Compliance Verification Activity Report: CV2122-383 - Commandité gestion energy windmill DREAM Québec inc., Zibi Community Utility

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2122-383
Start date: 2022-03-08
End date: 2022-03-11

Team:

Regulated company: Commandité gestion energy windmill DREAM Québec inc., Zibi Community Utility

Operating company: Zibi Community Utility (Zibi/Windmill)

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

<span style="font-size:11pt"><span style="font-family:Calibri,sans-serif">The Canada Energy Regulator (CER or Regulator) will be conducting a Compliance Verification Activity (CVA) with field inspections of Commandit&eacute; gestion energy windmill DREAM Qu&eacute;bec inc. (Windmill/Zibi) operating and / or abandoned Pipelines and associated facilities and workplaces. &nbsp;&nbsp;</span></span><br /> <br /> <span style="font-size:11pt"><span style="font-family:Calibri,sans-serif">The purpose of these inspections is to verify compliance with:</span></span> <ul> <li><span style="font-size:11pt"><span style="font-family:Calibri,sans-serif">the<em> Canadian Energy Regulator Act</em>; </span></span></li> <li><span style="font-size:11pt"><span style="font-family:Calibri,sans-serif">Relevant Regulatory instruments such as Certificate(s), Order(s) (as amended); </span></span></li> <li><span style="font-size:11pt"><span style="font-family:Calibri,sans-serif">Any other relevant plans, manuals, and procedures, for the operations of the pipelines(s); </span></span></li> <li><span style="font-size:11pt"><span style="font-family:Calibri,sans-serif">Reports and &nbsp;filings from Windmill/Zibi on file with the Regulator; and</span></span></li> <li><span style="font-size:11.0pt"><span style="font-family:&quot;Calibri&quot;,sans-serif">Follow-up to CV2122-332. </span></span></li> </ul>

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Observations (no outstanding follow-up required)

Observation 1 - CV2122-383 - Field Inspcetion Zibi/Windmill Pipelines - General Observations

Date & time of visit: 2022-03-10 13:30

Discipline: Administrative

Categories:

Facility:

Observations:

Context / Background

On 28 September 2018 the Board issued Order MO-071-2018 (Deactivation Order) the effect of which was to approve the deactivation of four (4) pipelines as described in Schedule A of the Deactivation Order for pipelines regulated under Certificate CPTC-1983-2 (as amended), and Order 1995-P-35 (as amended) which further describes those regulated pipelines.

On 20 July 2018 Zibi filed with the Board its Review of Abandonment Cost Estimates (ACE).

On 25 June 2020 Zibi/Windmill requested leave from the Commission to Abandon pipelines regulated under the Deactivation Order.

On 23 October 2020 the Commission issued Order ZO-005-2020 (Abandonment Order) granting leave to abandon the four (4) deactivated pipelines and associated facilities under the Deactivation Order.

On 22 February 2021, the Commission issued Order XC-001-2021 (Zibi Project or the Order) the effect of which was to approve the construction of six (6) new pipelines outlined in Schedule A of the Order.

On 2 February 2022, the Commission granted a partial Leave to Open the Zibi Project and Issued Order CPLO-001-2022 (Partial Leave to Open) for two (2) of the pipelines (Medium Temperature Service Lines) associated with the Zibi Project, which were placed into service shortly thereafter.

On 2 March 2022, Zibi/Windmill requested that the CER return the Letter of Credit associated stating it had decommissioned and abandoned all pipes in accordance with the Abandonment Order).  

Operations – Field Observations


Abandonment – Field Observations
New Construction / Operating Pipelines

Compliance tool used: No compliance tool used

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program