Compliance verification activity type: Field Inspection
Team:
Regulated company: Enbridge Pipelines Inc.
Operating company: Enbridge Pipelines Inc.
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Field inspection of the response to INC2022-029 release of crude oil within the Edmonton Terminal.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - General Observation - Spill Response
Date & time of visit: 2022-02-15 13:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
Environmental Protection Inspection Officers (IOs) inspected Enbridge's response to the crude oil release which occurred on the evening of 12 February 2022 at the Edmonton Terminal. IOs assessed Enbridge's general response to the clean-up, with focus on management and monitoring of the hazard that the crude oil poses to environmental and human health. Specific observations noted during the inspection are as follows:
Clean-up Approach
Air Quality Monitoring
Signage
Personal Protective Equipment
Compliance tool used: No compliance tool used
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program