Compliance verification activity type: Field Inspection
Team:
Regulated company: Plains Midstream Canada ULC
Operating company: Plains Midstream Canada ULC
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Field inspection of O&M activities. Inspection of 2nd party oversight in accordance with the Damage Prevention Regulations.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Damage Prevention 2nd party field inspection
Date & time of visit: 2022-10-13 07:03
Discipline: Damage Prevention
Categories:
Facility:
Observations:
The Canada Energy Regulator (CER) Inspections Officers (IO) conducted a Damage Prevention inspection focusing on second party contractor oversight with Plains Midstream Canada ULC (Plains) on Oct. 13, 2022. IOs were on site to observe a Plains integrity dig on the Kerrobert Pipeline at the Empress 1-5 facility. The integrity dig followed an in-line inspection that identified anomalies on the 8” NGL pipeline. IOs attended Plains 2nd party tail gate meeting led by the Plains Construction Supervisor, who is a contract employee that has worked for Plains for several years. BSR (the project contractor) also discussed the work for the day. Topics discussed during the morning safety meeting included:
Compliance tool used: No compliance tool used
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program