Compliance verification activity type: Field Inspection
Team:
Regulated company: Enbridge Pipelines Inc.
Operating company: Enbridge Pipelines Inc.
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Inspection of the Enbridge Line 3 decommissioning activities related to Segment 4 in Manitoba (KP 980.344 Ex-Cromer to 1242.403 Gretna Terminal).
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - General Observations
Date & time of visit: 2021-09-02 16:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
.Overall Observations
Compliance tool used: No compliance tool used
Observation 2 - IR No. 1 - Labelling of Hazardous Materials
The MSDS for One Shot XS indicates that the solution is hazardous to human health and fish and warns users to prevent contact with skin and flush immediately if contact occurs. The solution, although diluted at a 40:1 ratio, was observed in an unlabeled container and the lid was not secure.The Decommissioning EPP does not outline requirements for labelling hazardous materials, however Section 47 of the OPR requires "A company shall develop, implement and maintain a safety management program that anticipates, prevents, manages and mitigates potentially dangerous conditions and exposure to those conditions during all activities relating to construction, operation, maintenance, abandonment and emergency situations."In reviewing the Project's documentation and requirements, the Officer was unable to locate the Construction Safety Manual (or equivalent) for the Decommissioning Activities.
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
Due date: 2021-10-01
Date closed: 2021-09-30 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - IR No. 2 - Soil Sampling Results from MB-RF-7019-1
When crossing the track to 7019-1 site the Officer and IAMC Indigenous monitor smelled a strong VOC odor that appeared to be associated with one rig mat that had an area of staining. Company rep stated they smelled manure/wet wood but checked it with their 4-head gas monitor and did not get a hit. Enbridge confirmed that when the mats are removed they will collect a soil sample from below the rig mat of concern to confirm contaminants have not entered the soil. Enbridge stated it will conduct confirmatory sampling under the potentially contaminated rig mat after its removal.
Provide the sampling results upon receipt, and if exceedances are identified explain what Enbridge has or will do to address any exceedances.
Due date: 2021-10-15
Observation 4 - IR No. 3 - Environmental Training
Section 5.3 of the EPP states "Ensure construction foremen have the requirements associated with spill containment and clean-up of equipment leak. Ensure Contractor equipment operators and foremen are aware of the Fuels and Hazardous Materials Spill Contingency Plan [FHMSCP] (Appendix D4)." One Operator the Officer spoke with, and their Foreman, explained the correct steps to implement, but neither were able to name or even generally refer to the FHMSCP. Enbridge provided the training slide deck that is used for the Level 1 training which the Operator and all other workers are required to take. The applicable slide for Environmental incidents and Spills outlines the requirements for reporting environmental incidents and spot spills, but does not include any information on what actions they should take in the event of spills (ex: steps outlined in the FHMSCP). Given the first step in the FHMSCP states "the first person on the scene will follow the actions presented", it is unclear how the training provided will ensure that all workers on site are aware of the steps to take in the event of a spill when no details on those steps are provided in the training.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program