Compliance verification activity type: Field Inspection
Team:
Regulated company: NOVA Gas Transmission Ltd.
Operating company: TransCanada PipeLines Limited
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
NGTL 2021 - Karr Section: The Karr Section consists of approximately 57 km of NPS 48 pipeline, mainline block valves, associated crossover assemblies and launcher/receiver assemblies. The Karr Section begins at NW 28-63-01 W6M and ends at NE 26-67-05 W6M. Assess field implementation of construction safety manual and project specific safety plans for ongoing construction activities; worker tasks including identification of hazards and appropriate controls relevant to the job tasks via hazard assessments; company implementation COVID-19 safety protocols; company oversight of contractors - training & competence, monitoring, supervision and accountability; assess execution of work per applicable procedures and documented work practices.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - IM Observations
Date & time of visit: 2021-09-22 09:00
Discipline: Indigenous Monitoring
Categories:
Facility:
Observations:
The following section contains independent observations made by an Indigenous Monitor who accompanied the Canadian Energy Regulator Inspection Team during this inspection, as part of the CER’s commitment to the NGTL's Indigenous Monitoring Program. They are reproduced and publicized within my report for greater transparency. They are not my conclusions but represent one source of information among others I have considered throughout the inspection along with my own direct observations and information received from the company.IMAC – Sucker Creek First Nation - SCFN Services – IM:Safety Inspection - September 21-24, 2021 CV2122-185 Grande Prairie area accompanied with CER and NGTL/Midwest Environmental Team
Compliance tool used: No compliance tool used
Observation 2 - General
Discipline: Safety Management
General
Compliance tool used: Information Request (IR)
Regulatory requirement:
Relevant section(s):
Company action required:
KARR – SMJV:Please provide the following:
Due date: 2021-10-21
Date closed: 2021-11-05 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 3 - CNC#1: Lack of adequate controls while working in proximity to open excavation
A worker was observed at KP 0.00 standing within 0.5m of an open excavation (greater than 2.5m in depth) without any means of protective measures in place to prevent falling into the excavation. The individual was working as a spotter for a second worker who was working within the excavation with a high pressure water wand from a VacTruck. According to company and contractor site personnel, the worker had previously worn a fall arrest harness while performing similar tasks but was not doing so at the time of the inspection. Once noted, the company took action to ensure the worker donned a fall arrest harness at the time of the inspection.
Compliance tool used: Corrected Non-compliance (CNC)
The issue was resolved to the satisfaction of the Inspection Officers at the time of the inspection. No further action is required.
Due date: 2021-09-22
Date closed: 2021-09-22 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program