Compliance Verification Activity Report: CV1920-155 - Trans Mountain Pipeline ULC

Overview

Compliance verification activity type: Field Inspection

Activity #: CV1920-155
Start date: 2019-11-12
End date: 2019-11-15

Team:

Regulated company: Trans Mountain Pipeline ULC

Operating company: Trans Mountain Pipeline ULC (TransMountain)

Province(s) / Territory(s):

Discipline(s):

Related events:

Rationale and scope:

Environmental Program based inspection of the Trans Mountain Expansion Project (TMEP), Spread 2. In accordance to the CERs approach and Terms of Reference for the Indigenous Advisory and Monitoring Committee (IAMC), CER Officers, pursuant to subsection 102(5) of the Canadian Energy Regulator Act (CERA), will be accompanied by Indigenous Monitors (IMs). The purpose of these inspections is to verify compliance with the CERA, the National Energy Board Onshore Pipeline Regulations (OPR), referenced standards such as the CAN/CSA Z662 Oil and Gas Pipeline Systems, Certificate OC-065 and associated conditions, notably condition 72 (Pipeline Environmental Protection) and Condition 100 (Heritage Resources), Amending Order AO-001-XO-T260-007-201, Order OPL-002-2019, as well as other associated relevant Regulatory Instruments. The primary focus area for this Compliance Verification Activity (CVA)will be, but may not be limited to, Environmental Protection. Inspections will include verification of implementation of mitigation measures, commitments, and other information associated with Project Environmental Protection Plans (EPPs), and any other relevant plans, manuals, and procedures, as well as management plans. The scope of these inspections will include, but will not be limited to: Ongoing activities along Spread 2, Temporary Sites (Bone Yards, Construction Sites/Yards, Staging Areas), as well as Survey, Access, and Forestry Activities. Areas of interest include wildlife mitigation, wetland and watercourse crossings, waste management, storage and handling of hazardous materials, traditional land & resource use, heritage resource sites, invasive species management, and erosion and sediment controls while focusing on pre-clearing survey methods, delineation and staking activities occurring on the RoW.

Compliance tool(s) used:

Facility details

Facilities:

Regulatory requirements

Regulatory requirements that apply to this activity:

Observations (no outstanding follow-up required)

Observation 1 - Information caviardée conformément au paragraphe 144(5) du Code canadien du travail

This information has been redacted pursuant to Section 144(5) of the Canada Labour Code

Observation 2 - Meeting with TransMountain Representatives - TMEP Environmental Handbook

Date & time of visit: 2019-11-12 07:49

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Company Representatives provided a copy of, and reviewed with the CER Inspection Team, the TMEP Environmental Handbook. Company Representatives indicated this document is provided to all visitors on the TMEP following completion of visitors’ orientation.
Topics included but are not limited to:

Compliance tool used: No compliance tool used

Observation 3 - Clear Stream Energy Services (Pipe Yard) Yard B & Yard A

Date & time of visit: 2019-11-12 09:30

Discipline: Safety Management

Categories:

Facility:

Observations:

General

Yard BYard A

Compliance tool used: No compliance tool used

Observation 4 - TMEP Pipeline RoW – General Observations

Date & time of visit: 2019-11-13 16:30

Discipline: Environmental Protection

Categories:

Facility:

Observations:

KP244 to KP255

~KP 269+700 to 270+700~KP 273 + 900

Compliance tool used: No compliance tool used

Observation 5 - Meeting with TransMountain Representatives - Environment Inspectors (EIs)

Date & time of visit: 2019-11-14 07:20

Discipline: Environmental Protection

Categories:

Facility:

Observations:

NEB Inspection Team and TransMountain Representatives had discussions on several topics including:

Compliance tool used: No compliance tool used

Observation 6 - TMEP Pipeline RoW – General Observations

Date & time of visit: 2019-11-14 17:17

Discipline: Environmental Protection

Categories:

Facility:

Observations:

~KP 135+500 to ~ KP 136+600

~KP157+000 to ~KP 158+000~KP 175+000 to ~KP 74+000Little Brulé CreekUnnamed Creek / Tributary (West of AB114)Carrot Creek

Compliance tool used: No compliance tool used

Observation 7 - Corrected Non-Compliance (CNC) – CNC No.1 Pipeline Identification Signage – Unnamed Tributary (TMP RoW)

Date & time of visit: 2019-11-14 15:17

Discipline: Damage Prevention

Categories:

Facility:

Observations:

Along the existing and operating TransMountain Pipeline RoW, at an Unnamed Tributary identified on the TMEP as feature (AB 114), pipeline identification signage does not identify the current operating company and the emergency number is out of service.

