Compliance Verification Activity Report: CV2122-184 - NOVA Gas Transmission Ltd.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2122-184
Start date: 2021-09-23
End date: 2021-09-23

Team:

Regulated company: NOVA Gas Transmission Ltd.

Operating company: TransCanada PipeLines Limited

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

NGTL 2021 - Elmworth Wapiti Steep Slope. Assess field implementation of construction safety manual and project specific safety plans for ongoing construction activities; worker tasks including identification of hazards and appropriate controls relevant to the job tasks via hazard assessments; company implementation COVID-19 safety protocols; company oversight of contractors - training & competence, monitoring, supervision and accountability; assess execution of work per applicable procedures and documented work practices.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - General

Date & time of visit: 2021-09-23 13:00

Discipline: Safety Management

Categories:

Facility:

Observations:

General

Compliance tool used: No compliance tool used

Observation 2 - Wapiti River – North Side:

Discipline: Safety Management

Categories:

Facility:

Observations:

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Elmworth - Midwest:
Please provide the following:
 

  1. Provide copies of any safety audits completed on the project by NGTL or their contractor. If no audits were conducted please provide the rationale. “The audit/formal inspection must be conducted when a representative sample of the personnel and Work activities can be observed.”
  2. For Elmworth - Completed inspection forms from NGTL and contractor H&S management - last 3 Wednesdays( Sep 1,8,15 2021)
  3. Copies of craft inspector dailies (3 most recently completed for each person):
    • Elmworth:
      • TC Safety Inspector
      • the inspector on the Wapiti North and South steep slope  - one inspection report for each of the following stages clearing grading, stringing, and lowering-in
  4. Provide explanation/documentation to identify how requirements of s. 4.2 of TES-CT-SLOPE-GL Slope Work Specification CAN-US-MEX have been achieved. 
  5. Confirmation if there have been any updates to the steep slope documents required as per the TES-CT-SLOPE-GL Slope Work Specification CAN-US-MEX (provide the updates if so. If not, provide rationale for not being completed).  For example. Section 4.6.2 of the TES-CT-SLOPE-GL Slope Work Specification (CAN-US-MEX)  states The Hazardous Slope Work Plan shall identify the changes to the site conditions that would effect a change to the Hazardous Slope Work Plan (e.g., tropical rain, ice, snow,
  6. lighting storm).
  7. Please provide the Machine Stability Risk Assessment for the machines being used by NGTL inspectors on Elmworth. Section 4.5.2 of the TES-CT-SLOPE-GL Slope Work Specification (CAN-US-MEX)  states “The Hazardous Slope Work Plan shall identify the equipment and machine manufacturers’ recommended safe working limitations.”
  8. Please explain how the TES-CT-SLOPE-GL Slope Work Specification CAN-US-MEX Table 3-2: Wheeled and Tracked Machine Stability Risk Matrix was created.
  9. Please identify the ‘wheeled machines’ used on the Wapiti North and South slopes and their maximum slope limitations established by the manufacturer.
  10. Please provide a rationale for Post Grade ‘Machine Stability Risk Assessment – Risk Value for Wheeled Vehicles’. The CER observed that there appeared to be no assessments for slope limitations of wheeled vehicles.
  11. Provide the NGTL inspector training and competency evaluation for ATV/UTV use.
  12. Please provide copies of the 3 most recently completed “ATV/UTV Competency Evaluation” forms (Midwest Doc # HSE-FRM-C01)
  13. Please provide copies of the 3 most recently completed “Supervisor Steep Slopes Competency Evaluation” forms (Midwest Doc # HSE-FRM-C09)
  14. Please provide copies of the 3 most recently completed “Steep Slope Worker Competency Evaluation” forms (Midwest Doc # HSS-FRM-C10)

Due date: 2021-10-21

Date closed: 2021-11-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 3 - NNC #1 Failure to ensure company requirements related to identification and analyzing hazard associated with work on slopes are adhered to.

