Compliance Verification Activity Report: CV2223-089 - Trans Mountain Pipeline ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2223-089
Start date: 2022-12-06
End date: 2022-12-08

Team:

Regulated company: Trans Mountain Pipeline ULC

Operating company: Trans Mountain Pipeline ULC

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

TMX Spread 5B - Assess field implementation of construction safety manual and project specific safety plans for ongoing construction activities including the Miner&#39;s Tunnel; worker tasks including identification of hazards and appropriate controls relevant to the job tasks via hazard assessments; company implementation of infection prevention protocols; company oversight of contractors - training &amp; competence, monitoring, supervision and accountability; assess execution of work per applicable procedures and documented work practices.<br /> <br /> &nbsp;

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - General Observations

Date & time of visit: 2022-12-08 11:30

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) and TMX-IAMC Indigenous Monitors (IMs) performed an unannounced safety inspection of TMEP Spread 5b on December 6-8, 2022. Two WorksafeBC Inspection Officers accompanied the inspection team and performed a simultaneous inspection. 

Opening meeting and planning  

TMEP safety oversight on spread 5b  

Field observations 

 

Compliance tool used: No compliance tool used

Observation 2 - Inspection Officer Order BL-001-2022 - Respiratory Protection

Date & time of visit: 2022-12-19 12:00

Discipline: Safety Management

Categories:

Facility:

Observations:

RELEVANT FACTS

I, XXXXX, designated as a CER Inspection Officer (IO) under subsection 102(1) of the Canadian Energy Regulator Act (CER Act), believe the following are the relevant facts relating to the issuance of this Order: designated as a CER Inspection Officer under subsection 102(1) of the Canadian Energy Regulator Act (CER Act), believe the following are the relevant facts relating to the issuance of this Order:

On 6 December 2022, the CER conducted an inspection where it was observed that welders and welders’ helpers were welding in an area that project personnel had identified as a confined space. The contractor’s confined space documentation for this location identified ‘general dilution ventilation’ without the use of respiratory protective equipment (RPE) as a control. At the time of the inspection, the CER noted that both contractor and Trans Mountain Expansion Project (TMEP) representatives were overseeing the welding activities and did not demonstrate they were aware of the requirement in the TEAM5B Exposure Control Plan-Welding Process to wear RPE. This process is further discussed below.

The CER observed that the welding was being conducted inside a high arch trench box, inside an excavation. The top and both sides of the welding area were partially enclosed, and the work area was filled with visible welding fume. Trans Mountain did not demonstrate to the CER that partial enclosure achieved sufficient general dilution ventilation to reduce or minimize welding fume concentration to below applicable Occupational Exposure Limit(s) in the workers’ breathing zone.

On 7 December 2022 the CER was told by contractor representatives from ‘TEAM5B’ that an exposure control plan (ECP) was created in the summer of 2022. The inspection team was also told that workers were required to be fit tested and wear a P100 respirator during welding activities. The TEAM5B Exposure Control Plan-Welding Process dated 18 July 2022 states “A half mask respirator with a P100 Hepa Filter shall be considered the minimum acceptable level of respiratory PPE and shall be worn during all welding activities as the minimum protection from welding fumes.” The CER noted that most of the workers in the confined space were not clean shaven, demonstrating that the proper use of a P100 respirator is not a common practice.

The CER notes that the 6 December 2022 observation is a repeat non-compliance for Trans Mountain with respect to RPE and welding activities. On several inspections conducted since March 2020 across the TMEP, the CER observed that workers performing or participating in welding tasks were not consistently using RPE where required. During those inspections, when CER questioned welders and participating workers about the use of RPE, answers varied from it's a personal choice, it was not a requirement, there was fresh air ventilation, and/or that definitive guidance is not provided to them to aid in their decision making.

The ‘Health and Safety Management Plan TMEP’ Document # 01-13283-GG-0000-HS-PLN-0001 R5 Appendix A Section 31: Respiratory Protection 31.1.2 states “Any Contractor potentially exposed to hazardous atmospheres or substances in excess of permissible exposure limits must have applicable respiratory protection.”

Based on these observations, the CER IO is of the view that Trans Mountain’s oversight did not result in reasonable care to ensure safety of persons, and in work being carried out in accordance with the construction safety manuals. Therefore, the CER is requiring the company to take the measures described below.

SPECIFIED MEASURES

Trans Mountain must meet all requirements set out in section 94 of the CER Act, paragraphs 6.5(1)(f) and 6.5(1)(g) of the OPR, and subsection 54(1) of the OPR as they relate to exposure to airborne contaminants that may be generated by the specific welding, burning, or related processes. As the TMEP has activities occurring in the Provinces of Alberta and British Columbia, it must ensure that Occupational Health and Safety requirements of those jurisdictions are adhered to, including BC OHS Regulation s.5.53-5.55 and the Occupational Health and Safety Code Alberta Regulation 191/2021 ABOSHS244(1).

Trans Mountain shall:

Trans Mountain must meet all requirements set out in section 94 of the CER Act, paragraphs 6.5(1)(f) and 6.5(1)(g) of the OPR, and subsection 54(1) of the OPR as they relate to exposure to airborne contaminants that may be generated by the specific welding, burning, or related processes. As the TMEP has activities occurring in the Provinces of Alberta and British Columbia, it must ensure that Occupational Health and Safety requirements of those jurisdictions are adhered to, including BC OHS Regulation s.5.53-5.55 and the Occupational Health and Safety Code Alberta Regulation 191/2021 ABOSHS244(1).

