Compliance Verification Activity Report: CV2223-287 - Enbridge Pipelines Inc.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2223-287
Start date: 2022-11-16
End date: 2022-11-17

Team:

Regulated company: Enbridge Pipelines Inc.

Operating company: Enbridge Pipelines Inc.

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

Field inspection of the active remediation being conducted at a site near Lorne, MB and Swan Lake First Nation (REM2018-032)

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - MP708.35 Remediation Field Inspection

Date & time of visit: 2022-11-17 11:45

Discipline: Environmental Protection

Categories:

Facility:

Observations:

The Inspection Team conducted a field inspection of the active remediation work ongoing at Line 2, MP708.35:

Soil and groundwater management:


Air quality monitoring:
Aquatic Receptor (Creek) Management  
Engagement

Compliance tool used: No compliance tool used

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program