Compliance verification activity type: Field Inspection
Team:
Regulated company: TransCanada PipeLines Limited
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Verify compliance to the requirements contained within the Onshore Pipeline Regulations (OPR) and the CER Damage Prevention Regulations - Obligations of Pipeline Companies (DPR-Obligations) with a focus on third party oversight procedures. Field Inspection to include document review and site inspection of active third party crossing activity.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Damage Prevention Program Pre-Inspection IR
Discipline: Damage Prevention
Categories:
Facility:
Observations:
In preparation for the planned field inspection and to assist with document review, the CER IOs require information pertaining to the TransCanada PipeLines Limited (TCPL) Damage Prevention Program as required pursuant to section 47.2 of the OPR.
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
Due date: 2021-09-02
Date closed: 2021-11-04 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 2 - Worksite #1 - Field Visit of Hand Tunneling 3rd Party Project
Date & time of visit: 2021-11-03 08:00
The planned 3rd party project consisted of a tunnel to be dug by hand northbound (entry point south and exit point north of the right-of-way) under TCPL Line 100-2 and Line 100-1 for the installation of a 3rd party waterline. This trenchless construction method required that a 4-feet diameter steel casing be advanced through the tunnel, where workers hand-excavated soil material at the tunnel face while excavated soil was removed from the tunnel by a cart system.The CER IOs accompanied TC Energy representatives and 3rd party project Site Supervisor onto the worksite. The work being performed at the time of the field visit was hand tunnelling under the RoW (northbound). CER IOs were informed that the tunnel face at that time was between Line 100-2 and Line 100-1:
Compliance tool used: No compliance tool used
Observation 3 - Worksite #2 - Field Visit of Temporary Ramp (Gravel Access Road) Construction
Date & time of visit: 2021-11-03 10:00
The CER IOs accompanied TC Energy representatives to an active construction site where a 3rd party contractor was building a temporary gravel ramp on top of the TCPL right-of-way (RoW) to allow access for the subsequent construction of a storm management pond south of the RoW. The gravel ramp was almost completely built at the time of the inspection:
Observation 4 - Location of Previous Unauthorized Activity
Date & time of visit: 2021-11-04 11:00
CER IOs accompanied TC Energy representatives to the site of a recent unauthorized activity which was discoverd by the pipeline company in August 2021. Upon arrival at the site of the unauthorized activity, CER IOs observed evidence of a narrow trench where a silt fence had been installed as well as signs of grading and removal of earth cover on the RoW (but not directly over the pipe). The silt fence was installed along the RoW at that time. The TC Energy representatives indicated that they were present for the relocation of the silt fence and for the earth work on the RoW and confirmed that the depth of cover directly over the pipe was not affected.This unauthorized activity (or DPR contravention) is being reviewed under a separate CER process (CER File DPR2021-204).
Observation 5 - Line Locate for Ground Disturbance within the Prescribed Area
Date & time of visit: 2021-11-04 11:30
CER IOs accompanied TC Energy representatives responding to a locate request that was received the day before for ground disturbance to be conducted outside of the ROW but within the prescribed area:
Observation 6 - Follow-up on CV2122-251 - Document Control
Date & time of visit: 2021-11-03 07:30
During the opening meeting, CER IO’s followed up with TC Energy’s Notice of Non-compliance - Document Control issued for CV2021-251. TC Energy field staff provided TC Energy’s response for IO’s review with TC Energy’s commitment to have the updated documents and review that reflect the CER regulatory requirements pursuant to the OPR s.6.5 (o) initiated by the end of November 2021 with an estimated publish date of January 2022.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program