Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Trans Mountain Pipeline ULC
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
TMX Burnaby & Westridge Terminal including tunnel boring activities. Verify effective implementation of construction safety manual and project specific safety plans including contractor oversight, implementation and oversight of the commitments made in condition 26 filing(s). Verify corrective actions from high potential near miss (incident 963, 14 Apr 2021) have been implemented on barges.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Day 1 (Sept 14)- General Observations- Westridge Marine Terminal
Date & time of visit: 2021-09-14 07:30
Discipline: Safety Management
Categories:
Facility:
Observations:
Tunnel Boring Machine
Compliance tool used: No compliance tool used
Observation 2 - Day 2 (Sept 15)- General Observations- Burnaby Terminal
Date & time of visit: 2021-09-15 07:30
Opening Meeting and Orientation
Observation 3 - Day 3 (Sept 16)- General Observations- Burnaby Terminal
Date & time of visit: 2021-09-16 06:00
Observation 4 - CNC - 1 - Covid-19 Prevention and Protection
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Update the site specific visitor orientation to reflect current BC Ministry of Health public health orders.
Due date: 2021-09-23
Date closed: 2021-09-20 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 5 - NNC - 1 - Compressed Breathing Air System and certification of Breathing Air Quality
Date & time of visit: 2021-09-15 10:01
Notice Non-Compliance (NNC) - 1
Compliance tool used: Notice of Non-compliance (NNC)
Provide to the Inspection Officer for review, a corrective action plan to address the Non-Compliance for compressed breathing air systems, worker fit-test programs, and equipment inspections.
Due date: 2021-09-17
Date closed: 2021-09-17 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 6 - CNC - 2 - Hearing Protection PPE
Date & time of visit: 2021-09-14 11:45
CNC - 2 - Hearing Protection
Ensure all workers exposed to levels of noise at the work site are abiding by the posted signage and requirements to use hearing protection.
Due date: 2021-09-14
Date closed: 2021-09-15 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program