Compliance Verification Activity Report: CV2324-066 - Many Islands Pipe Lines (Canada) Limited

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2324-066
Start date: 2023-11-22
End date: 2023-11-23

Team:

Regulated company: Many Islands Pipe Lines (Canada) Limited

Operating company: Many Islands Pipe Lines (Canada) Limited

Province(s) / Territory(s):

Discipline(s):

Rationale and scope:

Operations Inspection of the Many Islands Pipe Lines (Canada) Limited's Macklin Compressor Station.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - Inspection Observations

Date & time of visit: 2023-11-23 08:40

Discipline: Integrity Management

Categories:

Facility:

Observations:

CER inspectors’ observations and related discussions between CER inspectors and Many Islands representatives are summarized as follows:

[Many Islands: please confirm/correct these temperatures and their actions as stated above]

Compliance tool used: No compliance tool used

Observation 2 - Notice of Non-Compliance NNC 1 - Lubrication Oil Storage in the Compressor Unit 3 Building

Date & time of visit: 2023-11-23 08:40

Discipline: Integrity Management

Categories:

Facility:

Observations:

There was a barrel/tank of engine lube oil stored in the compressor unit 3 building at the time of the inspection. Many Islands representatives recognized that the lubricant quantities were greater than those required for everyday use.
 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Many Islands was asked to remove any extra quantity of lubricants from the compressor unit buildings (as applicable) to comply with the requirements of CSA Z662, Clause 10.9.1.5.

On 29 November 2023, following the inspection, Many Islands representatives confirmed by email that the oil storage tank was removed from the compressor unit building on 27 November 2023.
 

Due date: 2024-01-19

Date closed: 2024-01-18
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 3 - Notice of Non-Compliance NNC 2 - Maximum Pressure for Unit Engine Fuel Gaz (follow-up for IR No 3)

Date & time of visit: 2023-11-23 11:00

Discipline: Integrity Management

Categories:

Facility:

Observations:

In response to CER Information Request IR No 3, Many Islands stated that “the role of this PSV-A#-5102 is to provide over-pressure protection of the engine. Upon subsequent review of manufacturers literature, we agree that we need to implement a pressure protection solution that would protect the weakest component and the engine ie 75 psig (see attached document). We will expect to implement this corrective action at Macklin before Fall 2024. This corrective action will be applied to all MIPL facilities as required.”

CER inspectors are of the view that the current set up of the pressure control and overpressure protection system for the fuel gas entering the Macklin Stations’ compressor unit engines does not meet the requirements of CSA Z662, Clauses 4.14.2.10 d) and 4.18.1.2. MIPL committed to implement their corrective action at Macklin Station before Fall 2024 (i.e., to install pressure protection solutions that would limit the unit engines’ fuel gas pressure at 75 psig). In addition, this corrective action will be applied to all MIPL facilities as required.
 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Following MIPL’s response to IR No 3, CER inspectors conducted further discussions with MIPL representatives. As the results, MIPL committed to complete the corrective action as follows:
 

  1. For the Macklin Station: MIPL will complete the corrective action to meet the requirements of CSA Z662. In addition, MIPL will submit a confirmation (including a summary of the completed action) to the CER by 30 April 2024; and
  2. For other MIPL facilities MIPL will complete the corrective action to meet the requirements of CSA Z662. MIPL will also provide the list of these facilities and the completion confirmation (including a summary of the completed action) by 30 September 2024.

Due date: 2024-09-30

Date closed: 2024-12-23
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 4 - Notice of Non-Compliance NNC 3 - Corrosion Inspection Procedure (follow-up for IR No 5)

Date & time of visit: 2023-11-23 11:00

Discipline: Integrity Management

Categories:

Facility:

Observations:

In response to CER Information Request IR No 5, MIPL stated that its “Plant Integrity Management Program was recently merged into a single overarching Integrity Management Program. During this process, some content within the original program was identified as being more suitability contained within a procedure, or other document types. Details relevant to the procedure for external piping corrosion inspection requested by the CER are included within this content. Along with supplemental information, these details will be incorporated into a new procedure(s) meeting the requirements of CSA Z662-23 10.9.1.3. A corrective action plan for this work is in place to ensure publication of this document by September 30, 2024.”

CER inspectors are of the view that MIPL did not demonstrate compliance with CSA Z 662, Clause 10.9.1.3 regarding the Macklin Station’s corrosion inspection procedure.
 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Following MIPL’s response to IR No 5, CER inspectors conducted further discussions with MIPL representatives. During that meeting, MIPL committed to complete its station corrosion inspection procedure (that meets the requirements of CSA Z662) and submit a copy to the CER by 30 June 2024.
 

Due date: 2024-06-30

Date closed: 2024-12-23
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 5 - Notice of Non-Compliance NNC 4 - Pressure Vessel Inspection Procedure (follow-up for IR No 6)

Date & time of visit: 2023-11-23 11:00

Discipline: Integrity Management

Categories:

Facility:

Observations:

In response to CER Information Request IR No 6, Many Islands stated that “MIPL’s Plant Integrity Management Program was recently merged into a single overarching Integrity Management Program. During this process, some content within the original program was identified as being more suitability contained within a procedure, or other document types. Details relevant to the procedure for pressure vessel inspection requested by the CER are included within this content. Along with supplemental information, these details will be incorporated into a new procedure(s) meeting the requirements of CSA Z662-23 clauses 10.9.2.8 and 10.3.2.5. A corrective action plan for this work is in place to ensure publication of this document by September 30, 2024.”

CER inspectors are of the view that MIPL did not demonstrate compliance with Clauses 10.9.2.8 and 10.3.2.5 of CSA Z662 regarding the Macklin Station’s pressure vessels inspection procedure.

 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Following MIPL’s response to IR No 6, CER inspectors conducted further discussions with MIPL representatives. MIPL committed to complete its pressure vessel inspection procedure (that meets the requirements of CSA Z662) and submit a copy to the CER by 30 June 2024.
 

Due date: 2024-06-30

Date closed: 2024-12-23
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program