Compliance Verification Activity Report: CV1920-108 - Manitoba Hydro-Electric Board - Régie de l'hydro-électricité du Manitoba

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1920-108
Start date: 2019-10-21
End date: 2019-10-24

Team:

Regulated company: Manitoba Hydro-Electric Board - Régie de l'hydro-électricité du Manitoba

Operating company: Manitoba Hydro-Electric Board - Régie de l'hydro-électricité du Manitoba

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

Canada Energy Regulator (CER) Environmental Protection Program construction inspection of Manitoba Hydro’s Manitoba-Minnesota Transmission Project (MMTP or Project) near Winnipeg, MB. The Project consists of the construction of a 500 kV AC transmission line and upgrades to the Dorsey, Riel, and Glenboro converter stations. The transmission line work is divided into two sections: Section 1 is approximately 92 km long and runs from the Dorsey Converter Station northwest of Winnipeg to Tower #225, and Section 2 is approximately 121 km long and runs from Tower #226 to the USA border where it will connect with the Great Northern Transmission Line.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Observations (no outstanding follow-up required)

Observation 1 - MMTP Section 1

Date & time of visit: 2019-10-22 10:15

Discipline: Environmental Protection

Categories:

Facility:

Observations:

General

Dorsey Converter StationTower #2South Side of Assiniboine River CrossingTower #142Various Access Locations
Observed various temporary access roads and assembled foundations from the roadside due to very wet conditions. Rutting, admixing, and ponding was observed at each site, and was particularly severe at sites along the Red River floodway which is classified as industrial use. No working equipment was observed. Some wooden crates were observed near partly assembled towers. Company Representatives indicated that they would discuss this with the contractor to ensure that equipment, parts, and materials aren’t left behind before snowfall. IOs were satisfied that given current wet weather conditions, with no crew working, additional environmental damages are minimized.

Indigenous Engagement and Liaison Meeting
IOs met with Indigenous Compliance Monitors, Manitoba Hydro Community Liaisons as well as Environmental Inspectors for the Project. Discussions included roles and responsibilities, current wet weather conditions and adjustments made by the contractors for difficult working conditions. Company Representatives also explained MTTP’s Indigenous Advisory and Monitoring Committee (IAMC), including consultations with affected communities through Project planning, communities represented on the IAMC, and ongoing monitoring with Indigenous Compliance Monitors.

Compliance tool used: No compliance tool used

Observation 2 - MMTP Section 2

Date & time of visit: 2019-10-23 12:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Tower #481

Tower #480Tower #483Tower #484Tower #491Tower #496Tower #385/Fly Site #7Tower #351/Fly Site #6Towers #322-323Tower #310 Towers #302-306Tower #230Tower #255-256Tower #260

Compliance tool used: No compliance tool used

Observation 3 - Information Request (IR) #1 - Addressing Deficiencies/Non-Conformances

Date & time of visit: 2019-10-24 14:30

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Several deficiencies and non-conformances previously identified by Manitoba Hydro were observed throughout the inspection, including rutting observed adjacent to access matting in several areas, rutting observed adjacent to wetlands, and areas of rutting on dirt or field access trails.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide a response outlining how Manitoba Hydro will work with its prime contractor and sub-contractors to ensure that a process is in place to track, monitor, and correct identified deficiencies/non-conformances in a timely fashion (taking the changing seasons into consideration).

Due date: 2019-11-15

Date closed: 2019-11-18
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 4 - IR #2 - Perch Site Trees

Date & time of visit: 2019-10-24 14:30

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Manitoba Hydro was unable to demonstrate that it has measures in place to ensure the proper implementation of specific mitigation requiring retention of perch site trees in forested golden-winged warbler (GWW) habitat. CER Inspection Officers noted that perch site trees are to be located along the edge of the right-of-way. Company Representatives had indicated during the inspection that clearing along the edge of the RoW in GWW habitat had yet to occur.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide a response outlining how Manitoba Hydro will work with its prime contractor and sub-contractors to ensure that appropriate monitoring and oversight is in place when implementing the clearing prescription for perch site trees in GWW habitat.

