Compliance Verification Activity Report: CV1920-280 - NOVA Gas Transmission Ltd.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1920-280
Start date: 2019-05-23
End date: 2019-05-23

Team:

Regulated company: NOVA Gas Transmission Ltd.

Operating company: TransCanada PipeLines Limited

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

Environmental operations inspection of NOVA Gas Transmission Ltd. (NGTL)'s Bear River Lateral Loop No. 2. The Bear River Lateral Loop No. 2 is a 9.8 km long NPS 10 diameter pipeline transporting sweet natural gas from the Valhalla Meter Station to the Bear River Meter Station in northwestern Alberta. The pipeline route is a loop adjacent to NGTL’s Bear River Lateral and Bear River Lateral Loop, and parallels the existing NGTL right-of-way for approximately 9.6 km (97.5%) of its length. The pipeline route crosses two unnamed Class D watercourses and two drainage crossings that lack defined bed and banks. Construction commenced in August 2011 and was completed in October 2011. The purpose of this inspection was to observe reclamation success as compared to the final post-construction monitoring report submitted for the project.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - General Observations

Date & time of visit: 2019-05-23 12:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

KP 9+870  Bear River Lateral Loop 2 Receiving Station

KP 9+800 - 9+000 Cleared Forest ROWKP 8+450 Landowner Property and Unnamed Drainage #2KP 7+300 Unnamed Drainage #1KP 6+400 Western Toad Habitat (Man Made Dugout)  KP 3+200 Highway CrossingKP 2+100 & KP 1+200 Unnamed Tributaries to Bear River
KP 0 Valhalla and Valhalla 2 Meter Station
   

Compliance tool used: No compliance tool used

Observation 2 - NNC - Missing Signage at Road Crossings and Watercourse Crossings

Date & time of visit: 2019-05-23 14:05

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Multiple instances of non-compliance were observed regarding inadequate displays of TransCanada signs at road crossings and watercourse crossings along a ROW corridor that contains three paralleling pipelines. All locations in question are required to have three signs on each side of a crossing, for a total of six signs at each crossing. The required number of signs was not met.

KP 2+300 Off Highway Road Crossing to Non-TransCanada Facility

KP 2+100 Unnamed Tributary #2KP 1+200 Unnamed Tributary #1KP 0+020 Valhalla Meter Station  

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TransCanada/NGTL is obligated to install the required number of warning signs at all road crossings and watercourse crossings in the multiple pipeline corridor. Three individual signs should be placed on each side of the crossings and positioned according to TransCanada's Pipeline Right of Way Procedures.

Photographic evidence is to be provided to the NEB upon completion.  

Due date: 2019-07-19

Date closed: 2019-08-01
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 3 - CNC - Waste Management at Valhalla Meter Station

Date & time of visit: 2019-05-23 15:11

Discipline: Environmental Protection

Categories:

Facility:

Observations:

KP 0+000 Valhalla and Valhalla 2 Meter Station

Note: Some waste items, including the used oil absorbant pad, have potentially migrated from an industrial facility operating beside the meter station as no waste items were observed on the inner side of the perimeter fence of the meter station. TransCanada Representatives stated they are responsible for any collecting and disposing of any refuse that has migrated onto their site.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

NGTL/ TransCanada is required to abide their waste management plan and operating procedures. The Valhalla Meter station's perimeter is to be cleaned and the collected refuse/debris dipsoed of in accordance with regulatory requirements. Photographic evidence of the area in question is also to be sumbitted for confirmation. 

Due date: 2019-05-31

Date closed: 2019-05-30
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 4 - IR#1 - Documentation

Date & time of visit: 2019-05-23 16:55

Discipline: Environmental Protection

Categories:

Facility:

Observations:

NEB Inspection Officers have requested the following documentation relating to the following observations:

1) Bear River Receipt Station


2) Road / Watercourse Crossings
3) ROW on Landowners Property (KP 2+300 - 3+200) 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

NGTL / TransCanada is required to supply NEB Inspection Officers with the following documentation:

1) Most recent herbicide application logs for the Bear River #2 Receipt Station.
2) Most recent aerial patrol logs (excluding the leak survey) and ground patrol logs for the ROW.
3) Landowner consultation records for SW 19-75-9 W6. 

 

Due date: 2019-06-28

Date closed: 2019-06-24
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - IR#2 - Log Deck on Parallel NGTL ROW

Date & time of visit: 2019-05-23 16:50

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Near KP 9 + 500, just down the south side of the right of way (ROW) from the Bear River Lateral Loop 2 Receipt Station, there is an old log deck with hundreds of decaying logs. The logs are grey, mottled in color (appear to be rotten) and are likely remnants from construction of an older pipeline in the same corridor; NGTL/ TransCanada representatives could not confirm the origin of the log deck.



 

 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

NGTL / TransCanada is required to inform NEB Inspection Officers of plans for removal of the log deck, if any, and a timeline for removal if removal of the logs are warranted.

Due date: 2019-06-28

Date closed: 2019-05-30
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program