Compliance verification activity type: Field Inspection
Team:
Regulated company: NOVA Gas Transmission Ltd.
Operating company: NOVA Gas Transmission Ltd.
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
CER field inspection in response to INC2022-149. Verify implementation of the construction safety manual, including contractor oversight, and whether adequate controls are in place to prevent a recurrence.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - Inspection Officer Order DRP-001-2022 - Pipe unloading
Date & time of visit: 2022-08-30 12:30
Discipline: Safety Management
Categories:
Facility:
Observations:
COMPANY TO WHOM THIS ORDER IS DIRECTED NOVA Gas Transmission Ltd. (NGTL) is a company conducting work associated with a regulated facility located near Bear Canyon, AB as part of the North Corridor Expansion Project. On or about 30-Aug-2022 at 10:30am MST, the undersigned Canada Energy Regulator (CER) Inspection Officer conducted a compliance verification activity (CVA) at the NGTL Bear Canyon stockpile yard in response to an incident that was reported to the CER on 26 August 2022. RELEVANT FACTS I, Inspection Officer #2927, designated as a CER Inspection Officer (IO) under subsection 102(1) of the Canadian Energy Regulator Act (CER Act), believe the following are the relevant facts relating to the issuance of this Order:
Compliance tool used: Inspection Officer Order (IOO)
Regulatory requirement:
Relevant section(s):
Company action required:
Inspection Officer Order DRP-001-2022: Measure 1
Due date: 2022-09-30
Date closed: 2022-09-27 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
There are no observations with outstanding follow-up
Observation 2 - Bear Canyon Stockpile Yard
Date & time of visit: 2022-08-30 10:00
Compliance tool used: No compliance tool used
Observation 3 - NNC 1 - Documenting Inspector Duties
Date & time of visit: 2022-10-26 12:00
CER Inspection Officers (IOs) have reviewed the construction safety manuals for the Westpath Delivery 2022 Raven River Section and the North Corridor Expansion Bear Canyon North Extension (CV2223-269 and CV2223-270, respectively). The safety-related responsibilities specific to NGTL Inspectors documented in the construction safety manuals are broad. For example, section 6.3.1 of the safety management plan for both projects states the Inspector is responsible for the following:
In response to CER's request for the safety-related duties and responsibilities for Inspectors, NGTL provided the following:
Some of the duties documented in the above responses are broad. For example, NGTL's response to IR 1.10 states that the General Inspector must ensure that the contractor implements their SSSP. Although the Inspector was making observations on various tasks being performed in the stockpile yard, no document explicitly directed the Inspector to verify the implementation of specific requirements of the SSSP. A general statement in the Inspector's duties to verify all aspects of the SSSP does not constitute explicit direction to the Inspector to fulfill their oversight responsibilities.
Paragraph 6.1(1)(a) of the OPR requires a company's management system to be explicit. Specific oversight duties or responsibilities should be identified and included or referenced in the documents that constitute the construction safety manual required by Section 20 of the OPR.
Compliance tool used: Notice of Non-compliance (NNC)
Due date: 2023-02-10
Date closed: 2023-03-03 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program
Observation 4 - Inspection Officer Order DRP-001-2022 (AMENDED) - Pipe unloading
Date & time of visit: 2022-09-27 12:44
COMPANY TO WHOM THIS ORDER IS DIRECTED NOVA Gas Transmission Ltd. (NGTL) is a company conducting work associated with a regulated facility located near Bear Canyon, AB as part of the North Corridor Expansion Project (NCE). BACKGROUND On 30 August 2022, the undersigned Canada Energy Regulator (CER) Inspection Officer (IO) issued order DRP-001-2022 to NGTL after conducting a compliance verification activity (CVA) at the NGTL Bear Canyon stockpile yard in response to an incident that NGTL reported to the CER on 26 August 2022. Specified measure 1 of the order requires NGTL to cease pipe unloading activities for the NCE. On 16 September 2022, NGTL provided a partial response to specified measure 1 of the order. In their response, NGTL included pipe unloading procedures and measures to ensure Inspector competency for North Star 2 and Red Earth sections only, stating a response for the Bear Canyon section would be sent at a later date. NGTL requested CER amend the order to allow pipe unloading to continue on North Star 2 and Red Earth, stating the rationale for the request was to enable the completion of construction in the Red Earth section before the 15 February caribou Restricted Activity Period (RAP). In reviewing NGTL's request, the IO considered Condition 25 on the Certificate of Public Convenience and Necessity GC-131, which states, "The Commission expects NGTL to make every effort possible to avoid work during the RAP in the Red Earth caribou range." The IO is satisfied with NGTL's response to specified measure 1 of the order for the North Star 2 and Red Earth sections, as detailed below. Therefore, it is reasonable to amend the order allowing pipe unloading work to continue for these sections. The cease work order remains in effect for the Bear Canyon section. On 21 September 2022, NGTL submitted a corrective and preventative action plan (CAPA) applicable to all NGTL CER-regulated worksites. The CAPA satisfies specified measure 2 of DRP-001-2022. GROUNDS FOR AMENDING ORDER
Company action Required:
Due date: 2023-09-30