Due date: 2019-11-15

Date closed: 2019-11-15
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - Corrected Non-Compliance (CNC) #1 - Soil Separation

Date & time of visit: 2019-10-22 11:20

Discipline: Environmental Protection

Categories:

Facility:

Observations:

At the excavation for a foundation at Tower #2, it was observed that subsoil from the casing hole was being stored directly on topsoil. CER Inspection Officers (IOs) confirmed that it was a contractor requirement to salvaged topsoil and stockpile it separately from subsoil to prevent loss and admixing. Company Representatives notified the contractor about the issue and provided a copy of this communication to the IOs.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide a copy of the associated communication from Manitoba Hydro to the contractor regarding the issue observed, as well as the associated corrective action submitted by the contractor.

Due date: 2019-10-24

Date closed: 2019-10-28
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 6 - CNC #2 - Incorrectly Felled Timber

Date & time of visit: 2019-10-23 16:35

Discipline: Environmental Protection

Categories:

Facility:

Observations:

In a work area in the vicinity of Tower #304 within golden-winged warbler habitat, where mulching operations had not yet been completed to clear the tower footprint, CER Inspection Officers (IOs) observed that trees had been felled into remaining standing timber around the area’s perimeter. During the inspection, Company Representatives issued a corrective notice to the primary contractor which was verified by IOs.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Manitoba Hydro shall provide IOs with a copy of the correction notice that was given to the primary contractor regarding the issue observed.

Due date: 2019-10-24

Date closed: 2019-10-24
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 7 - CNC #3 - Rutting and Admixing on RoW Access Trails

Date & time of visit: 2019-10-23 17:25

Discipline: Environmental Protection

Categories:

Facility:

Observations:

CER Inspection Officers and Company Representatives identified rutting and early stages of admixing along a RoW access trail between Towers #304 and 305. During the inspection, Company Representatives issued a corrective notice for the issue to the primary contractor.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Manitoba Hydro shall provide IOs with a copy of the correction notice that was given to the primary contractor regarding the issue observed.
 

Due date: 2019-10-24

Date closed: 2019-10-24
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 8 - Notice of Non-Compliance #1 - Eastern Arm of Pine Creek Access Crossing

Date & time of visit: 2019-10-23 13:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) observed inadequate temporary access measures in place where an existing dirt road being utilized for access to the southernmost towers (#494-496) of Section 2 crosses the eastern arm of Pine Creek (LSD SW-4-1-12-E) along the U.S. border. Under current water flow conditions (at the time of inspection), access matting used for the temporary crossing was impeding natural stream flows which may lead to detrimental effects to the environment, including fish and fish habitat.

Company Representatives and the IOs discussed that the temporary crossing would be removed in a manner that minimizes potential disturbance to bed and banks of the watercourse and/or fish and fish habitat as soon as reasonably practicable, and once the current wet weather conditions had sufficiently improved. It would then be replaced by an appropriate temporary or permanent crossing that meets the applicable federal and provincial requirements. It was also discussed that this work would be conducted under the guidance of a qualified person(s).

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Manitoba Hydro shall provide the following information to IOs as soon as available but no later than 15 December 2019:

  1. A response outlining the methods or techniques utilized for the removal of the existing temporary crossing, as well as a copy of environmental inspection report(s) from the Environmental Inspector(s) and/or Monitor(s) having monitored that activity.
  2. Upon ensuring that a qualified person(s) has assessed the site and determined an appropriate temporary crossing method (i.e. Bailey bridge, clear span bridge, etc.), provide a response outlining the proposed replacement access crossing as well as the intended installation completion date.
  3. A copy of environmental inspection report(s) from the Environmental Inspector(s) and/or Monitor(s) having monitored the replacement crossing installation activities.

Due date: 2019-12-15

Date closed: 2020-02-21
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Full relief granted

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program