Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Trans Mountain Pipeline ULC
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Electrical inspection of Trans Mountain Expansion Project to verify compliance to NEB Certificate OC-065 Conditions 30 and 101.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - Kamloops Pump Station
Date & time of visit: 2022-10-17 13:00
Discipline: Integrity Management
Categories:
Facility:
Observations:
The Kamloops pump station has two separate pump stations, one for Line 1 and one for Line 2. The inspection scope was limited to the new Line 2 pump station electrical equipment. Line 2 has its own substation feed four 4.16 kV Variable Frequency Drives (VFDs) used to control 4x 5000 HP motors and the four new pumps from a 15/125 MVA, 138/4.16 kV transformer Line 2 also feeds a 4.16kV/600V Station Service Transformer (SST). CER staff inspected the Substation and observed the following:
Compliance tool used: No compliance tool used
Observation 2 - Black Pines Pump Station
Date & time of visit: 2022-10-18 13:00
Black Pines pump station has two new lines, Line 1 and Line 2. The station is fed from a 15/25 MVA 138/4.16 kV transformer. Line 1 feeds 2 x 2500 hp pump motors and Line 2 feeds 2 x 5000 hp pump motors through respective VFDs. 4.16 kV bus supplies to a 4.16 kV/600 V SST. The scope of the inspection was to check the substation yard, VFDs and respective protection systems, UPS system, pumps stations, emergency generator and electrical grounding in all these facilities. CER Staff inspected the VFD Building and observed the following:
Observation 3 - Kingsvale Pump Station
Date & time of visit: 2022-10-19 09:30
Kingsvale pump station is a common facility for the existing Line 1 and new Line 2 pump stations. The facility is fed from a 15/20/25 MVA 138/4.16 kV transformer which feeds both Line 1 and Line 2 through their independent medium voltage switchgear. Line 2 feeds 3 x 5000 hp motors through their respective VFDs. The 4.16 kV bus also feeds a 4.16 kV/600V SST. The scope of the inspection was to inspect the substation yard, Line 2 VFDs, protection system of the associated motors, UPS system, the motors and the associated pumps, grounding system and emergency generator. CER Staff inspected the VFD Building and observed the following:
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program