Compliance Verification Activity Report: CV2122-095 - Trans Mountain Pipeline ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2122-095
Start date: 2021-08-05
End date: 2021-08-06

Team:

Regulated company: Trans Mountain Pipeline ULC

Operating company: Kinder Morgan Canada Inc

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

TMX Spread 5B - Assess field implementation of construction safety manual and project specific safety plans for ongoing construction activities; company oversight of contractors - training & competence, monitoring, supervision and accountability; assess execution of work per applicable procedures and documented work practices. Verify compliance with condition 73 filings including the Ohamil camp traffic management plan filed with the CER in October 2020.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Observations (no outstanding follow-up required)

Observation 1 - Information Request (IR) -1

Discipline: Safety Management

Categories:

Facility:

Observations:

Information Request (IR) -1 
- Spread 5B Contractors Project Hazard Assessment

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

  1. File to the CER for review - the latest applicable version of the contractors (Kiewit+Bonatti) Spread 5B pipeline construction, Project Hazard Assessment. (Also known as CHRR - Contractors Hazard Risk Registry)
  2. Have on hand for review at the Inspection Opening Meeting for review or use, the Unified Hazard Risk Registry (UHRR)

Due date: 2021-08-02

Date closed: 2021-08-03
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 2 - General Observations - Spread 5B

Date & time of visit: 2021-08-05 11:00

Discipline: Safety Management

Categories:

Facility:

Observations:

General Observations - Spread 5B 

Compliance tool used: No compliance tool used

Observation 3 - Blasting Work Process

Date & time of visit: 2021-08-05 11:00

Discipline: Safety Management

Categories:

Facility:

Observations:

Blasting Task - Road 5/ (KP1003 + 350)

Compliance tool used: No compliance tool used

Observation 4 - Mountain Crossing 1 and Laidlaw Bluffs

Discipline: Safety Management

Categories:

Facility:

Observations:

Laidlaw Bluffs (LLB) KP 1060+050 to KP 1061+250

Mountain Crossing 1 (MC 1) KP 1049+050 to KP 1050+350Popkum Construction Yard

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

At the conclusion of inspection activities on August 5th, CER Inspection Officers asked TMEP to provide an answer to the following question during the closing meeting on August 6th. 

Demonstrate to CER Inspection Officers (IOs):

  1. Work activities including trench excavation and back filling on MC1 and LLB worksites are not subject to the Certificate of Public Convenience and Necessity OC-065, or
  2. How TMEP is taking all reasonable steps to ensure that construction activities are conducted in accordance with the condition 64a and 64b filings (HSMP and PSSP), specifically:
    1. evidence that the construction safety manuals (CSMs) being used by the MC1 and LLB contractors met the requirements of the TMEP HSMP/PSSP,
    2. safety oversight was performed in accordance with the HSMP (field safety inspections, daily reports)
    3. incidents and near misses were managed in accordance with the HSMP, including a copy of the TMEP CSM-001 form related to the near miss communicated to the IO on August 5th).
The closing meeting was rescheduled from August 5th to August 6th to allow TMEP to gather the requested information.

Due date: 2021-08-06

Date closed: 2021-08-06
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - IOO DRP-002-2021 (AMENDED)

Date & time of visit: 2021-08-06 17:25

Discipline: Safety Management

Categories:

Facility:

Observations:

Note: Mountain Crossing 2 (MC2) and Laidlaw Bluffs (LLB) refer to the same location and are used interchangeably.

IOO DRP-002-2021 (AMENDED) - RELEVANT FACTS
 

  1. On 5 August 2021 CER Inspection Officer No. 2927 (IO) learned through interviews and document review that TMEP construction activities were occurring outside of and not in adherence to project Certificate OC-065 on worksites referred to as Mountain Crossing 1 (MC1) and Mountain Crossing 2 (MC2).
    1. Trenching and backfilling activities had been performed on MC1 and MC2 by two contractors who were not operating under the construction safety manuals filed by Trans Mountain with the CER, specifically:
      1. Health and Safety Management Plan July 2020 CER File: OF-Fac-Oil-T260-2013-03 61 (HSMP), and
      2. Spread 5B, Macro Project Specific Safety Plan (Rev. 3) – Doc. #01-13283-S5B-HS-PLN-0002 (PSSP). 
  2. Trans Mountain was unable to demonstrate that construction activities authorized by Certificate OC-065 (construction activities) on the MC1 and MC2 work sites have been inspected to ensure that they meet the requirements of the HSMP and PSSP.
    1. When asked by the IO, TMEP Spread 5B field safety inspectors stated they do not conduct oversight of MC1 and MC2 work sites.
    2. When asked by the IO, the TMEP Spread 5B Project Manager (PM) and Health and Safety Lead (HSE) stated they do not receive notification of all incidents or near-miss reports that occur on the MC1 and MC2 work sites.
    3. The TMEP Spread 5B daily work plans for August 4th and 5th provided to the IO by Trans Mountain for the purpose of planning the compliance verification activity with the CER did not fully encompass all scopes of work related to MC1 and MC2.
       
