Compliance verification activity type: Field Inspection
Team:
Regulated company: NOVA Gas Transmission Ltd.
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
NGTL 2021 - Elmworth Wapiti Steep Slope. Assess field implementation of construction safety manual and project specific safety plans for ongoing construction activities; worker tasks including identification of hazards and appropriate controls relevant to the job tasks via hazard assessments; company implementation COVID-19 safety protocols; company oversight of contractors - training & competence, monitoring, supervision and accountability; assess execution of work per applicable procedures and documented work practices.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - General
Date & time of visit: 2021-09-23 13:00
Discipline: Safety Management
Categories:
Facility:
Observations:
General
Compliance tool used: No compliance tool used
Observation 2 - Wapiti River – North Side:
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
Elmworth - Midwest:Please provide the following:
Due date: 2021-10-21
Date closed: 2021-11-05 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - NNC #1 Failure to ensure company requirements related to identification and analyzing hazard associated with work on slopes are adhered to.
Date & time of visit: 2021-09-23 10:00
An all-terrain vehicle (ATV) as well as a utility task vehicle (UTV) were observed at the top of slope at the Wapiti River crossing. Discussions with the vehicle operator (ATV) and site occupants, it was confirmed that these vehicles were utilized on the adjacent river slopes. The manufacturer recommended limits for slope gradient for these vehicles (a Bobcat UV34 Utility Vehicle and a Kawasaki 650 ATV) were not known by either the operator or other company/contractor personnel on site. It was later determined that the manufacturer identified safe climbing angle for the Bobcat UV34 Utility Vehicle was 15 degrees. Company personnel indicated that slopes at this location exceeded 15 degrees was identified as a hazardous slope. The company representatives took action to cease all use of ATVs/UTVs on hazardous slopes across the NGTL 2021 project until the manufacturer safe use recommendations had been confirmed for each UTV/ATV. Per the 'TES-CT-SLOPE-GL Slope Work Specification (CAN-US-MEX)': 4.2.1For conventional pipeline construction, the Hazardous Slope Work Plan shall include, but is not limited to, the following:
Compliance tool used: Notice of Non-compliance (NNC)
During the inspection, the company voluntarily halted all UTV/ATV use on all steep slopes across the project until such time as it could ensure that wheeled machines did not exceed their maximum slope limitations established by the manufacturer.
Due date: 2021-12-24
Date closed: 2022-07-04 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 4 - Indigenous Monitoring
Date & time of visit: 2021-09-23 09:00
Discipline: Indigenous Monitoring
The following section contains independent observations made by an Indigenous Monitor who accompanied the Canadian Energy Regulator Inspection Team during this inspection, as part of the CER’s commitment to the NGTL's Indigenous Monitoring Program. They are reproduced and publicized within my report for greater transparency. They are not my conclusions but represent one source of information among others I have considered throughout the inspection along with my own direct observations and information received from the company.IMAC – Sucker Creek First Nation - SCFN Services – IM:Safety Inspection - September 21-24, 2021 CV2122-185 Grande Prairie area accompanied with CER and NGTL/Midwest Environmental Team
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program