Compliance verification activity type: Field Inspection
Team:
Regulated company: Trans Mountain Pipeline ULC
Operating company: Trans Mountain Pipeline ULC
Province(s) / Territory(s):
Discipline(s):
Rationale and scope:
Integrity inspection of Sumas terminal tank construction to verify compliance to the OPR, CSA Z662-19, CLC and OC-065.
Compliance tool(s) used:
Facilities:
Facility Types
Life-cycle Phases
Regulatory requirements that apply to this activity:
Observation 1 - Day 1
Date & time of visit: 2023-03-21 08:30
Discipline: Integrity Management
Categories:
Facility:
Observations:
Opening Meeting: CER Inspection Officers (IOs) and TMEP staff introduced each others’ roles at a roundtable. TMEP staff described the contracting structure of the project where KLTP is the main contractor overseeing the project and Ganotec, who is overseeing the tank construction, is a subcontractor to KLTP. HCBI supplied the tank material. CER IOs and TMEP Staff discussed the project organizational chart. TMEP Staff provided an overview of the construction work being undertaken, which included:
Compliance tool used: No compliance tool used
Observation 2 - Day 2
Date & time of visit: 2023-03-22 08:30
Orientation: CER IOs met with TMEP representatives, including the Joining Program Welding Specialist (JPWS) from UPI, the engineer of record for the Joining Program. There is one UPI JPWS for the facilities in the lower mainland (Burnaby, Westridge, and Sumas). The JPWS explained that UPI’s role in pipeline construction includes auditing both the TMEP and contractor’s welding inspectors, but for facilities, UPI only audits the contractors’ welding inspectors. TMEP explained that the UPI JPWS and the three qualified TMEP welding inspectors conduct oversight of the joining program for the Sumas terminal. CER IOs and TMEP Staff went over the documentation provided by the company:
Identified non-compliances to company plans or procedures are non-compliances either to:
- the condition of an authorization document that requires the implementation of that plan or procedure; or
- the relevant section of the regulations that requires implementation of that plan or procedure including those sections that require implementation of plans or procedures as a part of a Program