Compliance verification activity type: Field Inspection
Team:
Regulated company: Pembina Prairie Facilities Ltd.
Operating company: Pembina Pipeline Corporation
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Field inspection of the Vantage Pipeline to verify successful reclamation of watercourse crossings, wetland function, and native prairie.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Additional Project-specific requirements or conditions:
Observation 1 - General Observations
Date & time of visit: 2021-07-22 13:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
Rare Plants / Wildlife habitat
Compliance tool used: No compliance tool used
Observation 2 - Information Requests - Historical Monitoring and Information
The five-year Post Construction Monitoring Report states that reclamation of the RoW is complete; however, during the inspection, Officers noted potential outstanding reclamation issues at the following locations:(1) Rare Plant (5-17-9-14 W3M);(2) Watercourse Crossing (3-17-8-7 W3M);(3) Wetland (13-34-4-21 W2M); and(4) Native Prairie (34-4-21 W2M). To verify appropriateness of statements and assements of the five-year Post Construction Monitoring Report, as well as determin potential needs for additional monitoring or corrective measures at these locations, CER Officers require additional information from historical records to:-assess the adequacy of reclamation along RoW and Temporary Work Space (TWS);-identify what recommendations for follow-up were included to address issues; and-verify that reclamation activities have occurred as described in Post Construction Monitoring Reports (PCMRs) since construction of the Pipeline.
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
Pembina will submit a response, based on the data and information from pre-construction, construction, and year 1,3,and 5 PMCRs outlining relevant information for each location.
Due date: 2021-08-13
Date closed: 2021-10-31 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - Reclamation at Pinto Creek
Date & time of visit: 2021-08-18 12:00
Compliance tool used: Notice of Non-compliance (NNC)
Pembina Prairie Facilities Ltd. (Pembina) will:
Due date: 2021-11-30
Date closed: 2021-11-29 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program