Compliance verification activity type: Emergency Response Exercise
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Trans Mountain Pipeline ULC
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
[Ensure TMPU is prepared to respond to an emergency. Verify that response actions are based on the EPM and company procedures (is the company doing what it said it would do); assess whether the EPM and procedures protect the health and safety of the public and responders, property and the environment; determine whether exercise objectives were met; and ensure that no effects or potential effects result from participants’ actions or lack of actions. Full scale exercise on 21 June 2022 which will include IMs and external parties.]
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Background Information and Exercise Objectives
Date & time of visit: 2022-11-09 08:00
Discipline: Emergency Management
Categories:
Facility:
Observations:
A Canada Energy Regulator (CER) Emergency Response Exercise Evaluation Team (evaluation team) attended the Trans Mountain Training Day (November 8th) and the Trans Mountain Alberta District Full Scale Exercise (November 9th) at the Coast West Edmonton Hotel and Conference Centre and at the Trans Mountain Gainford Station, approximately 80 kilometers west of the hotel. The evaluation team included 3 CER Emergency Management Specialists – one of which participated in Unified Command, 1 CER Safety Specialist that participated as a Safety Officer, 2 CER Environmental Specialists – one of which participated in the Environment Unit and 1 CER Communications Specialist that participated as an Information Officer. As indicated by Trans Mountain, the exercise was focused on providing an opportunity for response personnel to demonstrate and practice the implementation of the Trans Mountain Pipeline Emergency Response Plan (ERP) for an incident originating from the Trans Mountain Pipeline and impacting Wabamun Lake. Exercise Objectives: ICP Objectives
Compliance tool used: No compliance tool used
Observation 2 - Notification and Reporting
The level of emergency was determined to be a Level 3 in accordance with the company's ERP and Incident Classification Matrix. An incident name was established, and external notifications were simulated as part of the scenario as per incident reporting requirements under the OPR. Notifications were conducted as per the Trans Mountain Pipeline ERP and GRP’s and were placed in an appropriate time. CER staff observed that Trans Mountain took the opportunity to use the exercise function in the online event reporting system (ERS) and promptly made the required notification to the CER.
Observation 3 - Environment
Discipline: Environmental Protection
Observation 4 - Safety
Discipline: Safety Management
Observation 5 - Response Management
Observation 6 - Communications
Observation 7 - Interoperability with response agencies and organizations
Observation 8 - NNC - Offensive Materials on Hardhat
Discipline: Management System
During the Training day portion of the EM exercise held at the Trans Mountain Gainford Station, CER Inspection Officer (IO) observed an offensive hardhat sticker on the back of a worker’s hat. The sticker was a homemade label maker type of sticker citing a sexually suggestive term. The CER IO raised their concerns directly with the worker stating it was offensive and not appropriate for the workplace. The worker immediately removed the sticker. The IO also shared the issue with the Senior EHS Advisor, Alberta District who was on site for the training and exercise. CER IO notes that inappropriate materials have been identified on several other activities:
Compliance tool used: Notice of Non-compliance (NNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Corrective actions were issued as part of CV2223-121 (Field Inspection, Spread 3/4A) and are expected to address this non-compliance. The sticker observed on site was immediately removed. No additional corrective actions or submissions are required to address this NNC in this activity.
Due date: 2023-11-09
Date closed: 2022-11-09 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Full relief granted
Compliance achieved: Yes
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program