Compliance verification activity type: Field Inspection
Team:
Regulated company: NOVA Gas Transmission Ltd.
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Safety oversight of construction activities of NOVA Gas Transmission Ltd. (NGTL) Clearwater West Expansion Project. Field Inspection of Grande Prairie Mainline Loop No. 3 (Elmworth Section 1) and Loop No. 2 (Huallen Section). Assess compliance with the Onshore Pipeline Regulations (OPR), for the safety management program, including worker safety, contractor oversight and construction safety manuals / site specific safety plans. Observe compliance with respect to Canada Labour Code Part II, where applicable.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Project Yard
Date & time of visit: 2019-12-12 17:00
Discipline: Safety Management
Categories:
Facility:
Observations:
Compliance tool used: No compliance tool used
Observation 2 - Elmworth Section
Date & time of visit: 2019-12-10 17:00
Observation 3 - Huallen Section
Date & time of visit: 2019-12-11 17:00
Observation 4 - Contractor Oversight
Date & time of visit: 2019-12-12 16:00
Observation 5 - Information caviardée conformément au paragraphe 144(5) du Code canadien du travail
This information has been redacted pursuant to Section 144(5) of the Canada Labour Code
Observation 6 - IR1 Compressed breathing air compressors
Date & time of visit: 2019-12-11 13:30
While onsite, CER inspectors were unable to determine if the air compressors used for supplied air have been inspected as required.Alberta OHS applies with respect to the contractor's employees (workers), as is noted in the site specific safety plans submitted as the construction safety manual under Onshore Pipeline Regulations (OPR) section 20. The Alberta OHS Code requirement, Personal Protective Equipment, Respiratory Protective Equipment, Quality of breathing air, s. 249, states:
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
For the purpose of completing this inspection, provide documentation demonstrating that the company ensures its contractors' compliance to the Alberta OHS Code Part 18, Personal Protective Equipment, section 249, with respect to respiratory protective equipment.
Due date: 2020-01-13
Date closed: 2020-01-15 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 7 - IR2: Field Level Hazard Assessment Review
Date & time of visit: 2019-12-11 15:00
CER inspectors were told that the TC Energy lead safety inspector routinely reviews contractors' Field Level Hazard Assessment (FLHA) for the purpose of quality assurance. CER inspectors were not able to make inquiries to the lead safety inspector as he was unable to participate in the inspection at the time inspectors were on site.
For the purpose of completing this inspection, provide the documented results of TC Energy's in depth review of the contractor's Field Level Hazard Assessments.
Due date: 2020-01-31
Date closed: 2020-01-31 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 8 - IR3: Coating Substance - Worker Protection
Date & time of visit: 2019-12-11 13:00
Observation 9 - IR4: Outdoor atmospheric testing - Coating
For the purpose of completing the inspection, provide documentation demonstrating that the company has assessed the immediate work area of the coating crew to determine if appropriate respiratory protection controls are in place.
Due date: 2020-01-17
Date closed: 2020-01-17 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 10 - IR5: Direct Pipe Install
Date & time of visit: 2019-12-10 13:30
The Direct Pipe Installation (DPI) activity was not observable at the time of the field inspection. For purpose of inspection, provide a schedule with dates of the stages of the DPI, in particular the dates of worker entries into the pipe that are planned, and the purpose of each planned entry. The inspector's interest is in the DPI method, is on safety risks and controls, primarily confined space entry, as managed by the company with respect to the DPI contractor and its workers.
Provide the DPI schedule and information on the method and hazard controls during the DPI, particularly with respect to confined space entry.
Due date: 2020-01-22
Date closed: 2020-01-24 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program