Compliance Verification Activity Report: CV2223-149 - Trans-Northern Pipelines Inc.

Overview

Compliance verification activity type: Field Inspection

Activity #: CV2223-149
Start date: 2022-07-19
End date: 2022-07-21

Team:

Regulated company: Trans-Northern Pipelines Inc.

Operating company: Trans-Northern Pipelines Inc.

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

[Process Safety - Field verification follow-up to HAZOP action item implementation; assessing the completion of preventive maintenance (inspection and testing) activities on safety systems and safeguards (i.e., pressure relieving devices; emergency, fire, gas and release protection systems; sensors, alarms and interlocks) per prescribed frequencies under CSA Z662 and company programs; Completeness and accuracy of records (e.g., P&IDs, equipment inventory, labelling and consistency with facility operating/field assets etc.)]

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - General observations

Date & time of visit: 2022-07-21 16:00

Discipline: Safety Management

Categories:

Facility:

Observations:

Farrans Point Terminal (19 July 2022)​​​​​


Maitland Station (20 July 2022)

Iroquois Station (20 July 2022)


Integrity Digs at MP 112.69 and MP 113.57 (21 July 2022)

Prescott Block Valve (21 July 2022)

Other

Compliance tool used: No compliance tool used

Observation 2 - CNC 1 Farrans Point valve position indicator

Date & time of visit: 2022-07-19 13:30

Discipline: Safety Management

Categories:

Facility:

Observations:

The sight glass on the west pig launch discharge valve (V575) was stained with product and therefore blocking the visibility of the valve open/closed position. 

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Ensure the open and closed position indicator on V575 is clearly visible.

Due date: 2022-07-21

Date closed: 2022-07-21
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 3 - Warning signage on pump house buildings

Date & time of visit: 2022-07-20 13:00

Discipline: Safety Management

Categories:

Facility:

Observations:

IOs observed the entrances to pump house buildings at Farran's Point, Maitland station, and Iroquois station do not have hazard or toxic substance warning signs. Piping in the pump houses contains low vapour pressure hydrocarbons including diesel, gasoline, and distillate.
See IR#6

Compliance tool used: No compliance tool used

Observation 4 - NNC 2 - Lockout & energy isolation

Date & time of visit: 2022-07-20 11:30

Discipline: Safety Management

Categories:

Facility:

Observations:

IO learned through discussion with a TNPI supervisor that bleeds are not secured in the open position when performing energy isolation contrary to the company's internal Lockout and Energy Isolation Procedure, Rev. 7. This practice was also confirmed by another company supervisor. Both supervisors were unaware of the company's requirement for securing bleeds in the open position.

Compliance tool used: Notice of Non-compliance (NNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide a corrective action plan with target completion dates to ensure all workers involved in energy isolation and lockout are trained on the company's internal procedure(s), specifically regarding bleeds.

Due date: 2022-08-12

Date closed: 2022-08-17
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

There are no observations with outstanding follow-up

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program

Observation 5 - Information caviardée conformément au paragraphe 144(5) du Code canadien du travail

This information has been redacted pursuant to Section 144(5) of the Canada Labour Code