Compliance verification activity type: Field Inspection
Team:
Regulated company: NOVA Gas Transmission Ltd.
Operating company:
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Inspection of NGTL’s Berland River compressor station.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Berland River Compressor Station
Date & time of visit: 2021-10-20 11:15
Discipline: Integrity Management
Categories:
Facility:
Observations:
Integrity Management – Local Control Centre (Building) The discussions between CER inspectors and NGTL representatives and CER inspectors’ observations are summarized as follows:
Compliance tool used: No compliance tool used
Observation 2 - IR No 1 – Valve Maintenance Records
CER inspectors requested certain information that was not readily available during the inspection. They agreed with NGTL representatives that NGTL provide this information later.
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
Provide the following information:The maintenance records for the last 24 months for the following valves (including inspections, assessments, tests, and repairs):
Due date: 2021-11-22
Date closed: 2021-12-22 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - IR No 1.1 – Valve Maintenance Scope and Frequency (Follow up for IR No 1)
IR to be issued regarding follow up to IR No 1 – Valve Maintenance Records.
In response to IR No 1 – Valve Maintenance Records, NGTL submitted an attachment titled CV2122-327 ATTACHMENT 11 Valve Maintenance Records. This attachment disclosed two maintenance plans known as 102246 VLV&Op Insp and Servicing and 102247 VLV&Op Leak Insp/Cycle Test EMER VLV. Request:
Due date: 2022-04-25
Date closed: 2022-06-06 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 4 - IR No 2 – Station Leak Detection Survey
Provide the following information:
Date closed: 2022-04-08 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 5 - IR No 3 – Station Cathodic Protection Survey
CER inspectors requested certain information that was readily available during the inspection. They agreed with NGTL representatives that NGTL provide this information later.
Provide the summary of the station CP system survey result, including but not limited to, the survey date, the minimum potential value recorded for the station, and corrective actions completed or planned (if any).
Observation 6 - IR No 4 – Maintenance Interval for PSVs
Observation 7 - IR No 5 – Set Point for PSVs
During the inspection, CER inspectors observed apparent inconsistencies in some PSV maintenance reports such as for PSV tags # 0-PSV-0009 and B2-PSV-0061. The set pressures (for “Condition Received” and/or “Final Test”), as showed on the Final Inspection Test Reports appears to be higher than 110% of MOP.
Due date: 2021-12-10
Observation 8 - IR No 6 – Fuel Gas Supply for Turbines
Explain why the gas supplying the turbines’ fuel gas system was not odorized. If the decision is based on the gas lower explosive limit (LEL) consideration, specify the applicable LEL and the alarm set point (gas concentration) for the electronic gas detectors.
Observation 9 - IR No 7 – Removal of Paint and Cladding
CER inspectors observed that the paint is removed from a location on the Unit B discharge check valve. Also, the insulation cladding of the Unit A cooler discharge piping is damaged at the above-ground/below-ground transition area.
Observation 10 - IR No 8 – Operation of Unit’s Ventilation System
NGTL representatives explained that the compressor unit buildings are equipped with lower explosive limit (LEL) detections and fire eyes. Additional information is required.
Provide a detailed explanation of how the LEL detectors and fire eyes work with the compressor unit’s ventilation systems. Specify when the ventilation system start working or stop working based on LEL levels and/or fire detection.
Observation 11 - NNC No 1 - Open and Closed Positions and the Function of Major Valves
Date & time of visit: 2021-11-03 13:20
The open and closed positions and the function of several major valves within the station (e.g., Unit A discharge valve, valve GPM30-1-BV, valve GPM30-C-1SS-BLR, Unit B cooler isolation valve) were not clearly marked.
Compliance tool used: Notice of Non-compliance (NNC)
NGTL is required to:
Due date: 2022-05-27
Date closed: 2022-07-20 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 12 - NNC No 2 - Direction of Flow and/or Contents of Piping
Many piping segments throughout the station (e.g., piping for the scrubber, areal cooler, Unit A) did not have a marked flow direction and/or contents.
Date closed: 2022-06-30 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 13 - NNC No 3 - Follow up for IR No 5 – Set Point for PSVs
Date & time of visit: 2022-04-08 10:50
CER inspectors reviewed the information provided on 10 December 2021 by NGTL and during the follow-up meeting with NGTL and its contracting company (Access Valve) on 2 March 2022. NGTL confirmed that for the Berland River Compressor Station instance, where the Maximum Operating Pressure (MOP) is 8275 kPa, the maximum set pressure for PSVs (equivalent to 110% of MOP) should be 9102 kPa as per CSA Z662 Clause 4.18.1.2. TC Energy has been using an accuracy/tolerance of +/-3% for its PSVs in accordance with the ASME Boiler and Pressure Vessel Code Section VIII Division 1 - UG-155(d). Therefore, the company had been considering up to 9375 kPa (i.e., 9102 + 3% of 9102) as a maximum set pressure. TC Energy representatives recognized that allowing +3% on top of 110% of MOP permits certain PSVs to release at a pressure too high that would not meet the requirement of CSA Z662 Clause 10.9.5.5. TC Energy representatives stated that the company has started to implement a corrective action plan which involves the following:
Provide the following:
Date closed: 2022-07-11 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program