Compliance Verification Activity Report: CV2324-138 - TransCanada Keystone Pipeline GP Ltd.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2324-138
Start date: 2023-10-10
End date: 2023-10-13

Team:

Regulated company: TransCanada Keystone Pipeline GP Ltd.

Operating company: TransCanada PipeLines Limited

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

Inspection of the Keystone XL Pipeline Project, Alberta segment and reclamation phase to date, including assessment of year One (1) Post Construction Environmental Monitoring Report. Due to the cancelation of this Project in 2021, most of the Right-of-Way was not fully disturbed beyond topsoil stripping and grading, with some areas where pipe had been laid in the ground and back-filled. Construction has halted with no assurances of being reactivated. The Project is actively being reclaimed. 

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Information Request

IR from CER (Information Request sent from CER to company)
IR1 - Documentation

Legislative Requirement : Onshore Pipeline Regulations (OPR) 2020-03-16

Sections of the Act

  • Onshore Pipeline Regulations (OPR) 2020-03-16
    • 48 A company shall develop, implement and maintain an environmental protection program that anticipates, prevents, manages and mitigates conditions that could adversely affect the environment.

Theme and Categories

Environmental Protection
  • General
    • General

Due Date : 2023-10-09

Review Response
Acceptable

Follow-up Action
None

Observations (no outstanding follow-up required)

Observation 1 - General Observations ROW

Date & time of visit: 2023-10-11 12:00

Discipline: Environmental Protection

Categories:

Facility:

Observations:

TC Energy submitted year 1 Post Construction Environmental Monitoring (PCEM) Report on or before January 31, 2023, as part of Condition 19 in compliance with the approved certificate. PCEM work to date showed progress with vegetation re-establishment, weed control (nuisance and noxious), wetland and watercourse recovery. Overall, most areas observed on Right-of-Way (ROW) are on track with first year reclamation expectations. The following general observations were made in field during the inspection of the TC Energy Keystone XL Pipeline from October 11 - 12, 2023.

Soils and Ground Disturbance 

Erosion and Sediment Controls Vegetation  Rare plants and Invasive Plant Controls  Watercourse Crossings 

- Loyalist Creek  - Monitor Creek Reclamation of HDD Sites 
Wetlands Bio-security  Heritage Resource Sites

Compliance tool used: No compliance tool used

Observation 2 - Corrected Non-Compliance - Erosion and Sediment Controls SSR

Date & time of visit: 2023-10-12 10:28

Discipline: Environmental Protection

Categories:

Facility:

Observations:

While observing reclamation success at the horizontal directional drilling (HDD) pad entry site, the inspecting officer observed and documented multiple locations within the area (KP 15+260 - 15+650) where erosion and sediment control (ESC) mitigation were deficient and requiring corrective actions. Observations include:


 

 

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Trans Canada Keystone is required to adequately maintain any mitigation still designated to be in effect on the project. The erosion and sediment controls at the reclaimed HDD site for the South Saskatchewan River, described as ineffective by the inspecting officer, must receive corrective maintenance to ensure the controls are fully effective until designated for removal. Once corrective actions have been completed, evidence will be provided to the CER to confirm completion. This includes time stamped photographs indicating the corrective actions were implemented in a timely manner.    

Due date: 2023-10-13

Date closed: 2023-10-31
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program