Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Trans Mountain Pipeline ULC
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
TMX Spread 5B - Assess field implementation of construction safety manual and project specific safety plans for ongoing construction activities including the Miner's Tunnel; worker tasks including identification of hazards and appropriate controls relevant to the job tasks via hazard assessments; company implementation of infection prevention protocols; company oversight of contractors - training & competence, monitoring, supervision and accountability; assess execution of work per applicable procedures and documented work practices.<br /> <br />
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - General Observations
Date & time of visit: 2022-12-08 11:30
Discipline: Safety Management
Categories:
Facility:
Observations:
CER Inspection Officers (IOs) and TMX-IAMC Indigenous Monitors (IMs) performed an unannounced safety inspection of TMEP Spread 5b on December 6-8, 2022. Two WorksafeBC Inspection Officers accompanied the inspection team and performed a simultaneous inspection. Opening meeting and planning
TMEP safety oversight on spread 5b
Field observations
Compliance tool used: No compliance tool used
Observation 2 - Inspection Officer Order BL-001-2022 - Respiratory Protection
Date & time of visit: 2022-12-19 12:00
RELEVANT FACTS I, XXXXX, designated as a CER Inspection Officer (IO) under subsection 102(1) of the Canadian Energy Regulator Act (CER Act), believe the following are the relevant facts relating to the issuance of this Order: designated as a CER Inspection Officer under subsection 102(1) of the Canadian Energy Regulator Act (CER Act), believe the following are the relevant facts relating to the issuance of this Order:
On 6 December 2022, the CER conducted an inspection where it was observed that welders and welders’ helpers were welding in an area that project personnel had identified as a confined space. The contractor’s confined space documentation for this location identified ‘general dilution ventilation’ without the use of respiratory protective equipment (RPE) as a control. At the time of the inspection, the CER noted that both contractor and Trans Mountain Expansion Project (TMEP) representatives were overseeing the welding activities and did not demonstrate they were aware of the requirement in the TEAM5B Exposure Control Plan-Welding Process to wear RPE. This process is further discussed below.
The CER observed that the welding was being conducted inside a high arch trench box, inside an excavation. The top and both sides of the welding area were partially enclosed, and the work area was filled with visible welding fume. Trans Mountain did not demonstrate to the CER that partial enclosure achieved sufficient general dilution ventilation to reduce or minimize welding fume concentration to below applicable Occupational Exposure Limit(s) in the workers’ breathing zone.
On 7 December 2022 the CER was told by contractor representatives from ‘TEAM5B’ that an exposure control plan (ECP) was created in the summer of 2022. The inspection team was also told that workers were required to be fit tested and wear a P100 respirator during welding activities. The TEAM5B Exposure Control Plan-Welding Process dated 18 July 2022 states “A half mask respirator with a P100 Hepa Filter shall be considered the minimum acceptable level of respiratory PPE and shall be worn during all welding activities as the minimum protection from welding fumes.” The CER noted that most of the workers in the confined space were not clean shaven, demonstrating that the proper use of a P100 respirator is not a common practice.
The CER notes that the 6 December 2022 observation is a repeat non-compliance for Trans Mountain with respect to RPE and welding activities. On several inspections conducted since March 2020 across the TMEP, the CER observed that workers performing or participating in welding tasks were not consistently using RPE where required. During those inspections, when CER questioned welders and participating workers about the use of RPE, answers varied from it's a personal choice, it was not a requirement, there was fresh air ventilation, and/or that definitive guidance is not provided to them to aid in their decision making.
The ‘Health and Safety Management Plan TMEP’ Document # 01-13283-GG-0000-HS-PLN-0001 R5 Appendix A Section 31: Respiratory Protection 31.1.2 states “Any Contractor potentially exposed to hazardous atmospheres or substances in excess of permissible exposure limits must have applicable respiratory protection.”
Based on these observations, the CER IO is of the view that Trans Mountain’s oversight did not result in reasonable care to ensure safety of persons, and in work being carried out in accordance with the construction safety manuals. Therefore, the CER is requiring the company to take the measures described below. SPECIFIED MEASURES
Trans Mountain must meet all requirements set out in section 94 of the CER Act, paragraphs 6.5(1)(f) and 6.5(1)(g) of the OPR, and subsection 54(1) of the OPR as they relate to exposure to airborne contaminants that may be generated by the specific welding, burning, or related processes. As the TMEP has activities occurring in the Provinces of Alberta and British Columbia, it must ensure that Occupational Health and Safety requirements of those jurisdictions are adhered to, including BC OHS Regulation s.5.53-5.55 and the Occupational Health and Safety Code Alberta Regulation 191/2021 ABOSHS244(1).
Trans Mountain shall:
Compliance tool used: Inspection Officer Order (IOO)
Regulatory requirement:
Relevant section(s):
Company action required:
Due date: 2023-02-28
Date closed: 2023-03-10 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - CNC 1 - Open excavation road 77
Date & time of visit: 2022-12-08 10:30
CER Inspection Officers (IOs) observed an excavation adjacent to a public roadway. TMEP told IOs that no work had occurred or been planned at the location that day. IOs observed that while fencing was present to block off the stairs, the stair access was open when the CER arrived; presumably, it was left open to public access overnight. In addition, the front side of the excavation was not fenced off in any way to prevent unintended access from the project personnel, the public, or animals.
Compliance tool used: Notice of Non-compliance (NNC)
TMEP shall ensure the excavation at road 77 is secured in accordance with the HSMP and PSSP.
Due date: 2022-12-08
Date closed: 2022-12-08 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 4 - NNC - Contractor oversight
Date & time of visit: 2022-12-06 15:00
CER Inspection Officers (IOs) observed and were informed that Trans Mountain inspectors are regularly in the field and conducting inspections. The CER notes that while the Trans Mountain craft and safety inspection team is conducting inspections and verifying the safety of workers in the field, there appears to be a focus on acute hazards rather than chronic hazards, in addition to safeguarding. Examples include:
Orders to address the deficiencies noted in the CER's observations have been issued to TEAM5B by WorkSafeBC.
Due date: 2023-02-03
Observation 5 - Electrical grounding
Date & time of visit: 2022-12-07 12:24
CER Inspection Officers (IOs) observed several generators and light stands at road 18 that were not grounded. No information was provided to the IOs during the inspection indicating that the generators did not require grounding. The generators in question appeared not to be the type that does not require grounding, such as the light stand at road 71. Per the TMEP HSMP - Appendix A section 10.2.4 All electrical equipment must be properly grounded and/or bonded. Post inspection:
Observation 6 - NNC - walking under counterweights road 28
CER Inspection Officers (IOs) performed an inspection at road 28. Several side booms were observed holding suspended loads with counterweights extended. During the FLHA review, the contractor told CER not to walk under the side boom counterweights. Despite this, CER observed workers walking under the extended boom and the counterweights of the side boom due to the site congestion. The practice continued even after WSBC Officers stood down the work to address this and other issues on the site.
Due date: 2023-01-13
Date closed: 2023-02-27 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program