action required:

TNPI will implement an interim fix for the swale system at Belleville Pump Station to properly direct surface water and potential spills to the oil water separator. TNPI will provide photographic evidence of the completed interim mitigation as well as a schematic plan of the interim system by 11 September 2019.

 

Due date: 2019-09-11

Date closed: 2019-09-11
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program