Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans-Northern Pipelines Inc.
Operating company: Trans-Northern Pipelines Inc. (TNPI or Company)
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
The purpose of these inspections is to verify compliance with the Canadian Energy Regulator Act, the Canadian Energy Regulator Onshore Pipeline Regulations, CSA Z662, and any other relevant plans, manuals, and procedures. The primary focus area of these inspections will be the Environmental Protection Program, its implementation at facility operations, as well as operations & maintenance activities (O&M Activities), primarily integrity dig sites and reclamation of those sites. The scope of these inspections will include, but may not be limited, to pre-disturbance planning for O&M Activities, surface water management at facility sites, deactivated facilities, and follow-up to previous CVAs having occurred in 2019, 2020 and 2021, as well as the general state of regulated facilities.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Stations - General - Environment
Date & time of visit: 2022-09-07 08:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
CER Officer inspected several stations on TNPIs System, including the: Saint Clet Transition Farran's Point Station Prescott Junction Belleville Meter Station Deseronto Pump Station Ste Rose Junction The main themes of observations are summarized below, grouped by subject. Surface Water Management and Containment Systems (swales, berms, sumps, oil water separators)
Compliance tool used: No compliance tool used
Observation 2 - Information caviardée conformément au paragraphe 144(5) du Code canadien du travail
This information has been redacted pursuant to Section 144(5) of the Canada Labour Code
Observation 3 - Mirabel Station
Date & time of visit: 2022-09-08 09:00
Discipline: Administrative
Observation 4 - Maintenance Activities
Date & time of visit: 2022-09-07 14:30
Operations and Maintenance Activities (O&M)were observed at four locations, each at a different stage of the process. Before the inspection began, the CER Officer requested TNPI's O&M schedule to assist with planning, which TNPI Representatives provided as requested and required. The first O&M site inspected was a series of digs which had been completed in the last year with the site reclaimed to its pre-work conditions.
Observation 5 - Pipeline Right-of-Way (RoW) - General
Date & time of visit: 2022-09-08 13:30
Discipline: Damage Prevention
Work in Prescribed Area
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program