Compliance verification activity type: Field Inspection
Team:
Regulated company: Many Islands Pipe Lines (Canada) Limited
Operating company: Many Islands Pipe Lines (Canada) Limited
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Operations Inspection of the Many Islands Pipe Lines (Canada) Limited's Macklin Compressor Station.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Inspection Observations
Date & time of visit: 2023-11-23 08:40
Discipline: Integrity Management
Categories:
Facility:
Observations:
CER inspectors’ observations and related discussions between CER inspectors and Many Islands representatives are summarized as follows:
Compliance tool used: No compliance tool used
Observation 2 - Notice of Non-Compliance NNC 1 - Lubrication Oil Storage in the Compressor Unit 3 Building
There was a barrel/tank of engine lube oil stored in the compressor unit 3 building at the time of the inspection. Many Islands representatives recognized that the lubricant quantities were greater than those required for everyday use.
Compliance tool used: Notice of Non-compliance (NNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Many Islands was asked to remove any extra quantity of lubricants from the compressor unit buildings (as applicable) to comply with the requirements of CSA Z662, Clause 10.9.1.5. On 29 November 2023, following the inspection, Many Islands representatives confirmed by email that the oil storage tank was removed from the compressor unit building on 27 November 2023.
Due date: 2024-01-19
Date closed: 2024-01-18 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - Notice of Non-Compliance NNC 2 - Maximum Pressure for Unit Engine Fuel Gaz (follow-up for IR No 3)
Date & time of visit: 2023-11-23 11:00
In response to CER Information Request IR No 3, Many Islands stated that “the role of this PSV-A#-5102 is to provide over-pressure protection of the engine. Upon subsequent review of manufacturers literature, we agree that we need to implement a pressure protection solution that would protect the weakest component and the engine ie 75 psig (see attached document). We will expect to implement this corrective action at Macklin before Fall 2024. This corrective action will be applied to all MIPL facilities as required.” CER inspectors are of the view that the current set up of the pressure control and overpressure protection system for the fuel gas entering the Macklin Stations’ compressor unit engines does not meet the requirements of CSA Z662, Clauses 4.14.2.10 d) and 4.18.1.2. MIPL committed to implement their corrective action at Macklin Station before Fall 2024 (i.e., to install pressure protection solutions that would limit the unit engines’ fuel gas pressure at 75 psig). In addition, this corrective action will be applied to all MIPL facilities as required.
Following MIPL’s response to IR No 3, CER inspectors conducted further discussions with MIPL representatives. As the results, MIPL committed to complete the corrective action as follows:
Due date: 2024-09-30
Date closed: 2024-12-23 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Observation 4 - Notice of Non-Compliance NNC 3 - Corrosion Inspection Procedure (follow-up for IR No 5)
In response to CER Information Request IR No 5, MIPL stated that its “Plant Integrity Management Program was recently merged into a single overarching Integrity Management Program. During this process, some content within the original program was identified as being more suitability contained within a procedure, or other document types. Details relevant to the procedure for external piping corrosion inspection requested by the CER are included within this content. Along with supplemental information, these details will be incorporated into a new procedure(s) meeting the requirements of CSA Z662-23 10.9.1.3. A corrective action plan for this work is in place to ensure publication of this document by September 30, 2024.” CER inspectors are of the view that MIPL did not demonstrate compliance with CSA Z 662, Clause 10.9.1.3 regarding the Macklin Station’s corrosion inspection procedure.
Following MIPL’s response to IR No 5, CER inspectors conducted further discussions with MIPL representatives. During that meeting, MIPL committed to complete its station corrosion inspection procedure (that meets the requirements of CSA Z662) and submit a copy to the CER by 30 June 2024.
Due date: 2024-06-30
Observation 5 - Notice of Non-Compliance NNC 4 - Pressure Vessel Inspection Procedure (follow-up for IR No 6)
In response to CER Information Request IR No 6, Many Islands stated that “MIPL’s Plant Integrity Management Program was recently merged into a single overarching Integrity Management Program. During this process, some content within the original program was identified as being more suitability contained within a procedure, or other document types. Details relevant to the procedure for pressure vessel inspection requested by the CER are included within this content. Along with supplemental information, these details will be incorporated into a new procedure(s) meeting the requirements of CSA Z662-23 clauses 10.9.2.8 and 10.3.2.5. A corrective action plan for this work is in place to ensure publication of this document by September 30, 2024.” CER inspectors are of the view that MIPL did not demonstrate compliance with Clauses 10.9.2.8 and 10.3.2.5 of CSA Z662 regarding the Macklin Station’s pressure vessels inspection procedure.
Following MIPL’s response to IR No 6, CER inspectors conducted further discussions with MIPL representatives. MIPL committed to complete its pressure vessel inspection procedure (that meets the requirements of CSA Z662) and submit a copy to the CER by 30 June 2024.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program