Compliance Verification Activity Report: CV2021-328 - Husky Oil Operations Limited

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2021-328
Start date: 2021-01-11
End date: 2021-01-19

Team:

Regulated company: Husky Oil Operations Limited

Operating company: Husky Oil Operations Limited

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

Verify compliance to the Onshore Pipeline Regulations (OPR) and CER Damage Prevention Regulations - Obligations of Pipeline Companies (DPR-Obligations) with a focus on third party oversight procedures.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - Part 1 Document Review - General Observations

Date & time of visit: 2021-05-06 12:00

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Part 1 of this CVA consisted of documentation to be reviewed by CER Inspection Officers (IOs). Husky submitted various documents as well as additional responses and clarifications in a separate document:

Compliance tool used: No compliance tool used

Observation 2 - Part 2 Virtual Meeting and Presentation - General Observations

Date & time of visit: 2021-07-06 13:00

Discipline: Damage Prevention

Categories:

Facility:

Observations:

A meeting (virtual) was held with Husky/Cenovus representatives on 6 July 2021 as Part 2 of the CVA in lieu of the planned field component given that there were no third party activities to observe near Husky’s pipelines during the past fiscal year. 

The following Damage Prevention Program requirements were discussed in order to inform Husky of the CER expectations, provide guidance and identify possible areas for improvements (presentation attached):

IOs noted the following areas for improvements by Husky:

Compliance tool used: No compliance tool used

Observation 3 - IR#1 - Technical Guidelines - Section 15 of the DPR-Obligations

Discipline: Damage Prevention

Categories:

Facility:

Observations:

In response to the initial Information Request, Husky briefly detailed its guidelines that third parties (e.g., contractors) must follow when sending requests for written consent referred to in paragraph 7(1)(a) or 10(1)(a) of the CER DPR-Authorizations. However, a documented copy was not provided and it was not indicated how Husky makes those guidelines public.

Additional information is required at this time.

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

The following is requested:

Due date: 2021-06-28

Date closed: 2021-07-05
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 4 - Obligations Following a Request to Locate - Section 6 of DPR-Obligations

Date & time of visit: 2021-07-06 15:00

Discipline: Damage Prevention

Categories:

Facility:

Observations:

IOs reviewed the Husky Energy Line Locator Scope of Work and Husky Ground Disturbance Damage Prevention Procedure (GDDP). Husky indicated that it uses third party contractor for all ground disturbance work on the CER-regulated pipelines. The documentation reviewed addressed the requirements for marking the pipes' location as per DPR-Obligations s.6(1)(b) and to provide line locating information as per DPR-Obligations s.6(1)(c).

The documentation submitted for review did not provide information pertaining to the written "safety practices to be followed" and that are to be provided following a locate request to the person that intends to undertake facility construction or ground disturbance in order to inform them on how to safely carry out the work in the vicinity of the pipe (pursuant to paragraph 6(1)(a) of the DPR-Obligations).

Information Requests were sent to Husky/Cenovus and responses were reviewed by IOs. This regulatory requirement was also discussed during a meeting on 6 July 2021. IOs explained that for written safety practices to meet the intent of the regulations, it is expected that they be provided following a locate request and be associated with the locate information provided on the field. Such practices are to be applied on the field by the person(s) performing the work to ensure their safety and prevent damage, and as such should be site-specific and appropriate for the audience (e.g., contractor, landowner). 

The IOs noted the following deficiency:

A notice of non-compliance was issued.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

IR#2a

The following is requested:

IR#2b

The requirements under paragraph 6(1)(a) were clarified during a meeting with Husky/Cenovus representatives on 6 July 2021. The following is requested: NNC

The following is required:

Due date: 2021-09-15

Date closed: 2021-10-04
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - Obligation to Report - Section 11 of the DPR-Obligations

Date & time of visit: 2021-07-06 15:00

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Husky submitted its Ground Disturbance Damage Prevention Procedure for review by the IOs. This document contained information pertaining to the reporting requirements specified in section 11 of the DPR-Obligations by referencing the requirements as per the excerpt below:

Non-immediate notifications to the NEB using the OERS specific to ground disturbance events are:
  • unauthorized activities under the NEB Act and Pipeline Damage Prevention Regulations – Authorizations (DPR-A);
  • pipeline damage and consent suspensions under the Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies (DPR-O). 


The reporting requirements pursuant to section 11 of the DPR-Obligations were further discussed during a meeting with Husky/Cenovus representatives on 6 July 2021, where they indicated that the company has procedures for the reporting of incidents and referenced other company documents that apply. However, it was unclear how the procedures applied to the reporting of DPR-A contraventions (contravention events) related to facility construction or the operation of vehicle or mobile equipment across the RoW (not only specific to ground disturbances). The linkages between the patrols conducted by the company and the reporting of unauthorized activities or contraventions events discovered was also not evident.

An Information Request was sent to Husky/Cenovus and responses were reviewed by IOs. Husky/Cenovus has specified that page 37 of the Corporate Ground Disturbance Damage Prevention Procedure (GDDP) explains the reporting required under section 11 of the DPR-Obligations. 

Upon review of the documentation and consideration of the information provided, the following deficiencies were noted by the IOs:

Therefore, the IOs have determined that Husky/Cenovus did not demonstrate compliance with this requirement.

The CER DPR guidance notes provides additional information to assist pipeline companies in understanding the regulatory requirements that apply to them. Guidance specific to section 11 is available on the CER's website - CER – Guidance Notes – Canadian Energy Regulator Regulations for Pipeline Damage Prevention (cer-rec.gc.ca) and provides a list of unauthorized activities that are reportable to the CER:

A notice of non-compliance was issued.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

IR#3

The following is requested:

If supporting documentation is available, you may provide a copy of the specific applicable pages.


  NNC

The following is required:

Due date: 2021-09-15

Date closed: 2021-10-04
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program