Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company:
Province(s) / Territory(s):
Discipline(s):
Related events:
Rationale and scope:
TMX Spread 3/4A - Assess field implementation of the environmental protection plan and association resource specific plans for ongoing construction activities; verify mitigation measures at watercourse crossings, specifically adequacy of erosion and sediment control measures.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Regulatory instrument number(s):
IR from CER (Information Request sent from CER to company) IR No. 1 – Watercourse Crossing Checklist
Legislative Requirement : Project-specific Environmental Protection Plan (EPP)
Applicable Wording from Legislative Document 2. Ensure completion by the Contractor of the on-site checklist for pipeline and vehicle crossings provided in Appendix D for each classified watercourse and wetland prior to, during and following construction. These checklists will be approved by a QAES/QEP. Retain these checklists as a permanent record of pipeline watercourse and wetland crossing installation
Theme and Categories
Due Date : 2023-01-13
Review Response Acceptable
Follow-up Action None
Observation 1 - General Construction Observations
Date & time of visit: 2022-11-29 11:00
Discipline: Environmental Protection
Categories:
Facility:
Observations:
General observations:
Compliance tool used: No compliance tool used
Observation 2 - Watercourse Crossings
BC-275 Mad River Crossing KP 678+830
Observation 3 - CNC1- Failure to use provided washroom facilities
Date & time of visit: 2022-12-01 11:30
Discipline: Safety Management
At KP686+600 IAMC IM observed a contractor not using the toilet and instead urinating in the snow behind the portable toilet, and brought this to attention of CER IO. CER IO confirmed the non-compliance which was brought to the attention of company representatives. Trans Mountain issued a bulletin the next morning to remind crews of the requirement to use washroom facilities.
Compliance tool used: Corrected Non-compliance (CNC)
Regulatory requirement:
Relevant section(s):
Company action required:
Explain how Trans Mountain will prevent reoccurrence of this matter, and provide documentation that this has been completed.
Due date: 2022-12-02
Date closed: 2022-12-02 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Reason closed: Requirement met
Compliance achieved: Yes
Observation 4 - CNC2 - Missing Drip Catcher on Fuel Nozzle
Date & time of visit: 2022-11-29 11:22
CER IO inspected contractor truck #131042 and observed Diesel slip tank nozzle not installed within drip catcher receptacle. Trans Mountain personnel rectified the issue to the satisfaction of the IO and replaced nozzle in an appropriate manner.
CER IO brought the non-compliance to the attention of company representatives, and required the matter be rectified with an appropriate drip catching receptacle, and requested photographic evidence of completion.
Due date: 2022-11-29
Date closed: 2022-11-29 Note: the date closed is the date that the inspector completed their review of the company corrective actions for adequacy and determined that no further actions are required.
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program