Date & time of visit: 2021-09-23 10:00

Discipline: Safety Management

Categories:

Facility:

Observations:

An all-terrain vehicle (ATV) as well as a utility task vehicle (UTV) were observed at the top of slope at the Wapiti River crossing.  Discussions with the vehicle operator (ATV) and site occupants, it was confirmed that these vehicles were utilized on the adjacent river slopes.  The manufacturer recommended limits for slope gradient for these vehicles (a Bobcat UV34 Utility Vehicle and a Kawasaki 650 ATV) were not known by either the operator or other company/contractor personnel on site.  It was later determined that the manufacturer identified safe climbing angle for the Bobcat UV34 Utility Vehicle was 15 degrees. Company personnel indicated that slopes at this location exceeded 15 degrees was identified as a hazardous slope.  The company representatives took action to cease all use of ATVs/UTVs on hazardous slopes across the NGTL 2021 project until the manufacturer safe use recommendations had been confirmed for each UTV/ATV.

Per the 'TES-CT-SLOPE-GL Slope Work Specification (CAN-US-MEX)':
 4.2.1
For conventional pipeline construction, the Hazardous Slope Work Plan shall include, but is not limited to, the following:

4.5.2 The Hazardous Slope Work Plan shall identify the equipment and machine manufacturers’ recommended safe working limitations.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

During the inspection, the company voluntarily halted all UTV/ATV use on all steep slopes across the project until such time as it could ensure that wheeled machines did not exceed their maximum slope limitations established by the manufacturer. 

  1. The company will review documentation developed and provided by their contractors across the NGTL 2021 System Expansion Project as required by the Slope Work Specification and identify any information gaps.
  2. The company will ensure work by any vehicles/mobile equipment on hazardous slopes does not occur until information gaps identified in part 1 above have been corrected and it is confirmed that the use of vehicles/mobile equipment is deemed safe and within manufacturer recommended limits. Where manufacturer recommended limits do not exist, outline mitigation measure to address the hazard.
  3. The company will review their internal processes for reviewing and accepting contractor documentation associated with the Slope Work Specification to determine how submissions that did to meet the requirements were accepted.
  4. The company will identify and implement measures to prevent acceptance of contractor submissions that do not fulfill the requirements of the Slope Work Specification as identified in part 3 above.

Due date: 2021-12-24

Date closed: 2022-07-04
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 4 - Indigenous Monitoring

Date & time of visit: 2021-09-23 09:00

Discipline: Indigenous Monitoring

Categories:

Facility:

Observations:

The following section contains independent observations made by an Indigenous Monitor who accompanied the Canadian Energy Regulator Inspection Team during this inspection, as part of the CER’s commitment to the NGTL's Indigenous Monitoring Program. They are reproduced and publicized within my report for greater transparency. They are not my conclusions but represent one source of information among others I have considered throughout the inspection along with my own direct observations and information received from the company.

IMAC – Sucker Creek First Nation - SCFN Services – IM:
Safety Inspection - September 21-24,  2021 CV2122-185 Grande Prairie area accompanied with CER and NGTL/Midwest Environmental Team

  1. September 22, 2021: Karr Yard with the CER, NGTL/Midwest Environmental Team and Emerinskin IM, for site Orientation and discuss the day activities
  2. September 23, 2021: Midwest Elmworth Yard with the CER, NGTL/Midwest Environmental Team and Emerinskin IM, for site Orientation and discuss the day activities
IMAC – Ermineskin Cree Nation – IM:
Canadian Energy Regulator 
IAMC-NGTL
September 22-23-2021
Safety Inspection
Karr (RoW) Elmorth section 

September 22-23-2021September 23-2021 
Arrived to Tc energy yard (Midwest)
Went through covid 19 form 
Introduction between the CER-IAMC IMs Tc energy representatives.
Went through visitor orientation for Midwest 

Stop 1# Kp 26-100 (step slope)  Stop #2 Kp 26+100 bottom of the wapiti HDD (exit side) 

Compliance tool used: No compliance tool used

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program