Compliance Verification Activity Report: CV1920-167 - Trans Mountain Pipeline ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1920-167
Start date: 2019-10-15
End date: 2019-10-16

Team:

Regulated company: Trans Mountain Pipeline ULC

Operating company: Trans Mountain Pipeline ULC

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

This inspection of the Burnaby and Westridge Terminals focused on environmental protection. The scope of the inspection includes works relating to the following: - Westridge Marine Terminal (OC-065, MO-042-2019). - Burnaby Terminal (OC-065, AO-002-XO-T260-010-2019). - Burnaby Terminal Facility Piping Relocations (XO-T260-003-2017). - Decommissioning of Facility Piping at Burnaby Terminal (MO-066-2018).

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Regulatory instrument number(s):

Observations (no outstanding follow-up required)

Observation 1 - Burnaby Terminal - General Observations

Date & time of visit: 2019-10-15 12:30

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 2 - Burnaby Terminal – Upper Road & Northwest Corner of the Terminal

Date & time of visit: 2019-10-15 12:58

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 3 - Burnaby Terminal – South Side Terminal

Date & time of visit: 2019-10-15 13:13

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 4 - Burnaby Terminal – Tertiary Containment Area (TCA)

Date & time of visit: 2019-10-16 08:26

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 5 - Westridge Marine Terminal - General Observations

Date & time of visit: 2019-10-16 11:37

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 6 - Westridge Marine Terminal - Watercourse Diversion Work

Date & time of visit: 2019-10-16 12:16

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 7 - Westridge Marine Terminal - Erosion Event

Date & time of visit: 2019-10-16 14:26

Discipline: Environmental Protection

Categories:

Facility:

Observations:

At the northern-most concrete swales, IOs and Company Reps discussed a recent environmental event on site that occurred within the weeks leading up to the inspection whereby a rain event caused a slope south of Tanks 201 and 202 to erode. Sediment laden water was released and made its way into the culvert and was discharged into the ocean. IOs observed turbidity curtains in the ocean surrounding the culvert outflow at the time of the inspection. Company stated it implemented additional mitigation when discovered and completed turbidity sampling inside and outside the turbidity curtain. Company stated that turbidity outside the curtain did not go above allowable levels immediately following the event.  IOs did not identify non-compliance with the Company’s response to this event.

Compliance tool used: No compliance tool used

Observation 8 - Westridge Marine Terminal - In-Water Works

Date & time of visit: 2019-10-16 15:54

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: No compliance tool used

Observation 9 - CNC # 1 – Fire Extinguishers

Date & time of visit: 2019-10-16 15:59

Discipline: Safety Management

Categories:

Facility:

Observations:

Officers observed three fire extinguishers with minor maintenance issues during the inspection.  At Burnaby Terminal, two fire extinguishers were observed to have an out-of-date monthly inspection tag.  At Westridge Marine Terminal, a fire extinguisher was observed to require charging. 
 

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

For each of the non-compliance extinguishers, Trans Mountain staff had the items removed for maintenance immediately, and photographs were sent to IOs confirming compliance.  
 

Due date: 2019-10-16

Date closed: 2019-10-30
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 10 - NNC # 1 – Spill Notification Contacts

Date & time of visit: 2019-10-16 08:27

Discipline: Environmental Protection

Categories:

Facility:

Observations:

IOs called the spill notification contact numbers for the Burnaby Terminal and found the posted phone number of the Environmental Manager to be out of service.  The contact numbers were observed to be posted on signage on trailers and on laminated cards within spill kits. When the Company provided updated contact information cards to the Officers during the inspection, IOs found that the contact information for the Construction Manager was also out of service.

During the inspection, Trans Mountain representatives discussed internal procedures, indicating that radio contact was the in-use and optimal internal communication method.  Photographs were sent to inspectors indicating the posted phone number issue was corrected.  In addition, an updated Burnaby Terminal Environmental Incident Response and Reporting Protocol document was sent to inspectors, indicating the immediate action within the reporting protocol to be “Call Safety/Environmental Radio Channel” in the event of an incident. 
 

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide:

Officers have reviewed the company’s response to the NNC #1 corrective action, including the Spill Kit Inventory Focus Inspection.  Officers have determined that the bullet #1 of the corrective action, is satisfied, however the corrective action provided by the company does not satisfy bullet #2. 

For convenience and clarity, bullet # 2 is copied here: “What the Company has been done (or what the Company plans to do) to ensure that this issue will not reoccur on other Project sites.” As the corrective action in bullet #2 is yet unsatisfied, NNC #1 remains open at this time (and the company remains out of compliance).  Officers note the non-compliance was found at multiple location, indicating the issue may be systemic in nature, which is why bullet #2 is included in the corrective action. 

In order to facilitate a sufficient response to NNC #1, bullet #2, an extension has been granted until on or before Jan. 17, 2020, noting compliance cannot be confirmed until a sufficient response has been received. 
 

