Compliance verification activity type: Field Inspection
Team:
Regulated company: Westcoast Energy Inc.
Operating company: Enbridge Inc.
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Process Safety: T-South Compressor Stations 4A, 4B, and 6A: Assess implementation of identification, analysis and control of process hazards including established process hazard inventory. Assess completion of preventive maintenance activities on safety systems and safeguards per prescribed frequencies under CSA Z662 and company programs.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - IR 1 - Pre-inspection document request
Discipline: Safety Management
Categories:
Facility:
Observations:
CER Inspection Officers requests documentation in advance of the field inspection.
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
Process Hazard Identification, Analysis, and Control
Safety Critical Equipment
Due date: 2022-03-07
Date closed: 2022-03-15 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 2 - CS-4A, 4B, 6A general observations
Date & time of visit: 2022-03-17 14:00
PROCESS HAZARD IDENTIFICATION, ANALYSIS, CONTROL CER Inspectors (IOs) performed field safety inspections on 3 compressor stations involved in the T-South Reliability and Expansion Program (TSRE) over 3 days. TSRE construction was completed in 2021 and the new compressor units at each station were operating at the time of inspection. Prior to the inspection, IOs asked the company to demonstrate how process related hazards were identified, analyzed, and controlled for CS-4A, CS-4B, and CS-6A. Hazard Identification and Analysis In their response, the company stated process related hazards were identified and analyzed in accordance with their GTM IMS 2.1-Hazard Identification and Inventory Process and Hazard and Operability (HAZOP) Study Procedure, PSM-P0002-17. Section 3 of this procedure states its applicability to both major projects (such as TSRE) and operations and applies to Canadian assets inclusive of compressor stations and pipeline systems. The company provided copies of the HAZOP studies for CS-4A, CS-4B, and CS-6A completed May 7-11, 2018, July 24-26, 2018, and May 7-11, 2018 respectively. Each of these studied identified several risk-prioritized recommendations. Through document review and discussions with company staff, IOs verified the timing, team composition, and general methodology of the studies were performed in accordance with the company’s procedure. No items of non-compliance were identified. Hazard Control Section 9.5 of PSM-P0002-17 describes the company’s processes for following up on HAZOP recommendations. It states that a formal record and audit trail shall be kept for each recommendation which includes technical reasons for recommendation resolution. IOs selected 6 recommendations from CS-4A, 2 recommendations from CS-4B, and 5 recommendations from CS-6A to verify the company had addressed the recommendations in accordance with their procedure. Verification involved reviewing each of the signed HAZOP Action Sheets, discussions with company operational staff, and field verification were possible. No items of non-compliance were observed. Process Hazard Inventory IOs requested a copy of the hazard inventory for CS-4A, CS-4B, and CS-6A. An inventory was provided that included process related and non-process related hazards. The company stated new hazards, such as those identified by operations staff, are entered into a computerized system and tracked until resolution. PREVENTATIVE MAINTENANCE IOs requested and received from the company a list of safety critical equipment applicable to CS-4A, CS-4B, and CS-6A. IOs verified completion of preventative maintenance of selected equipment by reviewing maintenance records and through discussions with operations staff. Details of these verification activities can be found below in the station specific observations. IOs asked company operational staff to demonstrate they had access to written procedures for maintenance tasks such as fuel gas filter change, calibration of fixed gas detectors, and valve maintenance. In all cases, company staff demonstrated they had access to task specific written procedures. Additionally, IOs verified that station operators had access to red-lined as built drawings including P&IDs for each station. STATION SPECIFIC OBSERVATIONS Compressor 4A
Compliance tool used: No compliance tool used
Observation 3 - CNC 1 - Lube oil stored in CS-6A compressor building
Date & time of visit: 2022-03-17 11:45
CER Inspection Officer observed two barrels of lube oil stored in the unit 10 compressor building. When asked, company representative stated the 2 barrels represented a year's worth of supply.
Compliance tool used: Corrected Non-compliance (CNC)
Remove the lubricants from unit 10 compressor building beyond that which is required for everyday use and store in a noncombustible structure located a suitable distance from the compressor building.
Due date: 2022-03-17
Date closed: 2022-03-17 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program