Compliance Verification Activity Report: CV2223-096 - Trans Mountain Pipeline ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2223-096
Start date: 2022-09-07
End date: 2022-09-09

Team:

Regulated company: Trans Mountain Pipeline ULC

Operating company: Trans Mountain Pipeline ULC

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

  1. TMX compliance with condition 5 construction timing commitments for Watson Elementary and Vedder Middle School lands near Chilliwack, BC.
  2. TMX Burnaby & Westridge Terminals - Contractor oversight of construction activities - training & competence, monitoring, supervision and accountability; assess the execution of work per applicable procedures and documented work practices; compliance with condition 80 noise management plan.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Information Request

IR from CER (Information Request sent from CER to company)
#1. HIPO investigation report

Legislative Requirement : Canadian Energy Regulator Act (CERA)

Sections of the Act

  • Canadian Energy Regulator Act (CERA)
    • Administration and Enforcement
      • Duty to assist<br />103 (4) The owner or person in charge of the place and every person in the place must give all assistance that is reasonably required to enable the inspection officer to perform their duties and functions under this section and must provide any documents or information, and access to any data, that are reasonably required for that purpose.

Theme and Categories

Safety Management
  • Records & Documentation
    • Internal near miss and incident trending, reporting, preventive and corrective actions

Due Date : 2022-09-07

Review Response
Acceptable

Follow-up Action
None

IR from CER (Information Request sent from CER to company)
#2. FSI Daily Report Westridge Marine Terminal

Legislative Requirement : Canadian Energy Regulator Act (CERA)

Sections of the Act

  • Canadian Energy Regulator Act (CERA)
    • Administration and Enforcement
      • Powers on entry<br />103 (2) The inspection officer may, for that purpose,

Theme and Categories

Safety Management
  • Contractor Management & Oversight
    • Supervision, Inspection and Monitoring

Due Date : 2022-09-19

Review Response
Acceptable

Follow-up Action
None

IR from CER (Information Request sent from CER to company)
#3. Deck Barge Fuel Transfer Procedure

Legislative Requirement : Project-specific Contractor/Project Safety Plan (CSP)

Applicable Wording from Legislative Document
2.9.3 Document Control Pertinent documents will be filed as per the KLTP Document Control Procedures. All other documents are filed and shared using the KLTP Project SharePoint.

Theme and Categories

Safety Management
  • Workplace Practices
    • Procedures/Work Instructions

Due Date : 2022-09-19

Review Response
Acceptable

Follow-up Action
None

Observations (no outstanding follow-up required)

Observation 1 - OPL-005-2021 Condition 5 - Chilliwack School District

Date & time of visit: 2022-09-07 12:00

Discipline: Administrative

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 2 - Burnaby Terminal

Date & time of visit: 2022-09-08 14:30

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officer (IO) and IAMC-TMX Indigenous Monitors (IMs) performed a field inspection of Burnaby Terminal (BT) on 8 Sep 2022. 

TMEP Oversight and Inspection of Work Activities

TMEP Field Safety Inspectors

Human Equipment Interface

No items of non-compliance were observed.

Compliance tool used: No compliance tool used

Observation 3 - Westridge Marine Terminal

Date & time of visit: 2022-09-09 14:30

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) and TMX-IAMC Indigenous Monitor (IM) performed a field inspection of Westridge Marine Terminal (WMT) on 9 Sep 2022.

Deck Barge Olympia Incident Investigation

TMEP Oversight and Inspection of Work Activities

Fueling on the Deck Barge Columbia

No items of non-compliance were observed.

Compliance tool used: No compliance tool used

Observation 4 - OC-065 Condition 80 - Noise Management

Date & time of visit: 2022-09-09 14:30

Discipline: Administrative

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) reviewed August 2022 noise monitoring data for Westridge Marine Terminal and Burnaby Terminal to verify compliance with the TMEP Noise Management Plan submitted under condition 80 (NMP).

No items of non-compliance were observed,

Compliance tool used: No compliance tool used

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program