Compliance tool used: Inspection Officer Order (IOO)

Regulatory requirement:

Relevant section(s):

Company action required:

  1. By 10 February 2023, provide to the Inspection Officer for review, an air monitoring study (Study) of pipeline welding fume exposure. The Study must demonstrate welders, support workers’, and TMEP inspectors’ breathing zone exposure levels on all sides of the pipe where routine pipe welding activities would occur. The Study must also assess breathing zone exposure levels of workers conducting and participating in the welding activities inside pipeline welding enclosures. Suggested (but not required) factors to consider in the Study:
A. Type of welding process (manual or automated), the size and thickness of pipe, duration of weld time, and material being welded;
  1. Type of welding rod (include the applicable Safety Data Sheet)
B. Conditions at time of survey – ambient weather information, number of persons inside the enclosure, and details of the style of enclosure, whether the enclosure is partially or fully enclosed, and whether the enclosure has general ventilation or not.
2. By 10 February 2023, establish a minimum standard for RPE where an:

a. exposure assessment has not been conducted;
b. an ECP is not in place; and
c. an effective means of natural, mechanical or local exhaust ventilation is not practicable. 3. Whenever an ECP exists, ensure that it meets or exceeds the minimum standard for RPE established by Trans Mountain under measure 2 of this Order. 4. Effective immediately, ensure that Trans Mountain is carrying out oversight activities to enforce the ‘Health and Safety Management Plan TMEP’ Document # 01-13283-GG-0000-HS-PLN-0001 R5 Appendix A Section 31: Respiratory Protection 31.1.2 across the Project. 5. By 28 February 2023, conduct an analysis of its oversight model, as outlined in ‘Health and Safety Management Plan TMEP’ Document # 01-13283-GG-0000-HS-PLN-0001 R5, section 7.0: TMEP Roles and Responsibilities, and develop corrective and preventive actions based on the analysis to ensure that TMEP representatives are aware of and ensuring that these specified measures are being implemented.

Due date: 2023-02-28

Date closed: 2023-03-10
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 3 - CNC 1 - Open excavation road 77

Date & time of visit: 2022-12-08 10:30

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) observed an excavation adjacent to a public roadway. TMEP told IOs that no work had occurred or been planned at the location that day. IOs observed that while fencing was present to block off the stairs, the stair access was open when the CER arrived; presumably, it was left open to public access overnight. In addition, the front side of the excavation was not fenced off in any way to prevent unintended access from the project personnel, the public, or animals.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

TMEP shall ensure the excavation at road 77 is secured in accordance with the HSMP and PSSP.

Due date: 2022-12-08

Date closed: 2022-12-08
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 4 - NNC - Contractor oversight

Date & time of visit: 2022-12-06 15:00

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) observed and were informed that Trans Mountain inspectors are regularly in the field and conducting inspections. The CER notes that while the Trans Mountain craft and safety inspection team is conducting inspections and verifying the safety of workers in the field, there appears to be a focus on acute hazards rather than chronic hazards, in addition to safeguarding. Examples include: 

Orders to address the deficiencies noted in the CER's observations have been issued to TEAM5B by WorkSafeBC. 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

  1. Trans Mountain shall develop a corrective action plan to address the described deficiencies. The corrective actions shall be implemented across the Trans Mountain Expansion Project and not restricted to Spread 5B. The corrective action plan shall outline the dates for implementation across the project. CER will verify the implementation of the corrective actions across the project during future CVAs. 
     
  2. Further, Trans Mountain has a requirement to ensure that its contractors meet their provincially legislated requirements, including all WorkSafeBC requirements. Trans Mountain shall ensure that all issues identified by WorkSafeBC during this inspection are shared with and equally addressed by all of its contractors in British Columbia.   
     
  3. Similarly, Trans Mountain shall review the Alberta Occupational Health and Safety legislation with respect to the issues identified by WorkSafeBC and ensure that these issues are identified and addressed (where applicable in legislation) with all contractors in Alberta.  

Due date: 2023-02-03

Date closed: 2023-03-10
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - Electrical grounding

Date & time of visit: 2022-12-07 12:24

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) observed several generators and light stands at road 18 that were not grounded. No information was provided to the IOs during the inspection indicating that the generators did not require grounding. The generators in question appeared not to be the type that does not require grounding, such as the light stand at road 71. Per the TMEP HSMP - Appendix A section 10.2.4 All electrical equipment must be properly grounded and/or bonded.

Post inspection:



 

Compliance tool used: No compliance tool used

Observation 6 - NNC - walking under counterweights road 28

Date & time of visit: 2022-12-06 15:00

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) performed an inspection at road 28. Several side booms were observed holding suspended loads with counterweights extended. During the FLHA review, the contractor told CER not to walk under the side boom counterweights. Despite this, CER observed workers walking under the extended boom and the counterweights of the side boom due to the site congestion. The practice continued even after WSBC Officers stood down the work to address this and other issues on the site.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

  1. Describe the actions TMEP will take to prevent a recurrence of the unsafe situation described in the observation.

Due date: 2023-01-13

Date closed: 2023-02-27
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program