Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans-Northern Pipelines Inc.
Operating company: Trans-Northern Pipelines Inc.
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Integrity and Emergency Management inspection of the Toronto Airport Terminal to verify compliance to the OPR, CSA Z662-19 and CLC.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Toronto Airport Terminal
Date & time of visit: 2022-05-19 09:00
Discipline: Integrity Management
Categories:
Facility:
Observations:
Introduction Trans Northern Pipeline Inc (TNPI)’s Toronto Airport Terminal includes:
Compliance tool used: No compliance tool used
There are no observations with outstanding follow-up
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program
Observation 2 - NNC No.1
Date & time of visit: 2022-05-19 12:00
Facility: TORONTO AIRPORT TERMINAL - Facility
The storage tanks fire protection system is powered by electricity. TNPI explained that they don’t have an alternate source of power capable of operating the fire protection system in the event of a power loss. This is a non-compliance to the OPR section 12 (c) and as a result a Notice of Non-Compliance (NNC) is issued to address this non-compliance. Update: On 30 June 2022, TNPI submitted the response to IR No.1.1 through which it was confirmed that the facility does not have a back up emergency power generator and that the Uninterruptible Power System (UPS) is not adequate to operate the manually operated valves (MOVs) during a power loss. TNPI is therefore also non-compliant to the OPR section 12(a). TNPI also submitted on 30 June 2022 a corrective action plan (CAP) to address this NNC. The CAP will address the non-compliances to the OPR section 12 (a) and (c) identified. However, CER inspectors have further questions regarding the timeline to complete the CAP.
Compliance tool used: Notice of Non-compliance (NNC)
Regulatory requirement:
Relevant section(s):
Company action Required:
On 29 March 2023, TNPI provided the following update: TNPI will install an emergency generator sized for the existing facility on or before the end of Q3 2023. This emergency generator will supply power to operate motor control valves for facility isolation/shutdown and the existing fire protection system. The reason for the faster turnaround is that TNPI has determined that the generator installed will be reevaluated once the new foam system design has been confirmed.
Due date: 2023-09-30
Observation 3 - NNC No.2 - Storage Tank Fire Protection System.
Date & time of visit: 2022-09-16 12:00
Discipline: Emergency Management
CER staff reviewed the information provided in response to IR 1.3 and virtually met with TNPI on 9 September 2022 to obtain clarifications on the information provided and to explain CER staff views on this matter. TNPI’s responses and supporting documentation provided did not demonstrate that it has an adequate fire protection system for the storage tanks at the Toronto Airport terminal. Although the design of the internal floating roof and fire protection system may have met the standards applicable at the time of construction, such combination of roof and fire protection system is no longer considered adequate for fire protection according to NFPA 11. CER staff notes that NFPA 11 is not a mandatory standard, but it is the industry reference and it is considered a good engineering practice by the National Fire Code of Canada. In the event of a tank fire, TNPI indicated that the following would occur: "TNPI will activate its emergency response plan and identify an Incident Commander. The TNPI Incident Commander will liaise with the appropriate personnel of the responding fire service and coordinate required Subject Matter Expertise (Firemaster Oilfield Services Inc.) and activate additional suppression resources; coordinated through service level agreements or directly with regional response contractors in the event that the incident has the potential to surpasses the capacity of the facility suppression system. Per agreements described in the Trans-Northern Pipelines Emergency Response Plan with QM Environment TNPI will request industrial fire- fighting capacities from Accuworx (Mississauga, ON) to support the facility and municipal response." The Toronto Airport Site Specific Emergency Response Plan (SSERP) includes a reference to QM Environment and Accuworx as stated above, but it does not provide any details on the capacity of those responders to address a tank fire. The pre-fire plan in Appendix C of the SSERP lists the resources available from the Tank Fire Specialist (Firemaster Oilfield Services Inc.) but no information is listed for the resources of QM Environment and Accuworx. TNPI has not provided a clear demonstration that a response involving the local fire service and external contractors, including regional response contractors such a QM Environment and Accuworx, would allow TNPI to extinguish a tank fire in a timely manner should the existing fixed fire protection system failed to extinguish a storage tank fire. Therefore, TNPI did not demonstrate that its emergency management program can adequately manage and mitigate conditions during a potential tank fire at the Toronto Airport terminal. Based on this information, and considering the risk associated with a potential tank fire at the Toronto Airport terminal due to its proximity to major highways and the Toronto Airport, CER staff has determined that TNPI is non-compliant to the OPR section 32 and a corrective action plan will be required.
On 29 March 2023, TNPI provided the following update: TNPI is working with a leading designer and constructor of tanks and storage facilities, to evaluate alternatives to address the fire protection systems for the storage tanks at the TA terminal. The scoping study is being finalized to determine the lead case to address the NNC, after which TNPI will progress into FEED and detailed engineering. The study has taken additional time to complete to assess design and execution complexities associated with existing and new environmental and permitting regulations for each alternative being considered. Over the next three months, TNPI expects to finalize the scoping study and preliminary execution documents and commence detailed engineering. Another update can be provided by June 30, 2023.
Due date: 2023-06-30