Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company:
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
TMX Spread 2 - Assess field implementation of construction safety manual and project-specific safety plans for ongoing construction activities; worker tasks including identification of hazards and appropriate controls relevant to the job tasks via hazard assessments; company implementation COVID-19 safety protocols; company oversight of contractors - training & competence, monitoring, supervision and accountability; assess execution of work per applicable procedures and documented work practices.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - General Observations
Date & time of visit: 2021-08-05 15:30
Discipline: Safety Management
Categories:
Facility:
Observations:
Day 1-Contractor daily work plan was provided and reviewed for purposes of oversight planning by TMEP inspectors.-Scopes of work were evaluated for risk and site visits were planned-Life Saving Rules were considered for TMEP Focused Inspection. Location 119-prep for ditching was ongoing-TMEP inspectors reviewed contractor documents – JSA, Tailgate Safety Meeting, Daily Safe Work Agreements.-hazards and controls were discussed at length with various workers.-TMEP inspectors executed meaningful engagement with contractors and sub-contractors. Day 2Midwest Road 138-2 contracted workers were observed sitting on welded pipe lengths on cribbage, several feet off the ground-TMEP Inspector quickly stepped in and eliminated the hazard. He took the opportunity to coach both the supervisor and other staff on the crew about the risks of sitting on elevated pipe. The FLHA was also not completed as required, which lead to another coaching opportunity of the TMEP inspector.--broader concerns about noise levels where crews were working was discussed. IR's issued on related matters.Overall, the 2 TMEP oversight inspectors observed were competent and effecting a high level of oversight of contracted workers. Excellent work.
Compliance tool used: No compliance tool used
Observation 2 - NNC 1 - Failure to Implement Hearing Conservation Program
Date & time of visit: 2021-08-30 10:14
Compliance tool used: Notice of Non-compliance (NNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Confirm action 4 and 5 of CAPA execution plan (CV 2122-094) has been completed on spread 2.
Due date: 2021-11-15
Date closed: 2021-11-15 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program