Compliance Verification Activity Report: CV2122-221 - Pembina Prairie Facilities Ltd.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2122-221
Start date: 2021-07-26
End date: 2021-07-30

Team:

Regulated company: Pembina Prairie Facilities Ltd.

Operating company: Pembina Pipeline Corporation

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

Field inspection of the Vantage Pipeline to verify successful reclamation of watercourse crossings, wetland function, and native prairie.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Additional Project-specific requirements or conditions:

Post-Construction Monitoring Reports for years 1, 3, and 5.

Observations (no outstanding follow-up required)

Observation 1 - General Observations

Date & time of visit: 2021-07-22 13:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Rare Plants / Wildlife habitat
 

Grazing Leases and Improved PasturesCropped LandsWetlandsWatercourse Crossings
  Piapot Creek
  Bone Creek
  Skull Creek
  Rock Creek
  Notekeu Creek
  Unnamed tributary to Notukeu Creek

Compliance tool used: No compliance tool used

Observation 2 - Information Requests - Historical Monitoring and Information

Discipline: Environmental Protection

Categories:

Facility:

Observations:

The five-year Post Construction Monitoring Report states that reclamation of the RoW is complete; however, during the inspection, Officers noted potential outstanding reclamation issues at the following locations:

(1) Rare Plant (5-17-9-14 W3M);
(2) Watercourse Crossing (3-17-8-7 W3M);
(3) Wetland (13-34-4-21 W2M); and
(4) Native Prairie (34-4-21 W2M). 

To verify appropriateness of statements and assements of the five-year Post Construction Monitoring Report, as well as determin potential needs for additional monitoring or corrective measures at these locations, CER Officers require additional information from historical records to:
-assess the adequacy of reclamation along RoW and Temporary Work Space (TWS);
-identify what recommendations for follow-up were included to address issues; and
-verify that reclamation activities have occurred as described in Post Construction Monitoring Reports (PCMRs) since construction of the Pipeline. 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Pembina will submit a response, based on the data and information from pre-construction, construction, and year 1,3,and 5 PMCRs outlining relevant information for each location.

Due date: 2021-08-13

Date closed: 2021-10-31
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 3 - Reclamation at Pinto Creek

Date & time of visit: 2021-08-18 12:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Pembina Prairie Facilities Ltd. (Pembina) will:
 

  1. Provide to CER Officers a scope of work for repairs at the Pinto Creek site (Pinto Repair) that correct, manage, and mitigate issues associated with crowning, mounding, and settlement of soils on the Pipeline trench RoW, as well as the identified area of soil erosion (loss of pipe cover) next to the Pipeline and the adjacent soil berm.
 
  Pembina Prairie Facilities Ltd. (Pembina) will:

2. Implement the scope of work identified in (1).

3. Provide CER Officers with site field inspection photos, including but not limited to, ongoing activities, as well as final site conditions once equipment has demobilized.  

4. Confirm that this site-specific information for the Pinto Repair will be included in the 10 year Post-Construction Environmental Monitoring Report required by Condition 46 of OC-59 (the Certificate).

Due date: 2021-11-30

Date closed: 2021-11-29
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program