Compliance Verification Activity Report: CV2223-106 - Trans Mountain Pipeline ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2223-106
Start date: 2022-09-21
End date: 2022-09-23

Team:

Regulated company: Trans Mountain Pipeline ULC

Operating company: Kinder Morgan Canada Inc

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

Inspection of TMEP Sumas Terminal Construction

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - INSPECTION REPORT

Date & time of visit: 2022-10-21 14:00

Discipline: Integrity Management

Categories:

Facility:

Observations:

Construction progress:
Pertaining to the site inspection, TMEP presented an overview of the construction progress (the primary contractor is Kiewit Ledcor Trans Mountain Partnership (KLTP) and TMEP with the role of oversight):


Transfer of custody and management of change from project to operations:
IOs discussed the process/procedure established by TMEP with respect to the transfer of custody from the project to operation. TMEP said that it is part of their Dry and Wet Transfer Commissioning and that operations personnel have already been involved at various stages of the project (a month before going “online”).
TMEP mentioned that operations personnel reviewed the installation design package before construction was started. Also, operations personnel did have a few minor requests for change during the construction to allow for better ergonomics (installation design such as the position of valves, etc.).

Site inspection:

Manifold (see pictures Manifold #1, #2 and #3) The installation (launchers/receivers) for the new line 2 will allow the line inside the terminal to be piggable like the existing ones. Also, TMEP said that the connection work of the new line 2 will comply with the requirements of the ASME IX code (TMEP confirmed that it is consistent with the welding procedure specification (WPS) of new line 2 spreads). IOs asked about the results of the Non-Destructive Examination (NDE) executed on the welded joints in the manifold. TMEP said that only one repair has been done (out of approximately 40 welds). The repair executed a week ago was due to a lack of penetration. The records of the repair NDE were provided by TMEP and the results of the x-ray interpretation were clearly indicating the lack of penetration (FW-101) and the results of the x-ray after the repair (FW-101R1) showed it was properly executed with no flaws.

Fire water building: Air quality monitoring system: (condition 44) Tank 100 construction site (see picture “Tank 100 #1”):
TMEP said that: Tank floor plates welding activities (see picture “Tank 100 Plate welding #1”)
Also, TMEP said that they were dealing with an NCR (#416) related to gaps between sand bedding (see picture “Sand bedding annular rings”) inside the tank ring beam and foundation and the sketch plates connected to the annular rings (see picture “NCR #416 Gap plates and sand Tank 100”). A request for interpretation (RFI) is in process to confirm the validity of the proposed solution.

Tanks’ shell welding:
X-ray will be done for the butt welds on the tank annular,
Every section underneath the shell will be X-rayed 100%.

Pipeline welding activities on new line to connect to Tank 100:
CER IOs inspected joint welding activities of line 2. The WPS used was the KE-068 (Facilities Welding) WPS and the consumables used were E6010 for the root pass and E8010-G hot pass / E8018-C3 fill & cap.
TMEP/the welders had paper copies of the WPS, WPDS, and the weld traveller form on hand. IOs reviewed a manual welding parameter sheet which contained only parameters for the root pass as the hot pass was currently in process.

CER IOs observed that the field welding procedure data sheet (WPDS) reflects effectively the WPS. Welders’ qualifications and certificates were also in conformance.
CER IOs noted that some pipelines stored next to the welding had numerous coating repair patches (see picture “Stored pipes with many patches”) and asked TMEP to follow up on this.

Stormwater management:
CER IOs asked if the drain valves were automatic. TMEP said that the valves to drain the water (if necessary) are operated manually, the main reason is that according to TMEP potential sheen on the water can only be detected visually.
Tanks 103 and 102 secondary containments are equipped with water level indicators. Once the water has flowed up to the terminal disposal valve, the valve can be opened only if there is less than 15 ppm of hydrocarbons detected in it (a detector is installed on this valve).
When water is on the roof of the tanks and needs to be drained, TMEP said that 3 verifications of the presence of contamination are done: before draining the roof, before opening the tank secondary containment drain valve and before opening the terminal disposal valve. For any water outside of the tank’s secondary containment, the water is discharged close to the manifold,
TMEP uses water treatment to treat muddy water.

Tank 104:
TMEP said that tank 104 , 102 and 100 are used as storage tanks and relief tanks. Therefore, they are equipped with a relief system including a bypass (heat traced) (see picture “Relief Tank system”).
Foam system:
The current foam system (see pictures Foam system #1, #2 and #3) is used only for tanks 104, 101, and 102 since they are currently active,
A new foam system with separate capacities will be used for tanks 100 and 103.

Review of documentation and records:
IOs verified Ganotec’s documents for the tank 100 construction (see picture “Ganotec documents”)

In Binder #3: Standard of acceptability API 650, CER IO checked: Also, CER IOs checked the WPS related to plate welding, (KIC-1 rev3) and found that the WPDS at the tank 100 construction site did not reflect the WPS (see picture “Tank 100 WPDS”) in the matter of minimum pre-heat temperatures: CER IOs discussed this Non Compliance with TMEP that whatever is the correct value for minimum preheat temperatures, the 2 documents must be aligned.
CER IOs also asked TMEP to provide records of the minimum temperature measurements, TMEP couldn’t provide them as it was not recorded. The reason for the minimum temperature not being recorded is that, or and the welding activities completed so far , the minimum temperature of 10 °C was accounted for instead of the 0 °C in the WPDS.

CER IOs checked the document “RT-GP-001-TMEP-REV-001” which indicates the General Radiographic Examination Procedure. In the document “Radiographic Examination Report” (see picture “Radiographic Examination Report”), it is reported in the table that the for the x-ray, the selected wire is B7. However, according to the procedure RT-GP-001-TMEP-REV-001, the wire B8 should have been considered instead (different range of wall thickness).
IOs requested TMEP to provide during the inspection further explanation about the wire selection for the x-ray performed on floor plates welding for Tank 100.  TMEP provided it as requested (see Closing meeting remarks).

Compliance tool used: No compliance tool used

Observation 2 - NNC: Tank 100 bottom plates welding WPS and WPDS not aligned

Date & time of visit: 2022-10-21 14:30

Discipline: Integrity Management

Categories:

Facility:

Observations:

CER IOs checked the WPS related to plate welding, (KIC-1 rev3) and found that the WPDS at the tank 100 construction site did not reflect the WPS (see picture “Tank 100 WPDS”) in the matter of minimum pre-heat temperatures:

CER IOs discussed this Non Compliance with TMEP and said to TMEP that whatever the correct value for minimum preheat temperatures, the 2 documents must be aligned.

Note: the
CER IOs also asked TMEP to provide records of the minimum temperature measurements, TMEP couldn’t provide them as it was not recorded. The reason for the minimum temperature not being recorded is that, or and the welding activities completed so far , the minimum temperature of 10 °C was accounted for instead of the 0 °C in the WPDS.

  

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TMEP shall confirm that:
- the minimum preheat temperature during welding activites of the Tank 100 bottom plates complies with applicable specifications (WPS or updated WPS) and,
- that its documentation (i.e., WPS and WPDS) will be aligned, including the reference of documents to be updated, date of completion and the list of the modifications.



 

Due date: 2022-11-04

Date closed: 2022-11-25
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program