Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Kinder Morgan Canada Inc
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
TMX Spread 2 - Assessing implementation of EPP and associated resource specific plans for ongoing construction, including clean-up and reclamation activities and Project hand-over. Focus on watercourse and wetland crossings, including erosion and sediment control, as well as sites of Indigenous significance.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - General Observations
Date & time of visit: 2022-09-28 12:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
Reclamation - Reclamation measures were observed at several locations along the right-of-way (RoW). - Animal tracks (deer, moose) were observed in some reclaimed areas. Two moose were observed on the reclaimed RoW in the vicinity of wetland WT-386A. - Recontouring appeared consistent with off RoW topography. - Coarse woody debris was observed in areas where required. - Company Representatives provided the following general information about reclamation on Spread 2:
Compliance tool used: No compliance tool used
Observation 2 - Corrected Non-Compliance (CNC) No. 1 - Spill Kits
Date & time of visit: 2022-09-28 10:00
At Maskuta Creek (AB-188, KP 326.110), clean-up and bridge removal activities were in progress with multiple pieces of heavy equipment working in the vicinity of the fish-bearing watercourse. No large barrel-style spill kits (i.e., containing materials to contain a spill to water) were observed on either bank. Although the equipment is required to carry (smaller) spill kits, they do not contain material (e.g., absorbent booms) appropriate for responding to a spill to water. Trans Mountain provided photographs later in the day showing that a barrel-style spill kit had been placed on each bank and the EI indicated that clean-up crews were reminded to keep the spill kits on site until equipment has left the area. No further corrective action is required.
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
1. Position spill kits at both sides of the watercourse crossing. 2. Provide a reminder to workers that spill kits are required to remain in place at all stages of construction.
Due date: 2022-09-29
Date closed: 2022-09-29 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - CNC No. 2 - Idling Vehicles
The inspection occurred in the vicinity of KP 303 for approximately one hour. Over that time, three separate instances of unoccupied idling pick-up trucks were observed. No pre-heating/cooling of the vehicles was necessary as the weather at the time was 16oC (indicated in IO's vehicle upon leaving site) and there was no rain or wind. In each instance, Trans Mountain representatives spoke to the appropriate personnel to have the vehicles turned off. No explanations were provided for the idling. Trans Mountain provided a reminder to all crews by way of a morning bulletin, which was provided to the IO prior to leaving the field. No further corrective action is required.
1. Turn off idling vehicles. 2. Provide communications to workers regarding this issue.
Observation 4 - Notice of Non-Compliance (NNC) No. 1- Inappropriate Workplace Materials
Date & time of visit: 2022-09-28 11:30
Discipline: Management System
At approximately KP 303, a worker was observed with a hardhat sticker of an offensive hand gesture and an individual’s initials on it. Company Representatives indicated there is zero tolerance for these materials in the workplace and that reminders would be sent to all crews and that the sticker in question would be removed/covered. Prior to leaving the field, Trans Mountain provided confirmation that the sticker was removed/covered and indicated that a communication bulletin was provided to all crews. CER Inspectors attended Trans Mountain's inspectors meeting the following morning at which a reminder was provided regarding this matter. Officers note that inappropriate materials have been identified on several other activities:
Compliance tool used: Notice of Non-compliance (NNC)
Due date: 2023-01-16
Date closed: 2023-02-14 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 5 - NNC No. 2 - Roundcroft Creek
Date & time of visit: 2022-09-27 12:15
Roundcroft Creek is one of seven (7) watercourses on Spread 2 that are subject to a FIsheries Act Authorization Also Acting as a Permit Under the Species at Risk Act (Authorization) as it provides critical habitat for Athabasca Rainbow Trout (listed as Endangered under Schedule 1 of the Species at Risk Act). The Authorization outlines conditions that apply to work at Roundcroft Creek, including conditions related to erosion and sediment control. A vehicle crossing (clear-span bridge) was in place. The bridge deck was muddy and the wingwalls were covered in mud splatter. The state of the bridge and risk for introduction of mud into the watercourse and/or riparian buffer was discussed with Company Representatives who indicated that it's a high-travel area and that the bridge had been repaired and scraped of mud frequently but would be added to the corrective action log for additional maintenance. At the time of the inspection, restoration activities had occurred within the bed and banks of the watercourse. Various erosion and sediment control measures were in place around the site, though some berms were damaged by vehicle traffic and did not appear functional. A sediment fence (constructed with filter fabric) and a keyed edge were in place immediately upslope of the riparian buffer. A small area of the keyed edge appeared to be slumping, and an area of sediment deposition (approximately 2.5 m2 and 1-3 cm deep) was observed within the riparian buffer approximately 1 m from the water. Discussions were held with Company Representatives about the sediment deposition, which may have occurred from an event in July 2022, though photographs provided from the event did not show the area in question. Given that sediment deposition has occurred within the riparian buffer, and within 1 m of the fish-bearing watercourse, the IO has concluded that the erosion and sediment control measures at this location were inadequate. The IO consulted with biologists at Fisheries and Oceans Canada (DFO) in reaching this determination and notes that DFO was scheduled for a site visit at this location within 2 weeks of this activity.
1. Provide details of any discussions held with DFO (related to Roundcroft Creek) during the site visit in October 2022. Include any information related to erosion and sediment control, including the use of filter fabric (vs. impermeable material) and maintenance of erosion and sediment control measures. 2. Outline any changes or additions to erosion and sediment control measures at Roundcroft Creek and the frequency of planned inspections and maintenance of these measures. 3. Provide a timeline for completing final grade in this area.
Due date: 2023-01-13
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program