Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Kinder Morgan Canada Inc
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
TMEP construction inspection of Spread 7B
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - Construction Work Package (CWP) 061 - day 1
Date & time of visit: 2023-02-14 13:30
Discipline: Integrity Management
Categories:
Facility:
Observations:
Compliance tool used: No compliance tool used
Observation 2 - CWP 080 and 081 - day 1
Date & time of visit: 2023-02-14 15:10
- Activities at this site were stopped at the time of CER and TMEP staff arrival due to issues encountered regarding the alignment of the pipe joint and the hot bend. A TMEP technical assessment was ongoing. - The safety hazard forms issued for the day were reviewed. These included: KLTP Daily Shoring Box Inspection Sheet issued for 34 trench boxes signed off by the foreman, Ground Disturbance form, Operators Start Card and Foreman's Safety/Quality Meeting Record. All documents listed the hazards and tasks required for the daily activities and were signed off. The foreman indicated that individual inspections are completed for individual trench boxes.
Observation 3 - CWP 088 - day 1
Date & time of visit: 2023-02-14 16:00
Observation 4 - CWP 061 - day 2
Date & time of visit: 2023-02-15 09:20
Observation 5 - CNC 1
Date & time of visit: 2023-02-15 11:00
Discipline: Safety Management
Two ladders (one for each pipe joint) were installed on the same side of the trench as entry and exit points. KLTP foreman stated that each ladder serves for both entry and exit purposes and they are installed in accordance with the Worksafe BC Regulation, section 20.87 (2), which was digitally available on site. CER inspectors noted that the requirement was interpreted incorrectly and notified KLTP and TMEP staff that ladders must be installed on both sides of the trench at the working area allowing workers from each side of the pipe joints to exit the trench in case of emergency. It was also noted that this is considered a non-compliance considering the work has not been started.
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Ladders must be installed on both sides of the trench at the working area allowing workers from each side of the pipe joints to exit the trench in case of emergency while working on the pipe.
Due date: 2023-02-15
Date closed: 2023-02-15 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 6 - CNC 2
Date & time of visit: 2023-02-15 14:00
CER inspectors notified TMEP that a non-compliance was being considered until appropriate information and documentation are provided to field personnel to address potential future similar situations of improper trench entry and exit access.
Appropriate information and documentation is required to be provided to field personnel to ensure similar future situations of improper trench entry and exit access will be avoided. The documentation must include the necessary requirements regarding the proper installation of ladders at the entry and exit access points.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program