  3. Inspection officer order DRP-002-2021 was verbally issued to Bryan Weir, Project Manager, Trans Mountain Expansion Project Spread 5B 17:25MST 6 August 2021, and in writing on 7 August 2021.

Compliance tool used: Inspection Officer Order (IOO)

Regulatory requirement:

Relevant section(s):

Company action required:

IOO DRP-002-2021 (AMENDED) Specified Measure 1

1. Cease construction activities on MC1 and MC2 work sites that are not being performed in accordance with the HSMP and PSSP until it is demonstrated to the satisfaction of the IO that construction activities will be performed in accordance with all conditions of OC-065 including the HSMP and PSSP. IOO DRP-002-2021 (AMENDED) Specified Measure 2

2. Provide to the IO on or before 27 August 2021 a written description of the actions Trans Mountain has taken or will take to ensure construction activities on MC1 and MC2 work sites are conducted in accordance with the HSMP and PSSP. IOO DRP-002-2021 (AMENDED) Specified Measure 3

3. Provide to the IO on or before 18 August 2021 a response confirming if work on the MC1 and MC2 worksites has been conducted under the following approved plans, filed with the CER under OC-065.

  1. Rare Plant Population Management Plan (condition 40);
  2. Wetland Survey and Mitigation Plan (condition 41);
  3. Watercourse Crossing Inventory (condition 43);
  4. Wildlife Species at Risk Mitigation and Habitat Restoration Plans (condition 44);
  5. Contamination Identification and Assessment Plan (condition 46);
  6. Grizzly Bear Mitigation Plan (condition 56);
  7. Riparian Habitat Management Plan (condition 71);
  8. Pipeline Environmental Protection Plan (condition 72);
  9. Old Growth Management Areas Mitigation and Replacement Plan (condition 76);
  10. Acid Rock Drainage Management Plan (condition 72 and 78);
  11. Plan for Indigenous Group Participation in Construction Monitoring (condition 98);
  12. Heritage Resources and Sacred and Cultural Sites Plan (condition 100);
  13. Condition 100 a) and b), specifically with regards to all permits, clearances and conditions required by Province of British Columbia.
IOO DRP-002-2021 (AMENDED) Specified Measure 4

4. Provide to the IO on or before 27 August 2021 the corrective actions which will be carried out for all instances in which work has not been conducted under the approved plans listed in [specified measure 3] of this amended order. IOO DRP-002-2021 (AMENDED) Specified Measure 5

5. Identify and provide to the IO on or before 20 August 2021 a summary of other instances across the TMEP project where work authorized by certificate OC-065 is being performed under any plan or procedure that differs from those filed with the CER under OC-065 including but not limited to the plans listed in [specified measure 3].
  1. If the work has not been conducted under the approved plans, provide to the IO a corrective action plan to mitigate all instances on or before 27 August 2021.

Due date: 2021-08-27

Date closed: 2021-09-01
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 6 - IOO DRP-002-2021 (AMENDED) Measure 1 - IR 1

Discipline: Safety Management

Categories:

Facility:

Observations:

CER has reviewed Trans Mountain’s response to measure 1 of IOO DRP-002-2021 (AMENDED) submitted on August 13th, 2021 and requires additional information.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide the following information to supplement Trans Mountain's response to measure 1 of IOO DRP-002-2021 (AMENDED).

 

TMEP Plan Item #Information Request
2Provide a list of TMEP approved variances, exceptions, or deviations to requirements of the following plans which are specifically related to OC-065 authorized construction activities for Mountain Crossing 1 and Mountain Crossing 2 (hereafter referred to as Laidlaw Bluffs). 
  • TMEP HSMP 
  • Spread 5B PSSP 
  • Environmental Protection Plans 
 
For clarity, I am referring to variances that have been approved under CESM Appendix A, referenced in TMEP HSMP sec 19.0.
 
4Provide confirmation when the CHRR review is completed. 
7Confirm commitments made in the Ohamil traffic control plan update – (C08746) have been or will be communicated to all contractors working on MC1 and Laidlaw Bluffs in accordance with section 5.0 of that filing. 
8Provide an organizational chart showing TMEP Inspection personnel that will initially provide oversight of Mountain Crossing 1 and Laidlaw Bluffs sites including: 
 
  • TMEP Traffic Inspector(s) 
  • Damage Prevention Inspector(s) 
  • Field Safety Inspector(s) 
  • Environmental Inspector(s) 
 
Indicate if positions listed above will be occupied by the same individual; Indicate reporting lines from TMEP Inspection personnel to project leadership; For each position, indicate months of experience providing oversight of OC-065 authorized construction activities on behalf of TMEP.  

Due date: 2021-08-27

Date closed: 2021-08-16
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program