Compliance verification activity type: Field Inspection
Team:
Regulated company: TransCanada Keystone Pipeline GP Ltd.
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Dig Inspection for Keystone
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Inspection Report
Date & time of visit: 2022-07-18 15:00
Discipline: Integrity Management
Categories:
Facility:
Observations:
Safe Excavation/Evaluation Pressure (SEP): TransCanada Keystone Pipeline GP Ltd. (TCK) supporting document: - Attachment 1- 2021 Safe Dig Pressure Tech Memo KS5 Additional Digs Rev 1.pdf CER inspector asked TCK to provide actual pressure within the line. This pressure is verified daily by the TCK supervisor after calling TCK OCC (Oil Control Center). During the inspection, the pressure was communicated to be 2773 kPa. In the Excavation procedure checklist (see IMG_0746.JPEG), the safe excavation pressures indicated were 8432 kPa (for GW 50540) and 8122 kPa (for GW 62000). Safety Management: - TCK's general supervisor presented its JSA and FLHA and checked the emergency response procedure (ERP) (a more recent one was in place at the time of inspection, TCK will provide the CER with this updated document). - The ditch areas had temporary fencing erected to control access - Excavation ingress/egress was via two temporary staircases - The excavation slope appeared to be within the requirements - The exposed pipe section appeared to be properly supported with timbers as required Specific to dig site GW50540: - CER inspector asked TCK to provide the actual Depth of Cover (DoC) for the daylighted pipeline. TCK said the minimum DoC was 1.4 m with a trench depth of 2.8 m. Emergency Procedures: TCK supporting documents: - Attachment 2 - E025686 GWD 50450 Emergency Response Plan.pdf - Attachment 3 - E025686 GWD 62000 Emergency Response Plan.pdf During the inspection, the ERP available at each dig site was an updated version of the above. TCK provided the updated documents on the 7th of July (see Attachments 6 and 7). TCK said that the ERPs are communicated to each contractor prior to the start of work and are readily accessible and contained in a hermetic red cylinder attached to each dig fence (see picture IMG_0740.jpeg) Right-of-way (ROW) Condition: From the adjacent roads, wood mats have been installed by TCK to facilitate access to the dig sites (see pictures IMG_0737.JPEG and TC_00515.JPG). At the start of the “mat path”, staff was instructed to spray decontaminant on their safety boots. Pipeline Identification: Signs indicating the presence of an oil pipeline were in place at each side of the road crossing next to dig sites (see pictures IMG_0749.JPEG and TC_00532.JPG). CER inspectors noted the presence of a parallel Enbridge oil pipeline (see pictures IMG_0743.JPEG and TC_00531.JPG). Warning signs on the mat paths were also visible (see picture IMG_0745.JPEG). Applicable Procedures and available documents on site: Upon the CER inspector's request, TCK's general supervisor presented several binders that are readily accessible to personnel working at the dig sites (see picture TC_00537.JPG). CER inspector verified the contents of the binder, and confirmed that the following documents were available:
Compliance tool used: No compliance tool used
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program