Compliance verification activity type: Field Inspection
Team:
Regulated company: TransCanada Keystone Pipeline GP Ltd.
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Environmental inspection of construction of Keystone XL Project, Alberta segment, Oyen, Monitor and Lakesend spreads. This inspection was conducted in cooperation with CER contracted Indigenous Monitors, focusing on traditional land use and cultural heritage programs as they relate to pipeline construction.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - General Observations
Date & time of visit: 2020-08-11 15:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
CER Inspection Officers (IOs), in cooperation with CER contracted Indigenous Monitors (IMs) inspected ongoing construction activities across the KXL project, observing environmental and cultural features and mitigation across three active construction spreads; Oyen, Monitor and Lakesend. The following observations were made over the course of the four day in-field inspection: Right-of-Way ObservationsStripping and Grading
Compliance tool used: No compliance tool used
Observation 2 - CNC 1 - Hydrocarbon staining at Oyen Yard
Date & time of visit: 2020-08-14 09:30
Inspection Officers observed areas of hydrocarbon staining in and around the refueling station and mechanics shop at the Oyen Yard. Specifically:
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
TC Energy must implement corrective actions to demonstrate compliance to the issues surrounding appropriate containment and cleanup of hydrocarbons. TC Energy will provide photographic evidence of completed corrective actions.
Due date: 2020-08-14
Date closed: 2020-08-25 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - CNC 2 - Waste inappropriately segregated at Oyen Yard
Date & time of visit: 2020-08-14 08:50
Inspection Officers observed aerosol spray paint cans inappropriately disposed of in the domestic waste bin.
Inappropriate waste materials must be segregrated according to labels on the bins. The aersol cans must be removed and placed in the correct bin.
Observation 4 - CNC 3 - Missing Secondary Containment in Oyen Yard Mechanics Shop
Date & time of visit: 2020-08-14 09:15
Inspection Officers observed two 1200L lube oil containers stored outside of secondary containment within the mechanics shop in the Oyen Yard.
TC Energy must place the lube oil containers within appropriate secondary containment.
Observation 5 - CNC 4 - Cigarette Butt on ROW
Date & time of visit: 2020-08-11 16:00
A single cigarette butt was discovered on the Right-of-way adjacent to the wetland 1340 crossing.
TC Energy will remove the observed cigarette butt for appropriate disposal.
Due date: 2020-08-11
Date closed: 2020-08-11 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 6 - Thunderchild First Nation - Indigenous Monitor Observation
Date & time of visit: 2020-08-14 09:00
Additional observations recorded by IAMC Indigenous Monitors participating in the CER inspection. Any compliance-related observations that require specific regulatory follow-up have been recorded above.Community involvementAcknowledgement that this inspection took place on Treaty 6 and Metis Nation 3 lands. These 5 communities were involved on this segment of pipeline Ermineskin Cree Nation, Louis Bull Tribe, Montana First Nation, Samson Cree Nation, and Siksika (blackfoot). Each nation had provided their own Indigenous monitors to conduct Traditional Land Use surveys and mark out discovered sites. All Traditional knowledge sites were generalized and grouped together by either a red no disturbance zone or green possible disturbance zone, a system to keep the sites private within the nations. They were given time to study, harvest and perform ceremonies on sites where they felt needed. The contractor had a fencing crew come after the IM’s to fence off these sites and then were reviewed again by the monitors and were able to requested expansion of the area if they felt needed. During the inspection we got to see the involvement of the nations and were able to have a conversation with the IM’s from the different nations about their experience and overall had positive feedback. It was great to see the nations excited to be working together and given the opportunity to learn from each other. Trans Canada and Michels seemed to be very accommodating of the difference nations wishes, it was great to see how well everyone was working together. The relationships between the companies, nations and the lands seemed strong and respectful, they are off to great start on this project. CommentsHaving the opportunity to be involved in the inspection with CER has been a great learning exercise. In this segment of the pipeline there was a lot of identified TK sites. Seeing how well the companies integrated the requests from the nations was really great to see. Knowing they are leaving time to for the nations and their workers to not only have ceremonies for sites that were disturbed by the ROW, but to have the companies invited to take part shows a level of respect throughout the workplace. I am excited to see this progress and I hope it continues throughout the project.
Observation 7 - Metis Nation of Alberta (R3) - Indigenous Monitor Observation
Additional observations recorded by IAMC Indigenous Monitors participating in the CER inspection. Any compliance-related observations that require specific regulatory follow-up have been recorded above.ArcheologicalInspected archeological site TK419, it was fenced (rope) off to protect them from being disturbed and numbered (catalogued) for future reference. Also discussed archeological red and green sites. Indigenous heritage sites TK224, 227, and 228 discussed the significance of the heritage site, fenced (rope) off to protect them from being disturbed and numbered (catalogued) for future reference. Inspected heritage sites TK 248, 249 and 251, fenced (rope) off to protect them from being disturbed and numbered (catalogued) for future reference. Inspected and discussed the base of a buffalo rubbing stone, and how it was moved off the ROW and fenced as requested by 5 nations.VegetationViewed wildflower called Blazing Star used for indigenous medicine.WildlifeInspected perimeter fencing on a 4-wire fence, making sure the bottom was smooth allowing wildlife to pass under without getting injured. The bottom strand was 19 inches off the ground. The upper 3 wires were barbed. Viewed Swainson Hawk nest and discussed the buffer zone (500/1000 metre). Inspected Canadian Toad breeding area at ID 867, fencing and signage in place.SoilsInspected workspace and viewed how topsoil is stored on top of pipeline. Inspected grading at R28 and topsoil piles sprayed with tacifier to prevent wind erosion.WetlandsInspected wetlands along ROW. Inspected wetland ID 139. Viewed matting at wetland KP58TR00. Wetlands along the ROW all exclusion fencing was in place and functioning as intended. Wind had blown an exclusion fence off one stake and it was repaired immediately. Matting was installed properly in wetland areas and functioning as intended.Other ObservationsViewed water supply pond and inspected water licence at SW34-26-4W4. Checked that the water suction hose had a screen on the end. Inspected equipment cleaning tag. Inspected area for underground rail line crossing, hydrovac area to ensure that topsoil is removed byhand before proceeding. Inspected wash station at KP58TR00 viewing level one cleaning. Level two cleaning will take place when equipment moves out of the area.SummaryIt was a very intriguing experience it be part of the field inspection group and working along with the CER, Michel’s, KXL, and the IMs. I gained a lot of knowledge at every inspection and every stop along the ROW. At the morning meetings we would discuss the previous days highlights. Any questions that were asked some one would have a answer. The mitigative measures the prime contractor and the proponent put in placeare working as intended and the companies are following the EPP. The indigenous coordinators were knowledgeable about the Red and Green area heritage sites and the buffalo rubbing stone. There were no TC Energy IMs available due to Covid19 isolation. It would have been interesting to hear their stories in person about the history of the area and the heritage sites as very impressed how the Proponentand the Prime Contractor went to great lengths to protect the wet lands, the soils, wildlife, and heritage sites. All areas were clean, the equipment was in impeccable shape. I was impressed how the Proponent and the Prime Contractor went to great lengths to protect the wetlands, soils, wildlife, and heritage sites. Covid19 safety and Personnel safety were Number One.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program