Compliance Verification Activity Report: CV2223-270 - NOVA Gas Transmission Ltd.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2223-270
Start date: 2022-08-30
End date: 2022-08-30

Team:

Regulated company: NOVA Gas Transmission Ltd.

Operating company: NOVA Gas Transmission Ltd.

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

CER field inspection in response to INC2022-149. Verify implementation of the construction safety manual, including contractor oversight, and whether adequate controls are in place to prevent a recurrence. 

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Observations (no outstanding follow-up required)

Observation 1 - Inspection Officer Order DRP-001-2022 - Pipe unloading

Date & time of visit: 2022-08-30 12:30

Discipline: Safety Management

Categories:

Facility:

Observations:

COMPANY TO WHOM THIS ORDER IS DIRECTED

NOVA Gas Transmission Ltd. (NGTL) is a company conducting work associated with a regulated facility located near Bear Canyon, AB as part of the North Corridor Expansion Project. On or about 30-Aug-2022 at 10:30am MST, the undersigned Canada Energy Regulator (CER) Inspection Officer conducted a compliance verification activity (CVA) at the NGTL Bear Canyon stockpile yard in response to an incident that was reported to the CER on 26 August 2022. 

RELEVANT FACTS

I, Inspection Officer #2927, designated as a CER Inspection Officer (IO) under subsection 102(1) of the Canadian Energy Regulator Act (CER Act), believe the following are the relevant facts relating to the issuance of this Order: 

Compliance tool used: Inspection Officer Order (IOO)

Regulatory requirement:

Relevant section(s):

Company action required:

Inspection Officer Order DRP-001-2022: Measure 1

  1. Cease pipe unloading activities on the North Corridor Expansion Project until such time that the Inspection Officer has confirmed in writing that it is satisfied that NGTL has demonstrated that:
    1. contractor(s) unloading pipe on behalf of NGTL have written work procedures that are sufficient to perform the work safely and prevent recurrence of the incident that occurred on 26 August 2022; and
    2. NGTL representatives (e.g., inspectors) overseeing pipe unloading have the expertise, knowledge, and training to competently carry out their safety related responsibilities.
Inspection Officer Order DRP-001-2022: Measure 2
  1. Provide the Inspection Officer a written corrective and preventive action (CAPA) plan by 21 Sep 2022 describing how NGTL will:
    1. verify all contractors unloading pipe on behalf of NGTL at CER regulated worksites have effectively implemented work procedures that are adequate to perform the work safely and prevent a recurrence of the incident, and
    2. verify NGTL representatives (e.g., inspectors) overseeing pipe unloading activities at CER regulated worksites are trained and competent to fulfill their inspection role as it relates to worker safety.
Inspection Officer Order DRP-001-2022: Measure 3
  1. Implement the CAPA identified in measure 2 and provide the Inspection Officer with written updates every month commencing on 30 Sep 2022 until the CAPA has been completed.

Due date: 2022-09-30

Date closed: 2022-09-27
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

There are no observations with outstanding follow-up

Observation 2 - Bear Canyon Stockpile Yard

Date & time of visit: 2022-08-30 10:00

Discipline: Safety Management

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 3 - NNC 1 - Documenting Inspector Duties

Date & time of visit: 2022-10-26 12:00

Discipline: Safety Management

Categories:

Facility:

Observations:

CER Inspection Officers (IOs) have reviewed the construction safety manuals for the Westpath Delivery 2022 Raven River Section and the North Corridor Expansion Bear Canyon North Extension (CV2223-269 and CV2223-270, respectively). The safety-related responsibilities specific to NGTL Inspectors documented in the construction safety manuals are broad. For example, section 6.3.1 of the safety management plan for both projects states the Inspector is responsible for the following:

In response to CER's request for the safety-related duties and responsibilities for Inspectors, NGTL provided the following:

Some of the duties documented in the above responses are broad. For example, NGTL's response to IR 1.10 states that the General Inspector must ensure that the contractor implements their SSSP. Although the Inspector was making observations on various tasks being performed in the stockpile yard, no document explicitly directed the Inspector to verify the implementation of specific requirements of the SSSP. A general statement in the Inspector's duties to verify all aspects of the SSSP does not constitute explicit direction to the Inspector to fulfill their oversight responsibilities.

