Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Kinder Morgan Canada Inc
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
An early environmental inspection of Spread 6 and 7A focusing on implementation of mitigation measure commitments in the EPP, Resource Specific Mitigation Tables, SARA Permits and specific contingency plans prior to clearing activities. Focus areas will be Oregon Forestsnail salvage, archeological shovel testing/TLU sites and potential HDD watercourse crossing sites.
Compliance tool(s) used:
Facilities:
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
Observation 1 - General Observations
Date & time of visit: 2021-09-23 08:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
General ObservationsInspection team met with company representatives at the Imasco Minerals yard. The yard is located beside the Fraser River. The entire yard is poly-lined and filled with gravel for containment and sediment fence surrounds the perimeter. Erosion and sediment controls and equipment are stored at the yard. Parking is limited and workers are shuttled to work site. Waste bins for spill materials and other items were labeled as required. Most of the equipment arriving onsite is brand new. Signage was in place at all required locations and vehicles were observed maintaining the speed limit. Company representatives indicated they are planning to use this site at the Fraser River as a water withdrawal area.The pipeline will cross 4 golf courses on Spread 6 and 7A. The inspection team observed Ledgeview Golf Club at KP 1117+900. Most of the new pipeline on Spread 6 will parallel Line 1 whereas it deviates on Spread 7A.Inspection team observed the contractor laydown yard at KP 1160+00. Crews were seen conducting line locates and the boundaries were staked. A wetland is located within the area. Bird nesting mitigations during the nesting season was discussed with company representatives and they indicated they would be put in place during the bird window. There are 3 road crossings that will be completed in this area where workspace is limited and will likely be very technical to complete. Company representatives indicated a permanent retaining wall will be installed on the steep slope and sediment fence will be placed around the wetland.
Compliance tool used: No compliance tool used
Observation 2 - Heritage Resources
Date & time of visit: 2021-09-21 13:00
Discipline: Socio-Economic
Heritage ResourcesDuring the opening meeting company representatives stated they have obtained a Heritage Conservation Act Site Alteration Permit for some of the required sites but are still waiting for others to come in. Currently there are no construction activities at these sites, but Indigenous Monitors and Environmental Inspectors will provide regular monitoring of these areas during construction. The project crosses Popkum 2 Indian Reserve, Matsqui Main Indian Reserve and Tzeachten Indian Reserve. KP 1163+500Inspection team met with archeologists conducting shovel testing and they provided a detailed explanation of how they conduct their activities and a few locations they have tested. The areas being tested have a high potential for artifact discovery. A 5m grid is set up and holes are hand dug to a depth of 70 cm. The soil is screened using a ¼ inch mesh and all artifacts are collected and analysed. Company Indigenous Monitor accompanied the inspection team during the inspection of this site and provided details of their observations.
Observation 3 - Oregon Forestsnail Salvage
Date & time of visit: 2021-09-22 11:00
Oregon Forest SnailPopkum IR Area KP 1076+760 to KP 1077+180Inspection team requested and received a copy of the Species at Risk Act (SARA) Permit to review site specific mitigation measures. Resource Specialists set up two translocation plots and one control plot off RoW. Company representatives indicated the Resource Specialists were working with ECCC to develop the habitat in the relocation plots. Personnel are currently working on habitat enhancements of the plots (24m by 24m and 36m by 18m) including:
Observation 4 - Watercourse Crossings
Date & time of visit: 2021-09-15 09:00
Watercourses ObservedBC774c (S6) KP 1163+190Environmental feature and high-water mark flagging were in place.Company representatives stated:
Observation 5 - Wildlife
Date & time of visit: 2021-09-22 10:00
WildlifeThere are many wildlife species of concern and SARA listed species identified on Spread 6 and 7A. During the opening meeting these species were discussed and some of the responses from company representatives included:
Observation 6 - Indigenous Monitor Observation #1
Date & time of visit: 2021-09-23 14:00
Discipline: Indigenous Monitoring
Additional observations recorded by IAMC Indigenous Monitors participating in the CER inspection. Any compliance-related observations that require specific regulatory follow-up have been recorded above.Observation – Indigenous MonitorCVA BACKGROUNDThis Compliance Verification Activity was assigned February 2021 originally as Virtual CVA 2122-188. In March the Canada Energy Regulators decided to postpone it until summer since the scope was focused on the Species at Risk Act compliance and Trans Mountain Expansion Project hadn’t received the SARA permits. This CVA 2122-188 was reassigned as CVA 2122-118 and rescheduled for August 23-27, 2021 however due to the wild fire season CVA 2122-118 was postponed to September 20-24, 2021. CVA 2122-118: IO-IM MEET & GREETDate: September 8, 2021Two Indigenous Monitors met with two Canada Energy Regulators. Collectively the group reviewed the Compliance Verification Activity Scope. The scope for this CVA was to verify Species at Risk Act compliance and wildlife-related requirements. The Scope was adapted to the early phase of construction, the mitigation measures and implementation process plan for Trans Mountain Expansion Project Spread 6 and 7A. Besides the Environmental Alignment Sheets, the Resource Specific Mitigation Plan, and the Mitigation Plans provided to review for the SARA listed species of interest are:
Observation 7 - Indigenous Monitor Observation #2
Date & time of visit: 2021-09-22 17:00
Additional observations recorded by IAMC Indigenous Monitors participating in the CER inspection. Any compliance-related observations that require specific regulatory follow-up have been recorded above.Observation – Indigenous MonitorI attended this inspection with the CER, and my observations have been appropriately captured by the Inspection Officer observations. I have nothing further to add currently.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program