Compliance verification activity type: Field Inspection
Team:
Regulated company: NOVA Gas Transmission Ltd.
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
NGTL 2021 - Brewster Section: Assess field implementation of construction safety manual and project specific safety plans for ongoing construction activities; worker tasks including identification of hazards and appropriate controls relevant to the job tasks via hazard assessments; company implementation COVID-19 safety protocols; company oversight.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - General Observations - Day 1
Date & time of visit: 2021-10-13 08:00
Discipline: Safety Management
Categories:
Facility:
Observations:
General Observations - Day 1 North Saskatchewan River HDD
Compliance tool used: No compliance tool used
Observation 2 - General Observations - Day 2
Date & time of visit: 2021-10-14 06:30
General Observations - Day 2
Observation 3 - Indigenous Monitor Observations
Discipline: Indigenous Monitoring
Legal Disclaimer re the Written Observations/Report provided by the Indigenous Monitors.The following section contains independent observations made by an Indigenous Monitor who accompanied the Canadian Energy Regulator Inspection Team during this CVA, as part of the CERs’s commitment to the NGTL IAMC’s Indigenous Monitoring Program. They are reproduced and publicized within my report for greater transparency. They are not my conclusions but represent one source of information among others I have considered throughout the CVA along with my own direct observations and information received from the company.Indigenous Monitor Observations
Observation 4 - CNC - 1 - Pipeline Coaters Crew
Date & time of visit: 2021-10-14 08:30
CNC - 1 - Pipeline Coaters Crew
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Due date: 2021-10-14
Date closed: 2021-10-14 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 5 - CNC - 2 - Trench Box Components
Date & time of visit: 2021-10-13 11:30
CNC - 2 - Trench Box Components
- Replace or repair the wire-lock clevis pin on the trench box
Due date: 2021-10-13
Observation 6 - Mainline and Tie-In Welding work processes
Compliance tool used: Information Request (IR)
Due date: 2022-03-25
Date closed: 2023-01-23 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program