Compliance tool used: Corrected Non-compliance (CNC)

Regulatory requirement:

Relevant section(s):

Company action required:

Install appropriate signage as required. 

Due date: 2019-11-15

Date closed: 2019-11-18
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 8 - IM Observation

Date & time of visit: 2019-11-15 08:00

Discipline: Indigenous Monitoring

Categories:

Facility:

Observations:

TMX-IMAC Environmental Inspection Report
Spread 2 Edson, Alberta
November 12-15, 2019
 
Edson Environmental inspection:
Observation focus: stated to be surveying and previous work done in the area.
 
November 12, 2019
 
Hotel Conference Room
Meeting:

End of meeting.

Compliance tool used: No compliance tool used

Observation 9 - IM Observation

Date & time of visit: 2019-11-15 08:00

Discipline: Indigenous Monitoring

Categories:

Facility:

Observations:

On November 12, we had an initial meeting to discuss the scope of work for the inspection. The following people from TMX:

CER IOS
IAMC IM
Chief Environmental Inspector 
Spread 2 Lead Environmental Inspector
H&S Lead Inspector
H&S Inspector 
 

During the meeting it was discussed that we would look at the pipe yard outside of Edson. We discussed the IAMC IMs concerns consisted of Carrot Creek and Little Brule Creek along with some accessible TLU sites. Some sites were not accessible due to the weather and ROW conditions. We were given traction aids as a safety measure to prevent and slips or trips. It was discussed what PPE we needed to be out on Row. 
 

Observation made during our inspection:


 

Compliance tool used: No compliance tool used

Observation 10 - Information Request (IR) - IR No.1 - Little Brule Creek - Existing Trans Mountain Pipeline RoW (TMP-RoW)

Date & time of visit: 2019-11-15 07:30

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

Provide a response outlining what operations and maintenance activities (O&M Activities) have occurred at the site; under what O&M Notification number was the Board (now Regulator) Notified of O&M Activities which have occurred in the vicinity of Little Brule Creek for the existing and operating TransMountain Pipeline RoW. Please provide a description of and details surrounding O&M Activities conducted and their timing. Provide available environmental monitoring / inspection report(s) of the site following ground disturbances or clean-up activities including the installation of erosion and sediment control measures at Little Brule Creek.  

Due date: 2019-11-21

Date closed: 2019-11-21
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observation 11 - Information Request (IR) IR No. 2 - Little Brule Creek - Existing Trans Mountain Pipeline RoW (TMP-RoW)

Date & time of visit: 2019-11-15 07:30

Discipline: Environmental Protection

Categories:

Facility:

Observations:

Approximately a dozen groundwater monitoring wells present along the northern edge of the Existing TMP RoW on the eastern side of Little Brule Creek. An ATCO Gas RoW is adjacent to TMP-RoW in the vicinity of these groundwater wells. 

Compliance tool used: Information Request (IR)

Regulatory requirement:

Relevant section(s):

Company action required:

A response providing additional information on the groundwater monitoring wells identified by the CER Inspection Team near Brule Creek located to the northern side to the TMP-RoW. In your response, please indicate if TransMountain is aware of their presence, their purpose, and if these are owned by TransMountain or owned and the responsibility of another party.

Due date: 2019-11-21

Date closed: 2019-11-21
Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.

Reason closed: Requirement met

Compliance achieved: Yes

Observations (company follow-up required)

Identified non-compliances to company plans or procedures are non-compliances either to:

- the condition of an authorization document that requires the implementation of that plan or procedure; or

- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program