Due date: 2020-01-17

Date closed: 2020-02-11
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 11 - CNC # 2 – Waste Segregation on the Barge

Date & time of visit: 2019-10-16 15:55

Discipline: Environmental Protection

Categories:

Facility:

Observations:

On a barge at Westridge Marine Terminal, Officers observed incorrectly segregated wastes in metal waste bins on the deck.  For example, garbage was observed in the waste bins labelled "cardboard" and "construction wood waste", and wood waste was in the bin labelled "construction debris".
 

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Confirm with photographs that the waste has been correcetly segregated.
 

Due date: 2019-10-16

Date closed: 2019-10-30
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 12 - IR # 1 – Wildlife Encounter Contingency Plan

Date & time of visit: 2019-10-16 12:17

Discipline: Environmental Protection

Categories:

Facility:

Observations:

During the inspection, IOs inquired regarding wildlife encounters with respect to the marine perimeter security fence (fence).  Trans Mountain staff indicated that on the day of the inspection (October 16, 2019) a seagull had encountered the fence at the Westridge Terminal location.  Officers and Trans Mountain representatives discussed the specific circumstances of the encounter, protocols and next steps by the company, as well as mitigation measures in place to prevent bird encounters with the perimeter security fence.  At the closing meeting, Trans Mountain representatives confirmed that the bird was deceased, and that the Canadian Wildlife Service (CWS) would be notified.
 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide a copy of all follow-up documentation specific to this incident, including but not limited to:

Provide a written explanation of any additional mitigations implemented to prevent such an event from reoccurring in the future. 
 

Due date: 2019-11-15

Date closed: 2019-12-06
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 13 - IR # 2 – Spot Spill at Westridge Marine Terminal

Date & time of visit: 2019-10-16 15:55

Discipline: Environmental Protection

Categories:

Facility:

Observations:

During the inspection, IOs observed a sheen that indicated a spot spill on rig matting, near the work area for a tree maintenance crew that included use of a chain saw.  TransMountain representatives were observed to follow the Spill Contingency Plan in response to the issue.  Immediate actions included the use of spill kit materials to clean up the spill. 
 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide a copy of documentation created in response to this spill. 
 

Due date: 2019-11-15

Date closed: 2019-12-03
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 14 - IR # 3 – Pilings in the Westridge Marine Terminal

Date & time of visit: 2019-10-16 15:55

Discipline: Environmental Protection

Categories:

Facility:

Observations:

During the inspection, Officers and Trans Mountain representatives discussed an area of wooden marine pilings (dock supports) suspected of historically containing creosote.  Officers understand that planned future work this area will require these pilings be removed from the marine environment. 

Trans Mountain’s Condition 46: Contamination Identification and Assessment Plan approved for WMT (A82636-2) outlines that WMT had a Desktop Phase I ESA completed in 2013 on the site and WMT was classified as a moderate risk site. Although the Plan states that WMT was classified as moderate risk because of a historic spill, the historic dock was present at the time the Desktop Phase I ESAs were completed for the WMT. Further, the Condition 46 filing states in Section 6.2 that “Should impacts be identified on Trans Mountain properties or as a result of Trans Mountain activities, Trans Mountain will implement appropriate mitigation and remediation measures in accordance with the NEB Remediation Process Guide (2011).”

The NEB Remediation Process Guide (2011) states that “a company may also encounter contamination that: a. is not liquid but may cause an adverse environmental effect; b. occurred because of a previous incident; or c. is an accumulation over time.” Further, the Guide states the “NEB expects notification of the contamination by writing to the Secretary of the Board as soon as practicable” and outlines requirements of the notification.
 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide:

Due date: 2019-11-15

Date closed: 2020-02-02
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 15 - IR # 4 - Fire Suppressants Storage

Date & time of visit: 2019-10-15 12:59

Discipline: Environmental Protection

Categories:

Facility:

Observations:

During the inspection, IOs observed five 55 gallon containers outside of North Fire Building not located within secondary containment. Company Reps stated that the drums are operational and fire suppressants and not related to TMEP or B.Mod. work activities. IOs requested MSDS for the chemicals. MSDS sheets state the chemicals are “biodegradable” and “may cause harm to aquatic life due to oxygen depletion”. 
Later in the inspection, the Company Rep stated that they had put the drums in secondary containment as good measure even though it is not a requirement as they are operational materials. Photo confirmation of the secondary containment showed that each drum was located in the plastic containers that were being used as equipment drip trays at other places on site.
Chemicals were located within 100m of the NW pond on site, as well as watercourses BC-785i and BC-785j.

 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide:

Due date: 2019-11-15

Date closed: 2019-12-06
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 16 - IR # 5 - Marine Wildlife Monitoring

Date & time of visit: 2019-10-16 12:55

Discipline: Environmental Protection

Categories:

Facility:

Observations:

While discussing the marine mammal monitoring during the inspection, which occurs during pile driving, the Company was unable to answer how it verified the subcontractors were qualified and trained to conduct the visual monitoring of marine mammals.
 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

  1. Provide documentation demonstrating how the Company verifies the visual monitoring is conducted by “trained, qualified personnel”.
  2. Provide a copy of the Marine Mammal Monitoring standard operating procedure used by the Company and its contractors at Westridge Marine Terminal.

Due date: 2019-11-15

Date closed: 2019-12-03
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program