Compliance verification activity type: Field Inspection
Team:
Regulated company: NOVA Gas Transmission Ltd.
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
Unannounced safety inspection of NGTL Groundbirch Mainline Loop Project (Sunrise section): The Project is located approximately 18 km northwest of Dawson Creek, British Columbia and consists of roughly 24 km of NPS 42. Verify implementation of the CSM and Kiskatinaw River HDD Execution Plan. Assess execution of work per applicable procedures and documented work practices.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Horizontal Directional Drilling (HDD) operations
Date & time of visit: 2022-11-29 09:30
Discipline: Safety Management
Categories:
Facility:
Observations:
Horizontal Directional Drilling (HDD) Rig 11 and Rig 5.
Compliance tool used: No compliance tool used
Observation 2 - Contractor Oversight - Safety
Date & time of visit: 2022-11-30 15:30
Summary
CER Inspection Officers (IOs) and Indigenous Monitors (IMs) performed an unannounced safety inspection of the NGTL Groundbirch Mainline Loop Sunrise Section. Work scopes inspected included the Kiskatinaw River HDD crossing, sandblasting, coating, and welding/tie-ins.
The inspection results demonstrate that NGTL is inspecting construction work daily and is making efforts to ensure work is completed per the construction safety manual. Despite this, IOs observed deficiencies in NGTL's inspection of coating operations (see Inspection Officer Order VAR-001-DJM-001-2022).
Field Observations
General
HDD
Tie-in
Observation 3 - Communication between Projects (CER Incidents 2022-147 and 2022-149)
Through discussions with the NGTL Construction Manager, Safety Lead, and Welding Inspector, CER Inspection Officer is satisfied that NGTL has communicated the circumstances and initial lessons learned from two incidents that occurred on NGTL projects in August 2022 (CER Incident Numbers INC2022-147 and INC2022-149).
Observation 4 - CNC 1 - Access to CSM
Date & time of visit: 2022-11-29 10:30
CER Inspection Officer requested a copy of the safety management plan and P/SSSP from NGTL's HDD Inspector. The document(s) were not immediately available.
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Ensure the relevant parts of the construction safety manual are available at the HDD construction site.
Due date: 2022-11-29
Date closed: 2022-11-29 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 5 - Inspection Officer Order VAR-001-DJM-001-2022 - Coating
Date & time of visit: 2022-11-29 11:30
NNC -1 - Mainline coating operations
Compliance tool used: Inspection Officer Order (IOO)
Specified Measures and Corrective Actions. 1. Cease the use of the pipeline spray-coating application system, provided by CRC- Evans, until a method of competent construction inspection, through the utilization of training, knowledge, and expertise, of the components, the use, and operation of the coating system, can be demonstrated to the Inspection Officer. Specified Measures and Corrective Actions 2. Provide assurance that those assigned the responsibility of General, Safety or Coating inspection, on behalf of NGTL, can demonstrate compliance with WHMIS requirements (as required by Condition 2 of Order XG-029-2019 and the Construction Safety Manual). Specified Measures and Corrective Actions 3. Provide to the Inspection Officer for review, an assessment completed by NGTL to identify the regulatory and legal requirements to safely manage Methyl Ethyl Ketone liquid, in line with Canada Energy Regulator Onshore Pipeline Regulations 6.5(1)(g) and 6.5(1)(h); and explain which requirements apply, and how they are implemented within the NGTL Management System. Specified Measures and Corrective Actions 4. Demonstrate that NGTL has reviewed the applicability of Management of Change (MOC), or a Hazard Analysis, of the CRC-Evans spray coating system, and provide to the Inspection Officer for review a summary of the key safety hazards and the management controls for MEK and other pipeline coating chemicals. Specified Measures and Corrective Actions 5. Provide a Corrective and Preventative Action Plan, noting systemic actions that will prevent recurrence, and detailing time to completion of Specified Measures 2, 3, & 4, to the Inspection Officer for review. Specified Measures and Corrective Actions 6. With regard to the details noted in this Observation, review and provide information related to items #3 - #12, and what if any measures have been taken. Specified Measures and Corrective Actions. 7. Provide a copy of the latest version, of an NGTL Coating Inspector's required training, time of minimum practice and experience, inclusive to job roles and responsibilities.
Due date: 2023-01-13
Date closed: 2023-02-17 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 6 - IM Observations - Lac Ste. Anne Métis Community Association
Date & time of visit: 2022-12-15 12:00
Discipline: Indigenous Monitoring
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program