Compliance Verification Activity Report: CV2223-103 - Trans Mountain Pipeline ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2223-103
Start date: 2023-03-13
End date: 2023-03-15

Team:

Regulated company: Trans Mountain Pipeline ULC

Operating company: Kinder Morgan Canada Inc

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

TMEP Inspection of Spread 5A, including the Coldwater River DPI

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Additional Project-specific requirements or conditions:

OC-65 - Condition 111

Observations (no outstanding follow-up required)

Observation 1 - INSPECTION DRAFT REPORT

Date & time of visit: 2023-03-31 13:35

Discipline: Integrity Management

Categories:

Facility:

Observations:

Review of documentation/records:

Welding:
Overall, the repair rate is to date 2.79%. TMEP mentioned that the most repairs occur on the HSC Girth Weld and heavier walls (+19 mm). TMEP provided some welding repair statistics (see picture “Welding activities Dashboard”).

WPS and WPDS:
TMEP provided the CER with actual welding activities WPS and WPDS for mainline welding and repairs.
CER IOs reviewed the following documents:

CER IOs checked the alignment between WPS, PQR and WPDS. The only noticeable difference is that on the WPS the maximum interpass temperature (Tmax) is 181 C but 200 C on the WPDS. However, following TMEP's response to condition 111, TMEP qualified the procedure with reference to CSA Z662 Annex K, Table K-1 where essential variables such as interpass temperature can change up to 50 C more than Tmax when Tmax in the WPS is less than 200 C (181 C in the WPS). CER IOs found both documents were aligned.
 
Lowering-In plan Spread 5A (see picture “Lower In plan Spread 5A.jpg”):
Backfill and compaction plan Spread 5A (see picture “Backfill and compaction plan Spread 5A.jpg”):
HDD execution plan Coldwater 2 (see picture “HDD execution plan Coldwater 2.jpg”):
CER IOs reviewed the document and noted several points to be verified in the field: SITE VISITS:

Bending (AK 12 +200) (see picture “Bending activities”):
Welding (AK 17+800) (see picture “Welding activities”):
Backfilling (AK 16 +220) (see picture “Backfilling site”):
CER IOs note the following:
HDD Rig 3 Site Visit (KP 966 + 500):
CER IOs note the following:

Compliance tool used: No compliance tool used

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program