Paragraph 6.1(1)(a) of the OPR requires a company's management system to be explicit. Specific oversight duties or responsibilities should be identified and included or referenced in the documents that constitute the construction safety manual required by Section 20 of the OPR.

 

 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

  1. Provide a detailed list, grouped by role, of NGTL Inspector safety responsibilities during the construction of CER-regulated projects.
  2. Confirm that the responsibilities identified above will be included or referenced (i.e. document number) in the construction safety manual(s) for future CER-regulated projects.

Due date: 2023-02-10

Date closed: 2023-03-03
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program

Observation 4 - Inspection Officer Order DRP-001-2022 (AMENDED) - Pipe unloading

Date & time of visit: 2022-09-27 12:44

Discipline: Safety Management

Categories:

Facility:

Observations:

COMPANY TO WHOM THIS ORDER IS DIRECTED

NOVA Gas Transmission Ltd. (NGTL) is a company conducting work associated with a regulated facility located near Bear Canyon, AB as part of the North Corridor Expansion Project (NCE).

BACKGROUND

On 30 August 2022, the undersigned Canada Energy Regulator (CER) Inspection Officer (IO) issued order DRP-001-2022 to NGTL after conducting a compliance verification activity (CVA) at the NGTL Bear Canyon stockpile yard in response to an incident that NGTL reported to the CER on 26 August 2022. Specified measure 1 of the order requires NGTL to cease pipe unloading activities for the NCE.

On 16 September 2022, NGTL provided a partial response to specified measure 1 of the order. In their response, NGTL included pipe unloading procedures and measures to ensure Inspector competency for North Star 2 and Red Earth sections only, stating a response for the Bear Canyon section would be sent at a later date. NGTL requested CER amend the order to allow pipe unloading to continue on North Star 2 and Red Earth, stating the rationale for the request was to enable the completion of construction in the Red Earth section before the 15 February caribou Restricted Activity Period (RAP). 

In reviewing NGTL's request, the IO considered Condition 25 on the Certificate of Public Convenience and Necessity GC-131, which states, "The Commission expects NGTL to make every effort possible to avoid work during the RAP in the Red Earth caribou range." 

The IO is satisfied with NGTL's response to specified measure 1 of the order for the North Star 2 and Red Earth sections, as detailed below. Therefore, it is reasonable to amend the order allowing pipe unloading work to continue for these sections. The cease work order remains in effect for the Bear Canyon section.

On 21 September 2022, NGTL submitted a corrective and preventative action plan (CAPA) applicable to all NGTL CER-regulated worksites. The CAPA satisfies specified measure 2 of DRP-001-2022.

GROUNDS FOR AMENDING ORDER


Inspection officer order DRP-001-2022 is AMENDED, pursuant to subsection 69(2) of the CER Act.

Compliance tool used: Inspection Officer Order (IOO)

Regulatory requirement:

Relevant section(s):

Relevant section(s):

Company action Required:

  1. Cease pipe unloading activities on the North Corridor Expansion Project Bear Canyon Section until such time that the inspection officer has confirmed in writing that it is satisfied that NGTL has demonstrated that:
    1. contractor(s) unloading pipe on behalf of NGTL have written work procedures that are sufficient to perform the work safely and prevent recurrence of the incident that occurred on 26 August 2022; and
    2. NGTL representatives (e.g., inspectors) overseeing pipe unloading have the expertise, knowledge, and training to competently carry out their safety-related responsibilities.
2. Provide the inspection officer with monthly status updates commencing on 30 September 2022 until the CAPA provided under specified measure 2 in DRP-001-2022 (as it read prior to this amendment) is fully implemented.

Due date: 2023-09-30